Licheng Taihang Iron & Steel Co Ltd (黎城太行钢铁有限公司) is a blast furnace-basic oxygen furnace (BF-BOF) steel plant operating in Changzhi, Shanxi, China.
Location
The map below shows the exact location of the plant in Changzhi, Shanxi, China:
- Location: Chengnan Village, Licheng County, Changzhi City, Shanxi Province
- Coordinates (WGS 84): 36.472303, 113.344155 (exact)
Background
Licheng Taihang Iron & Steel Co., Ltd. is in the process of upgrading its smelting equipment based on the "Shanxi Iron and Steel Industry Revitalization Plan." The 3 billion RMB project, to be completed by the end of 2025, will shift the plant from an integrated plant with blast furnace technology toward an electric steel plant producing special steel.[1]
In addition, the Licheng County Party Committee is planning the merger and reorganization of four private steel companies in Changzhi in order to form a new industrial base with a production capacity of 6 millions tons of crude steel per year. This project is set to resume "as soon as possible after the epidemic is over."[1]
Plant Details
Table 1: General Plant Details
Phase | Plant status | Start date | Retired date | Workforce size |
---|---|---|---|---|
Main plant | Operating[2] | 2000[3] | – | 1711[2] |
Closure | Retired[4] | – | 2020[4] | – |
Table 2: Ownership and Parent Company Information
Phase | Parent company | Parent company GEM ID | Owner | Owner company GEM ID |
---|---|---|---|---|
Main plant | Licheng Taihang Iron & Steel Co Ltd [100%] | E100000123261 [98.6%]; E100000001753 [1.4%] | Licheng Taihang Iron & Steel Co., Ltd.[2] | E100000126125 |
Table 3: Process and Products
Phase | Steel product category | Steel products | Steel sector end users | ISO 14001 | Main production equipment | Detailed production equipment |
---|---|---|---|---|---|---|
Main plant | finished rolled[3] | hot rolled smooth round steel bars, high wire, hot rolled ribbed steel bars for construction, rebar, disc screw[3] | building and infrastructure; tools and machinery; energy; transport[5] | 2022[5] | BF, BOF[6] | 2 BOF ( 2x50-tonne)[7] |
Closure | finished rolled[3] | hot rolled smooth round steel bars, high wire, hot rolled ribbed steel bars for construction, rebar, disc screw[3] | building and infrastructure; tools and machinery; energy; transport[5] | – | BF[4] | –[4] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Basic oxygen furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|---|
Main plant | operating | 1700 TTPA[8][8] | 1700 TTPA[8][8] |
Closure | retired | – | – |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Blast furnace capacity | Nominal iron capacity (total) |
---|---|---|---|
Main plant | operating | 618 TTPA[8][4] | 618 TTPA[8][4] |
Closure | retired | 560 TTPA[9] | 560 TTPA[9] |
Blast Furnace Details
Table 6: Blast Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Retired date | Current size | Current capacity (ttpa) | Decarbonization technology | Most recent relining |
---|---|---|---|---|---|---|---|---|---|
unknown | retired[4] | unknown | unknown | unknown | 2020[4] | 458 m³[6] | 560[9] | unknown | unknown |
unknown | operating[6] | unknown | unknown | unknown | – | 528 m³[6] | 618[8][4] | unknown | 2023-10-10[10] |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 公司简介, 太行钢铁有限公司, Retrieved on: Jul. 27, 2020
- ↑ 2.0 2.1 2.2 https://web.archive.org/web/20220110223614/https://www.qcc.com/firm/8ef95fc1e86c1f4f71a00ad8f0f3b62d.html. Archived from the original on 10 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 3.0 3.1 3.2 3.3 3.4 https://web.archive.org/web/20220113232914/http://lcthgt.com/company.asp. Archived from the original on 13 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 https://web.archive.org/web/20220129203126/https://huanbao.bjx.com.cn/news/20201203/1119846.shtml. Archived from the original on 29 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 5.0 5.1 5.2 https://web.archive.org/web/20240119055600/http://cx.cnca.cn/CertECloud/result/skipResultList?certNumber=&orgName=%E9%BB%8E%E5%9F%8E%E5%A4%AA%E8%A1%8C%E9%92%A2%E9%93%81%E6%9C%89%E9%99%90%E5%85%AC%E5%8F%B8&fromIndex=true. Archived from the original on 19 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 6.0 6.1 6.2 6.3 https://web.archive.org/web/20220207192044/https://finance.sina.com.cn/money/future/indu/2020-03-02/doc-iimxxstf5776330.shtml. Archived from the original on 07 February 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://finance.sina.com.cn/money/future/indu/2020-03-02/doc-iimxxstf5776330.shtml;https://huanbao.bjx.com.cn/news/20201203/1119846.shtml.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 8.2 8.3 8.4 8.5 8.6 http://www.changzhi.gov.cn/xxgkml/czsrmzf/zbwj_3466/202012/t20201203_2195352.shtml.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 9.0 9.1 9.2 (PDF) https://web.archive.org/web/20220224072927/http://www.gov.cn/zhengce/zhengceku/2021-05/07/5605092/files/4362a77483354513be0fc81be53a4a64.pdf. Archived from the original (PDF) on 24 February 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20231114162951/https://baijiahao.baidu.com/s?id=1779063870520333407&wfr=spider&for=pc. Archived from the original on 14 November 2023.
{{cite web}}
: Missing or empty|title=
(help)