Makran Steel Sistan and Baluchestan Complex is a direct reduced iron-electric arc furnace (DRI-EAF) steel plant under construction in Chabahar, Sistan and Baluchestan, Iran.

Location

The map below shows the exact location of the plant in Chabahar, Sistan and Baluchestan, Iran:

Loading map...
  • Location: Chabahar city, Sistan and Baluchestan, Iran
  • Coordinates (WGS 84): 25.44839771869034, 60.640848760016326 (exact)

Plant Details

Table 1: General Plant Details

Plant status Construction date Start date Workforce size
Construction[1] 2019[1] 2030[2] 300[1]

Table 2: Ownership and Parent Company Information

State-owned entity status Parent company Parent company GEM ID Owner Owner company GEM ID
Full Iranian Mines & Mining Industries Development & Renovation Organization [100.0%] E100001000255 [100%] Makran Steel Company[3] E100000131121

Table 3: Process and Products

Main production equipment Detailed production equipment
DRI, EAF[1] MIDREX DRI plant; EAF (# unknown)[1][4][5]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status* Electric arc furnace steelmaking capacity Nominal crude steel capacity (total)
construction 3200 TTPA[6] 3200 TTPA[6]

Table 5: Crude Iron Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status* Sponge iron/DRI capacity Nominal iron capacity (total)
construction 1600 TTPA[1][4][5] 1600 TTPA[1][4][5]

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 https://web.archive.org/web/20210423134032/http://danialpetro.com/default.aspx?PID. Archived from the original on 23 April 2021. {{cite web}}: Missing or empty |title= (help)
  2. (PDF) https://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-202.pdf. {{cite web}}: Missing or empty |title= (help)
  3. (PDF) https://web.archive.org/web/20210807133859/http://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-2020.pdf. Archived from the original (PDF) on 07 August 2021. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  4. 4.0 4.1 4.2 https://web.archive.org/web/20230207055556/https://iritec.co/en/project-details/makran-chabahar-steel-complex-mega-module-direct-reduction-plant/. Archived from the original on 07 February 2023. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  5. 5.0 5.1 5.2 (PDF) https://web.archive.org/web/20231103031625/https://www.midrex.com/wp-content/uploads/MidrexSTATSBook2022.pdf. Archived from the original (PDF) on 03 November 2023. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  6. 6.0 6.1 (PDF) https://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-2023.pdf. {{cite web}}: Missing or empty |title= (help)

Resources