JSW Steel USA Ohio plant, also known as Wheeling Pittsburgh Steel (predecessor), is an electric arc furnace (EAF) steel plant operating in Mingo Junction, Ohio, United States.

Location

The map below shows the exact location of the plant in Mingo Junction, Ohio, United States:

Loading map...
  • Location: 1500 Commercial Avenue, Mingo Junction, Ohio 43938, United States
  • Coordinates (WGS 84): 40.314891, -80.605553 (exact)

Background

The JSW Steel USA Ohio plant was originally built in 1872 (then known as Wheeling Pittsburgh Steel). In 2018, JSW Steel bought the plant, which had been sitting idle for more than 10 years, for nearly $81 million, modernizing the facility with an EAF, slab caster and 80” hot rolling mill.[1][2]

In 2020, the Covid-19 pandemic caused the plant to suspend production in July 2020, a period of stasis which was used to upgrade equipment.[3] The plant's EAF was restarted in March 2021.[4]

Plant Details

Table 1: General Plant Details

Plant status Start date Workforce size
Operating[5] 2018[5] 160[6]

Table 2: Ownership and Parent Company Information

Parent company Parent company PermID Parent company GEM ID Owner Owner company PermID Owner company GEM ID
JSW Steel Ltd [100.0%] 4295872888 [100%] E100000001753 [53.2%]; E100001010147 [15%]; E100001010148 [11%]; E100001000520 [7.5%]; E100001000521 [5.9%]; E100001010037 [0.9%]; E100001010033 [0.8%]; E100001010034 [0.7%]; E100001010036 [0.6%]; E100001010035 [0.6%]; E100001001119 [0.6%] Jsw Steel USA Ohio Inc[5] 5052546618 E100001000527

Table 3: Process and Products

Steel product category Steel products Steel sector end users Main production equipment Detailed production equipment
finished rolled[7] hot rolled coils[7] energy; steel packaging; tools and machinery[7] EAF[5] 1 Tenova Consteel EAF (2019)[8]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status* Electric arc furnace steelmaking capacity Nominal crude steel capacity (total)
operating 1500 TTPA[9][8] 1500 TTPA[9][8]

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. JSW Steel USA, Ohio, JSW USA, Retrieved on: Aug. 17, 2020
  2. Coyne, Justine (2021-05-04). "JSW Ohio signs HRC tolling agreement with ATI". www.spglobal.com. Retrieved 2021-10-22.
  3. "Tenova New Consteel® EAF Started-Up at JSW Steel USA". Tenova. 2021-03-18. Retrieved 2021-10-22.{{cite web}}: CS1 maint: url-status (link)
  4. "JSW to restart Ohio EAF next week | Argus Media". www.argusmedia.com. 2021-03-05. Retrieved 2021-10-22.
  5. 5.0 5.1 5.2 5.3 https://jswsteel.us/mingo/. {{cite web}}: Missing or empty |title= (help)
  6. https://web.archive.org/web/20201030231700/https://www.thehindubusinessline.com/companies/jsw-steel-idles-us-plant-to-lay-off-160-employees/article32104192.ece. Archived from the original on 30 October 2020. {{cite web}}: Missing or empty |title= (help)
  7. 7.0 7.1 7.2 https://web.archive.org/web/20230921193032/https://jswsteel.us/hot-rolled-coil/. Archived from the original on 21 September 2023. {{cite web}}: Missing or empty |title= (help)
  8. 8.0 8.1 8.2 https://tenova.com/newsroom/latest-tenova/tenova-new-consteelr-eaf-started-jsw-steel-usa. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 https://www.argusmedia.com/en/news/2407716-jsw-steel-ohio-production-falls#:~:text=JSW%20previously%20said%20%22subdued%20marketan%20unknown%20amount%20of%20downtime. {{cite web}}: Missing or empty |title= (help)

Resources