Klechovce-Negotino Gas Pipeline

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Klechovce-Negotino Gas Pipeline is an operating gas pipeline in North Macedonia

Location

The pipeline starts at the Skopje-Kriva Palanka Gas Pipeline and runs south to Negotino.[1]

Loading map...

Project details

  • Operator: MER JSC Skopje[1]
  • Owner: MER JSC Skopje[1]
  • Parent company: MER JSC Skopje[1]
  • Capacity:
  • Length: 97 km[2][3][4]
  • Diameter: 700, 500, 200 mm.
  • Status: Operating
  • Start year: 2019
  • Cost: $75.7 million[5]
  • Financing:
  • Associated infrastructure: Skopje-Kriva Palanka Gas Pipeline

Background

Built in two phases, this pipeline carries imported natural gas from Northern Macedonia to its southern regions. Receiving gas from the Skopje-Kriva Palanka Gas Pipeline, it connects to a compressor station at the city of Stip before passing through to Negotino. The first phase (Klechovce-Stip) was commissioned in 2016, while the second phase was commissioned in 2019.[3]

Articles and resources

References

  1. 1.0 1.1 1.2 1.3 European Bank for Reconstruction and Development (Apr, 2020). "Gas distribution network in North Macedonia Update of Feasibility study" (PDF). EBRD. Retrieved Jul 25th, 2022. {{cite web}}: Check date values in: |access-date= and |date= (help); line feed character in |title= at position 34 (help)CS1 maint: url-status (link)
  2. "NATIONAL ENERGY RESOURCES Skopje". mer.com.mk. Retrieved 2022-07-25.
  3. 3.0 3.1 "National gas pipeline Klechovce- Negotino, section BS5 – Negotino, 36km (61-97 km) | RapidBild". rapidbild.com.mk. Retrieved 2022-07-25.
  4. "NATIONAL ENERGY RESOURCES Skopje". mer.com.mk. Retrieved 2022-07-25.
  5. Skopje (Mar 14th, 2015). "Construction of Klecovce-Stip gas pipeline commenced". North Macedonian Ministry of Finance. Retrieved Jul 25th, 2022. {{cite web}}: Check date values in: |access-date= and |date= (help)CS1 maint: url-status (link)