Jincheng Fusheng Iron & Steel Co Ltd (山西晋钢智造科技有限公司) is a blast furnace-basic oxygen furnace (BF-BOF) steel plant operating in Jincheng, Shanxi, China.

Location

The map below shows the exact location of the plant in Jincheng, Shanxi, China:

Loading map...
  • Location: Bagong Town, Zezhou County, Jincheng City, Shanxi Province
  • Coordinates (WGS 84): 35.662985, 112.882395 (exact)

Background

The company plans to build a new 2×230m2 sintering machine, 2×180m2 sintering machine (technical transformation), 1.5 million tons of pellets, 2×1250m3 blast furnace, and 4×100t converter. The EIA report was approved in January 2021.[1]

In November 2019, the 2×1250m3 blast furnace started to build, and in October 2020, the 2×530m3 blast furnace retired.[2]The blast furnace stated to operate in 2021.[3]

Plant Details

Table 1: General Plant Details

Phase Plant status Announced date Construction date Start date Pre-retirement announcement date Idled date
Main plant Operating[4] 2002[5]
Expansion Operating[6] 2018[7] 2019-11-05[8] 2021[6]
Expansion Operating[6] 2018[7] 2019-11-05[8] 2021[6]
Closure Retired[7][9] 2018[7] 2020-10-09[9]

Table 2: Ownership and Parent Company Information

Phase Parent company Parent company GEM ID Owner Owner company GEM ID
Main plant Shanxi Jincheng Steel Holdings Group Co Ltd [60.0%]; persons [40.0%] E100000123261 [100%] Jincheng Fusheng Iron & Steel Co., Ltd.[4] E100000127056

Table 3: Process and Products

Phase Steel product category Steel products ISO 14001 Main production equipment Detailed production equipment
Main plant finished rolled[10] rebar, steel wire[10] yes[11] BF, BOF[12] 4 BOF (1x50-tonne, 3x80-tonne)[12][5]
Expansion finished rolled[10] rebar, steel wire[10] BF, BOF[13] 4 BOF (4x100-tonne)[13]
Expansion finished rolled[10] rebar, steel wire[10] BF, BOF[13] 4 BOF (4x100-tonne)[13]
Closure finished rolled[10] rebar, steel wire[10] BF, BOF[13] 4 BOF (1x50-tonne, 3x80-tonne)[13]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Basic oxygen furnace steelmaking capacity Nominal crude steel capacity (total)
Main plant operating
Expansion operating 2300 TTPA[14][15][14][15][14][15][14][15] 2300 TTPA[14][15][14][15][14][15][14][15]
Expansion construction 2300 TTPA[14][15][14][15][14][15][14][15] 2300 TTPA[14][15][14][15][14][15][14][15]
Closure retired 3760 TTPA[16][16][16][16] 3760 TTPA[16][16][16][16]

Table 5: Crude Iron Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Blast furnace capacity Nominal iron capacity (total)
Main plant operating 2480 TTPA[16][16] 2480 TTPA[16][16]
Expansion operating 2300 TTPA[13][13] 2300 TTPA[13][13]
Expansion construction [13][13] [13][13]
Closure retired 2786 TTPA[16][16][16][16] 2786 TTPA[16][16][16][16]

Blast Furnace Details

Table 6: Blast Furnace Details

Unit name Status Announced date Construction date Start date Retired date Current size Current capacity (ttpa) Decarbonization technology Most recent relining
unknown retired[17] unknown unknown unknown 2020-10[17] 530 m³[12] 620[16] unknown unknown
unknown retired[17] unknown unknown unknown 2020-10[17] 530 m³[12] 620[16] unknown unknown
unknown retired[7][9] unknown unknown 2009-04-01 00:00:00[18] unknown 680 m³[12] 773[16] unknown unknown
unknown retired[7][9] unknown unknown 2009-04-01 00:00:00[18] unknown 680 m³[12] 773[16] unknown unknown
unknown operating[12][5] unknown unknown 2010-02-01 00:00:00[18] 1380 m³[12] 1240[16] unknown unknown
unknown operating[12][5] unknown unknown 2011-12-01 00:00:00[18] 1380 m³[12] 1240[16] unknown unknown
unknown operating[6] 2018[19] 2019-11-01 00:00:00[18] 2021-05-10[6] 1250 m³[13] 1150[13] unknown unknown
unknown operating[18] 2018[19] 2019-11-01 00:00:00[18] unknown 1250 m³[13] 1150[13] unknown unknown

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. 总投资71亿!晋城福盛钢铁产能减量置换升级改造项目获批,山西省生态环境厅,February 5, 2021
  2. 发展大事记,晋钢机团网站,Accessed February 2022
  3. "捷报频传,安耐克再创精品工程_热风炉". www.sohu.com. Retrieved 2024-12-02.
  4. 4.0 4.1 https://web.archive.org/web/20220110223804/https://www.qcc.com/firm/df5b6682911e64c5b0bed0a53ebf3d5a.html. Archived from the original on 10 January 2022. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 5.2 5.3 https://web.archive.org/web/20220126160539/http://www.jggroup.cn/jtjj.asp. Archived from the original on 26 January 2022. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 6.2 6.3 6.4 6.5 https://www.sohu.com/a/470341261_313737. {{cite web}}: Missing or empty |title= (help)
  7. 7.0 7.1 7.2 7.3 7.4 7.5 https://finance.sina.com.cn/money/future/indu/2021-02-05/doc-ikftpnny5118309.shtml. {{cite web}}: Missing or empty |title= (help)
  8. 8.0 8.1 https://weibo.com/ttarticle/p/show?id=2309404435922211962970&sudaref=www.baidu.com. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 9.2 9.3 https://web.archive.org/web/20240122223532/https://www.sohu.com/a/423783880_120214183. Archived from the original on 22 January 2024. {{cite web}}: Missing or empty |title= (help)
  10. 10.0 10.1 10.2 10.3 10.4 10.5 10.6 10.7 https://web.archive.org/web/20220120030415/http://www.jggroup.cn/cpzx.asp. Archived from the original on 20 January 2022. {{cite web}}: Missing or empty |title= (help)
  11. https://web.archive.org/web/20220318154024/http://www.jggroup.cn/gywm_read.asp?id. Archived from the original on 18 March 2022. {{cite web}}: Missing or empty |title= (help)
  12. 12.0 12.1 12.2 12.3 12.4 12.5 12.6 12.7 12.8 12.9 https://web.archive.org/web/20220207192044/https://finance.sina.com.cn/money/future/indu/2020-03-02/doc-iimxxstf5776330.shtml. Archived from the original on 07 February 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  13. 13.00 13.01 13.02 13.03 13.04 13.05 13.06 13.07 13.08 13.09 13.10 13.11 13.12 13.13 13.14 13.15 13.16 13.17 https://info.lgmi.com/html/202102/05/5666.htm. {{cite web}}: Missing or empty |title= (help)
  14. 14.00 14.01 14.02 14.03 14.04 14.05 14.06 14.07 14.08 14.09 14.10 14.11 14.12 14.13 14.14 14.15 https://news.gangguwang.com/html/2019/01/11/193223.html. {{cite web}}: Missing or empty |title= (help)
  15. 15.00 15.01 15.02 15.03 15.04 15.05 15.06 15.07 15.08 15.09 15.10 15.11 15.12 15.13 15.14 15.15 https://web.archive.org/web/20220319181655/https://www.sohu.com/a/295774267_754864. Archived from the original on 19 March 2022. {{cite web}}: Missing or empty |title= (help)
  16. 16.00 16.01 16.02 16.03 16.04 16.05 16.06 16.07 16.08 16.09 16.10 16.11 16.12 16.13 16.14 16.15 16.16 16.17 16.18 16.19 16.20 16.21 16.22 16.23 16.24 16.25 (PDF) https://web.archive.org/web/20220224072927/http://www.gov.cn/zhengce/zhengceku/2021-05/07/5605092/files/4362a77483354513be0fc81be53a4a64.pdf. Archived from the original (PDF) on 24 February 2022. {{cite web}}: Missing or empty |title= (help)
  17. 17.0 17.1 17.2 17.3 https://web.archive.org/web/20240119005537/https://weibo.com/ttarticle/p/show?id=2309404558401832353876. Archived from the original on 19 January 2024. {{cite web}}: Missing or empty |title= (help)
  18. 18.0 18.1 18.2 18.3 18.4 18.5 18.6 https://web.archive.org/web/20221208025352/https://www.jggroup.cn/fzdsj.asp. Archived from the original on 08 December 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  19. 19.0 19.1 https://www.sohu.com/a/238004774_764282. {{cite web}}: Missing or empty |title= (help)

Resources