Mechel Chelyabinsk Metallurgical Plant
This article is part of the Global Steel Plant Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Mechel Chelyabinsk Metallurgical Plant (Челябинский металлургический комбинат (Russian)), also known as CHMK OAO Mechel; Chelyabinsk Metallurgical Combine, is a blast furnace-basic oxygen furnace (BF-BOF) and electric arc furnace (EAF) steel plant operating in Chelyabinsk, Russia.
Location
The map below shows the exact location of the plant in Chelyabinsk, Russia:
- Location: 2-ya Paveletskaya street, 14, Chelyabinsk, Chelyabinsk region, Russia, 454047
- Coordinates (WGS 84): 55.270730, 61.436492 (exact)
Background
Construction of the plant started in the 1930s and resumed during World War II. The first steel products were produced in 1943.[1] Previously, the plant was named the "Chelyabinsk Metallurgical Plant"; in 1983 it received the status of a "combine", being renamed into "Chelyabinsk Metallurgical Combine" (Челябинский металлургический комбинат).[2]
The plant currently has three operating blast furnaces, two basic oxygen furnaces (converter), and two electric arc furnaces (EAF). The blast furnace #4 basic oxygen furnace #1 have been fully reconstructed in 2020.[3][4] The blast furnace #5 has been fully reconstructed in 2023.[5] With no recent evidence, it is unclear if all the units are operating and at what capacity.
The plant added aspiration system to the blast furnace #4 and a dry gas cleaning system in the EAF shop in 2024. The cost of the projects amounted to 1 billion 40 million rubles. The projects are said to reduce emissions by 27% compared to 2017 emissions. Future plans include the construction of another aspiration system for the casting yard at the renovated blast furnace No. 5, as well as the modernization of filters on the plant's sintering machines.[3]
As of October 2024, the plant has been operating at a loss.[6]
The plant is one of the major pollutants of air and water in the region.[7][8]
In 2018, ChMK was fined 100 thousand rubles for dumping mercury into the river. In 2021, the Chelyabinsk Regional Court ordered the company to pay a fine of 142.6 million rubles. That same year, ChMK paid off a debt of 47 million rubles in another criminal case. In 2022, Chief Engineer Vladimir Kapnin, Head of the Department for Labor Protection, Industrial Safety and Environmental Protection Alexander Sadyrin and his deputy Alexander Sosunov were found guilty of the mercury spill in 2018. The plant's employees were given suspended sentences of two years in prison. However, the following year, the sentence was replaced with a fine.[9]
Rosprirodnadzor identified gross violations of environmental legislation in the plant's activities. For several years, the Chelyabinsk Metallurgical Plant has reported on the successful implementation of programs to both reduce the discharge of dirty waste into the Miass River and reduce emissions of hazardous substances into the air. In fact, an inspection by the supervisory authority showed that modernization did not help solve the problem - tons of heavy metals and other substances hazardous to humans continue to flow into the main reservoir of the capital of the Southern Urals.[8]
Plant Details
Table 1: General Plant Details
Plant status | Construction date | Start date | Workforce size | Iron ore source | Coal source |
---|---|---|---|---|---|
Operating[10] | 1942[11] | 1943[11] | 15196[12] | Korshunovskoye and Rudnogorskoye iron ore fields[13] | Raspadskaya coal mine |
Table 2: Ownership and Parent Company Information
Parent company | Parent company GEM ID | Owner | Owner company PermID | Owner company GEM ID |
---|---|---|---|---|
Mechel JSC [100.0%] | E100000000860 [100%] | Chelyabinskiy Metallurgicheskiy Kombinat PAO[10] | 4295887257 | E100000130740 |
Table 3: Process and Products
Steel product category | Steel products | Steel sector end users | ISO 14001 | Main production equipment | Detailed production equipment |
---|---|---|---|---|---|
semi-finished; finished rolled[14] | billet; slabs; wire rod; rebar; pipe; square bar; hot-rolled; cold-rolled; stainless steel; rails[14][15] | automotive; building and infrastructure; energy; tools and machinery; transport[14][16] | 2024[17][18] | BF, BOF, EAF[19][20][21] | coking plant (# batteries unknown, battery #7 began in Nov. 2006), battery #4 rebuilt in 2009); 1 sinter plant (began in 2005); 3 BF; 3 BOF (BOF #1 (rebuilt in 2019)); 2 EAF (EAF #2 (rebuilt in 2004), EAF #6 (rebuilt in 2004))[19][22][23][24][25] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum)
Capacity operating status* | Basic oxygen furnace steelmaking capacity | Electric arc furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|---|
operating | 3999 TTPA[26][25][26][25][26][25] | 1800 TTPA[26][26] | 5799 TTPA[26][25][26][25][26][25][26][26] |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum)
Capacity operating status* | Blast furnace capacity | Nominal iron capacity (total) |
---|---|---|
operating | 4000 TTPA[19][27][28][23][29][19][30][27][27] | 4000 TTPA[19][27][28][23][29][19][30][27][27] |
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Sinter | Coke |
---|---|
4500 TTPA[31][26] | 2900 TTPA[26] |
Table 7: Actual Crude Steel Production by Year (thousand tonnes per annum)
Year | Total (all routes) |
---|---|
2020 | – |
2021 | –[32] |
2022 | 3300 TTPA[33] |
Table 8: Actual Crude Iron Production by Year (thousand tonnes per annum)
Year | BF Production | Total (all routes) |
---|---|---|
2020 | – | – |
2021 | – | –[32] |
2022 | 3200 TTPA | 3200 TTPA[34][33] |
Blast Furnace Details
Table 9: Blast Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Current size | Current capacity (ttpa) | Decarbonization technology | Most recent relining |
---|---|---|---|---|---|---|---|---|
1 | operating[19][24][28][35][36][25] | unknown | unknown | 2004-03[35][37] | 2030 m³[19][25][38] | 1500[19][27] | unknown | 2004-03[39][40] |
4 | operating[19][23][24][28][35][36][25][41] | unknown | unknown | 2020-03[42][29][19][23] | 1386 m³[25] | 1100[28][23][29][19][30][27] | unknown | 2020-12[43][27][44] |
5 | operating[25][29][26][27] | unknown | unknown | 2023-09[27] | 1719 m³[45][25] | 1400[27] | unknown | 2023-09[27][46] |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
References
- ↑ "Челябинский металлургический комбинат". Wikipedia. Retrieved Apr 1, 2022.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Челябинский металлургический комбинат". Metallobazy.ru. Mar 2, 2020. Retrieved Jan 25, 2022.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 3.0 3.1 "Направления деятельности". mechel.ru. Retrieved 2024-11-13.
- ↑ "Челябинский металлургический комбинат". mechel.ru. Retrieved 2024-11-13.
- ↑ "Челябинский металлургический комбинат завершил капремонт доменной печи №5 — INFOLOM". infolom.su. Retrieved 2024-11-13.
- ↑ "Челябинский металлургический комбинат (CHMK) Итоги 9 мес. 2024 г.: текущих поступлений не хватает для обслуживания дорожающего долга". 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Pollution of the Miass River". 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 8.0 8.1 "ЧМК проигнорировал нацпроект «Чистый воздух». Зюзина назвали следующим претендентом на деприватизацию - Правда УрФО". Правда УрФО - Информационное агентство - окружная интернет-газета (in русский). 2024-11-13. Retrieved 2024-11-13.
- ↑ "ЧМК грозит административная ответственность за выбросы и загрязнение реки Миасс". Коммерсантъ (in русский). 2024-08-01. Retrieved 2024-11-13.
- ↑ 10.0 10.1 https://web.archive.org/web/20220112164656/https://www.mechel.com/sector/steel/chelyabinskiy-metallurgicheskiy-kombinat/. Archived from the original on 12 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 11.0 11.1 https://web.archive.org/web/20221209131158/https://www.mechel.com/sector/steel/chelyabinskiy-metallurgicheskiy-kombinat/history/. Archived from the original on 09 December 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220205152541/https://www.list-org.com/company/1053. Archived from the original on 05 February 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ (PDF) https://web.archive.org/web/20221130215516/https://anoire.center/wp-content/uploads/2022/08/iron.pdf. Archived from the original (PDF) on 30 November 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 14.0 14.1 14.2 https://web.archive.org/web/20200527161809/http://www.mechel.com/sector/steel/cmk/. Archived from the original on 27 May 2020.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20190801235937/http://www.mechel.com:80/sector/steel/cmk/production/. Archived from the original on 01 August 2019.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220126184909/https://www.mechel.com/. Archived from the original on 26 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230130040855/https://www.mechel.com/sector/steel/chelyabinskiy-metallurgicheskiy-kombinat/production/. Archived from the original on 30 January 2023.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230130040855/https://www.mechel.com/sector/steel/chelyabinskiy-metallurgicheskiy-kombinat/production/. Archived from the original on 30 January 2023.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 19.00 19.01 19.02 19.03 19.04 19.05 19.06 19.07 19.08 19.09 19.10 19.11 https://web.archive.org/web/20220319003551/https://www.mechel.ru/sector/steel/chelyabinskiy-metallurgicheskiy-kombinat/history/. Archived from the original on 19 March 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20221209122303/https://www.mechel.com/sector/steel/chelyabinskiy-metallurgicheskiy-kombinat/. Archived from the original on 09 December 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230608003126/https://mechel.com/sector/steel/. Archived from the original on 08 June 2023.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ http://www.mechel.com/press/press/chelyabinsk_metallurg_plant?rid=24885&oo=1&fnid=68&newWin=0&apage=1&nm=122583&fxsl=view.xsl.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 23.0 23.1 23.2 23.3 23.4 23.5 https://web.archive.org/web/20211028211316/https://www.mechel.ru/press/news/chmk-pristupil-k-montazhu-obnovlennoy-domennoy-pechi-/. Archived from the original on 28 October 2021.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 24.0 24.1 24.2 https://web.archive.org/web/20211018135312/https://metallobazy.ru/news/1211. Archived from the original on 18 October 2021.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 25.00 25.01 25.02 25.03 25.04 25.05 25.06 25.07 25.08 25.09 25.10 25.11 25.12 https://onlinepatent.ru/journal/CHMK/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 26.00 26.01 26.02 26.03 26.04 26.05 26.06 26.07 26.08 26.09 26.10 26.11 26.12 https://web.archive.org/web/20210411015449/https://metallobazy.ru/factory/10. Archived from the original on 11 April 2021.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 27.00 27.01 27.02 27.03 27.04 27.05 27.06 27.07 27.08 27.09 27.10 27.11 27.12 https://infolom.su/cheljabinskij-metallurgicheskij-kombinat-zavershil-kapremont-domennoj-pechi-5/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 28.0 28.1 28.2 28.3 28.4 https://web.archive.org/web/20220627084248/https://graphitecarbon.ru/na-chmk-mechel-zavershena-modernizatsiya-domennoj-pechi-4-i-konvertera-1/. Archived from the original on 27 June 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 29.0 29.1 29.2 29.3 29.4 https://web.archive.org/web/20221201163351/https://prochelyabinsk.ru/news/ekonomika/na-chmk-vozvodyat-novuyu-domnu.htm. Archived from the original on 01 December 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ 30.0 30.1 30.2 https://web.archive.org/web/20220701112015/https://www.mechel.ru/press/news/chmk-zavershil-kapitalnyy-remont-domennoy-pechi-/. Archived from the original on 01 July 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20190715171322/http://www.mechel.ru:80/sector/steel/cmk/history. Archived from the original on 15 July 2019.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 32.0 32.1 https://web.archive.org/web/20220911194706/https://www.mechel.ru/press/releases/mechel-reports-2021-operational-results/. Archived from the original on 11 September 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 33.0 33.1 (PDF) https://web.archive.org/web/20240111061915/https://mechel.ru/upload/iblock/626/526gbc63x2f3qt7xlka0rur2r9uzsz9r.pdf. Archived from the original (PDF) on 11 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20240111070903/https://mechel.ru/sector/steel/. Archived from the original on 11 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 35.0 35.1 35.2 https://regnum.ru/news/227952.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 36.0 36.1 https://web.archive.org/web/20191023120029/https://www.metaprom.ru/factories/chmk. Archived from the original on 23 October 2019.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230529143534/https://mechel.ru/sector/steel/chelyabinskiy-metallurgicheskiy-kombinat/history/.
{{cite web}}
: Check|archive-url=
value (help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20181023080235/http://www.metalinfo.ru:80/ru/news/80046. Archived from the original on 23 October 2018.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20240322054242/https://mechel.ru/sector/steel/chelyabinskiy-metallurgicheskiy-kombinat/history/. Archived from the original on 22 March 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://regnum.ru/news/227952.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://www.1obl.ru/tv/vremya-novostey/vremya-novostey-ot-18-04-2023/na-chmk-provodyat-modernizatsiyu-oborudovaniya/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230609220912/https://mechel.ru/press/news/chmk-zavershil-kapitalnyy-remont-domennoy-pechi-/.
{{cite web}}
: Check|archive-url=
value (help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230609220912/https://mechel.ru:443/press/news/chmk-zavershil-kapitalnyy-remont-domennoy-pechi-/. Archived from the original on 09 June 2023.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20240322054535/https://www.accesswire.com/580421/mechel-launches-upgraded-steelmaking-equipment-at-chelyabinsk-metallurgical-plant. Archived from the original on 22 March 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20210920151052/https://metalporn.ru/index.php/predpriyatiya-chernoj-metallurgii/po-nomenklature-produktsii/item/chelyabinskij-mk. Archived from the original on 20 September 2021.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20240322054601/https://www.metalbulletin.ru/news/black/10174370/. Archived from the original on 22 March 2024.
{{cite web}}
: Missing or empty|title=
(help)
Resources
- https://mechel.com/sector/steel/chelyabinskiy-metallurgicheskiy-kombinat/ Company website
- https://en.wikipedia.org/wiki/Pervouralsk_New_Pipe_Plant; https://ru.wikipedia.org/wiki/%D0%A7%D0%B5%D0%BB%D1%8F%D0%B1%D0%B8%D0%BD%D1%81%D0%BA%D0%B8%D0%B9_%D0%BC%D0%B5%D1%82%D0%B0%D0%BB%D0%BB%D1%83%D1%80%D0%B3%D0%B8%D1%87%D0%B5%D1%81%D0%BA%D0%B8%D0%B9_%D0%BA%D0%BE%D0%BC%D0%B1%D0%B8%D0%BD%D0%B0%D1%82 Wikipedia