Mesco Steel Kalinganagar plant, also known as MSKL; Mideast Integrated Steel (MISL), is a blast furnace-basic oxygen furnace (BF-BOF) steel plant operating in Kalinganagar, Odisha, India.
Location
The map below shows the exact location of the plant in Kalinganagar, Odisha, India:
- Location: Kalinga Nagar Industrial Complex, Khurunti, P.O. Danagadi - 755026, Distt. Jaipur, Orissa, India
- Coordinates (WGS 84): 20.976277, 86.044419 (exact)
Background
The Mesco Steel Kalinganagar steel plant began operating in 1992 under the Mesco Steel Group.[1] In 2005, pig iron production commenced.[2]
In December 2015, Mesco Steel Kalinganagar was forced to cease operations due to lack of raw materials; this closure went on at least until 2017.[3]
In February 2022, a civilian petition reported that Mesco was pursuing an illegal railway siding project at the site, which was releasing toxic substances into the environment. According to the petition, the Mesco Steel Kalinganagar plant had been shut since 2020.[4]
Expansion
According to Mesco Steel's website, an expansion including 2 BOF plants (100-tonnes each), 1 BF plant (3200 m3), a sinter plant, and coke oven battery was planned to be completed by 2021. The crude steel capacity would have amounted to 2300 ttpa.[2] However, no update has been posted since 2020.
Plant Details
Table 1: General Plant Details
Phase | Plant status | Announced date | Construction date | Start date | Power source |
---|---|---|---|---|---|
Main plant | Operating[5] | – | 1997[6] | 2005[7][8] | One captive power plant (24 MW capacity)[9] |
Expansion | Cancelled[9][10] | 2013[11] | – | –[7] | – |
Table 2: Ownership and Parent Company Information
Phase | Parent company | Parent company PermID | Parent company GEM ID | Owner | Owner company PermID | Owner company GEM ID |
---|---|---|---|---|---|---|
Main plant | Mesco Steel Ltd [100.0%] | 5000931939 [100%] | E100001000682 [100%] | Mesco Kalinga Steel Ltd[12] | 4296917434 | E100000130811 |
Table 3: Process and Products
Phase | Steel product category | Steel products | Main production equipment | Detailed production equipment |
---|---|---|---|---|
Main plant | crude; semi-finished[13] | pig iron; lump ore; plates; fines; lime slurry; flat and long products[13] | BF, BOF[14] | BOF (100-tonnes, began in 2020); sinter plant[14][9] |
Expansion | crude; semi-finished[13] | pig iron; lump ore; plates; fines; lime slurry; flat and long products[13] | BF, BOF[14] | 2 BOF (100-tonnes each); sinter plant; coke oven batterry[14] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Basic oxygen furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|---|
Main plant | operating | 1200 TTPA[10][15][7][9] | 1200 TTPA[10][15][7][9] |
Expansion | cancelled | 2300 TTPA[10][15][7][9][10][15][7][9] | 2300 TTPA[10][15][7][9][10][15][7][9] |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Blast furnace capacity | Nominal iron capacity (total) |
---|---|---|---|
Main plant | operating | 1200 TTPA[9][9] | 1200 TTPA[9][9] |
Expansion | cancelled | 2300 TTPA[9] | 2300 TTPA[9] |
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Phase | Sinter | Coke |
---|---|---|
Main plant | 770 TTPA[9] | –[9] |
Expansion | 3300 TTPA[14] | 1500 TTPA[14] |
Blast Furnace Details
Table 7: Blast Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Current size | Current capacity (ttpa) | Decarbonization technology | Most recent relining |
---|---|---|---|---|---|---|---|---|
unknown | operating[16] | unknown | unknown | 2005[6] | 389 m³[16] | 600[9] | unknown | unknown |
unknown | operating[16] | unknown | unknown | 2012[6] | 389 m³[16] | 600[9] | unknown | unknown |
unknown | cancelled[17][9][10] | 2014[18] | unknown | unknown | 3200 m³[19] | 2300[9] | unknown | unknown |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
References
- ↑ "Brochure" (PDF). Archived (PDF) from the original on January 27, 2022. Retrieved January 27, 2022.
- ↑ 2.0 2.1 "Home". Mesco Steel. Archived from the original on December 6, 2021. Retrieved January 24, 2022.
- ↑ Dash, Jayajit (2017-08-21). "Visa Steel suspends Kalinganagar operations as raw material supplies stop". Business Standard India. Retrieved 2022-03-04.
- ↑ "NGT orders action against illegal railway siding". OrissaPOST. 2022-02-08. Retrieved 2022-03-04.
{{cite web}}
: CS1 maint: url-status (link) - ↑ https://web.archive.org/web/20220312013301/http://mescosteel.com/locations.php. Archived from the original on 12 March 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 6.0 6.1 6.2 (PDF) https://web.archive.org/web/20240111011054/https://mescosteel.com/pdf/brochure_mesco-2017.pdf. Archived from the original (PDF) on 11 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 7.0 7.1 7.2 7.3 7.4 7.5 7.6 7.7 https://web.archive.org/web/20211206194651/http://www.mescosteel.com/. Archived from the original on 06 December 2021.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20221107043011/https://www.inventiva.co.in/trends/top-10-best-steel-manufacturing-company-in-india-in-2023/. Archived from the original on 07 November 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ 9.00 9.01 9.02 9.03 9.04 9.05 9.06 9.07 9.08 9.09 9.10 9.11 9.12 9.13 9.14 9.15 9.16 9.17 9.18 9.19 9.20 (PDF) https://web.archive.org/web/20220122092000/http://mescosteel.com/pdf/brochure_mesco-2017.pdf. Archived from the original (PDF) on 22 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 10.0 10.1 10.2 10.3 10.4 10.5 10.6 10.7 (PDF) https://web.archive.org/web/20220111173338/https://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-2021.pdf. Archived from the original (PDF) on 11 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://web.archive.org/web/20200605023406/http://mescosteel.com:80/pdf/3point5-MTPA-EC-MISL-Plant.pdf. Archived from the original (PDF) on 05 June 2020.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20211206194651/http://www.mescosteel.com/. Archived from the original on 06 December 2021.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ 13.0 13.1 13.2 13.3 https://web.archive.org/web/20240125060222/http://www.mescosteel.com/product.php. Archived from the original on 25 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 14.0 14.1 14.2 14.3 14.4 14.5 https://web.archive.org/web/20200725140406/http://mescosteel.com:80/future-projects.php. Archived from the original on 25 July 2020.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 15.0 15.1 15.2 15.3 15.4 15.5 https://web.archive.org/web/20181017034451/https://economictimes.indiatimes.com/industry/indl-goods/svs/steel/mesco-keen-to-buy-struggling-steel-companies/articleshow/62063828.cms. Archived from the original on 17 October 2018.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 16.0 16.1 16.2 16.3 https://web.archive.org/web/20220309175114/http://mescosteel.com/product.php. Archived from the original on 09 March 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220407134357/http://mescosteel.com/future-projects.php. Archived from the original on 07 April 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://sambadenglish.com/misl-fully-integrated-steel-plant-kalinganagar/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220401034543/https://www.oecd.org/officialdocuments/publicdisplaydocumentpdf/?cote=DSTI/SU/SC(2014)16/FINAL&docLanguage=En. Archived from the original on 01 April 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help)