Shyam Metalics Sambalpur Steel Plant is a blast furnace (BF), direct reduced iron (DRI) and electric arc furnace (EAF) steel plant operating in Sambalpur, Odisha, India.
Location
The map below shows the exact location of the plant in Sambalpur, Odisha, India:
- Location: Pandoli, Rengali, Sambalpur - 768212 Odisha, India
- Coordinates (WGS 84): 21.680344, 84.04179 (exact)
Background
Shyam Metalics and power Limited was incorporated in 1991.[1] The Sambalpur Steel plant began commercial production in 2006.[2] The Plant had a capacity of 792 ttpa sponge iron and 401.28 ttpa billet as of 31 December 2020, and is expanding capacity by 561 ttpa sponge iron, and 461.2 ttpa billet production by 2025.[3][4][5]
Plant Details
Table 1: General Plant Details
Phase | Plant status | Start date | Workforce size | Power source |
---|---|---|---|---|
Main plant | Operating[6] | 2006[7] | – | 118 MW Captive power plant[8] |
Expansion | Operating[9][7] | 2025[10] | 3060[11] | 40 MW Captive Power Plant[8] |
Expansion | Operating[9][7] | 2025[10] | 3060[11] | 40 MW Captive Power Plant[8] |
Table 2: Ownership and Parent Company Information
Phase | Parent company | Parent company GEM ID | Owner | Owner company PermID | Owner company GEM ID |
---|---|---|---|---|---|
Main plant | Shyam Metalics and Energy Ltd [100%] | E100001012153 [27.6%]; E100001012154 [20%]; E100001012155 [16%]; E100001012156 [9.1%]; E100001012157 [8.4%]; E100001012158 [5.6%] | Shyam Metalics and Energy Limited[12] | 5000933245 | E100001012152 |
Table 3: Process and Products
Phase | Steel product category | Steel products | ISO 14001 | Main production equipment | Detailed production equipment |
---|---|---|---|---|---|
Main plant | crude; semi-finished[13] | DRI; pellets; billets; bars; rods[13] | yes[6] | DRI, other[6] | 7 DRI (2x350 tpd; 2x100 tpd; 3x500 tpd); 12 IF (4x18 ton; 4x8 ton; 4x12 ton)[6] |
Expansion | – | – | – | DRI, BF, EAF, other[6][7] | 2 BF (450m3); 3 DRI (1x500 tpd; 2x600 tpd); 1 EAF (80 ton); 9 IF (9x18 ton)[6][7][11] |
Expansion | – | – | – | DRI, BF, EAF, other[6][7] | 2 BF (450m3); 3 DRI (1x500 tpd; 2x600 tpd); 1 EAF (80 ton); 9 IF (9x18 ton)[6][7][11] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Electric arc furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|---|
Main plant | operating | – | 862 TTPA |
Expansion | operating | –[11] | 461 TTPA[11] |
Expansion | announced | 673 TTPA[11] | 673 TTPA[11] |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Blast furnace capacity | Sponge iron/DRI capacity | Nominal iron capacity (total) |
---|---|---|---|---|
Main plant | operating | – | 1155 TTPA[6][6][6][6][6][6][6] | 1155 TTPA[6][6][6][6][6][6][6] |
Expansion | operating | –[11][11] | 528 TTPA[7][7][7] | 528 TTPA[11][11][7][7][7] |
Expansion | announced | 742 TTPA[11][11] | –[7][7][7] | 742 TTPA[11][11][7][7][7] |
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Phase | Sinter | Coke | Pellets |
---|---|---|---|
Main plant | – | – | 3000 TTPA[6] |
Expansion | 882 TTPA[11] | 550 TTPA[11] | 600 TTPA[6] |
Expansion | 882 TTPA[11] | 550 TTPA[11] | 600 TTPA[6] |
Table 7: Actual Crude Steel Production by Year (thousand tonnes per annum)
Year | Total (all routes) |
---|---|
2020 | 438 TTPA[14] |
2021 | 482 TTPA[14] |
2022 | 876 TTPA[14] |
Table 8: Actual Crude Iron Production by Year (thousand tonnes per annum)
Year | DRI Production | Total (all routes) |
---|---|---|
2020 | 584 TTPA[14] | 584 TTPA |
2021 | 781 TTPA[14] | 781 TTPA |
2022 | 1089 TTPA[14] | 1089 TTPA |
Blast Furnace Details
Table 9: Blast Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Current size | Current capacity (ttpa) | Decarbonization technology | Most recent relining |
---|---|---|---|---|---|---|---|---|
unknown | announced[11] | unknown | unknown | unknown | 450 m³[11] | 371[11] | unknown | unknown |
unknown | announced[11] | unknown | unknown | unknown | 450 m³[11] | 371[11] | unknown | unknown |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
References
- ↑ "Shyam Metalics and Energy". Wikipedia. Retrieved 09 January, 2024.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "Placement Document" (PDF). Shyam Metalics and Power Limited. Retrieved 09 January 2024.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "Shyam Metalics and Energy Limited" (PDF). Chittorgarh. Retrieved 09 January, 2024.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "Press Release" (PDF). Care Ratings. 04 January 2023. Retrieved 09 January, 2024.
{{cite web}}
: Check date values in:|access-date=
and|date=
(help)CS1 maint: url-status (link) - ↑ Bureau, Our (2021-09-27). "Shyam Metalics and Energy Ltd allocates ₹2,960 crore to scale up production". BusinessLine. Retrieved 2024-01-09.
- ↑ 6.00 6.01 6.02 6.03 6.04 6.05 6.06 6.07 6.08 6.09 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17 6.18 6.19 6.20 6.21 6.22 6.23 6.24 https://web.archive.org/web/20240115054903/https://www.shyammetalics.com/production-facilities/sambalpur-plant/. Archived from the original on 15 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 7.00 7.01 7.02 7.03 7.04 7.05 7.06 7.07 7.08 7.09 7.10 7.11 7.12 7.13 7.14 7.15 7.16 7.17 7.18 (PDF) https://www.shyammetalics.com/wp-content/themes/shyam/assets/investors/qip/placement-document.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 8.2 (PDF) https://web.archive.org/web/20240115072508/https://backoffice.phillipcapital.in/Backoffice/Researchfiles/PC_-__Shyam_Metaliks_IPO_Note_20210613131203.pdf. Archived from the original (PDF) on 15 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 9.0 9.1 https://web.archive.org/web/20240115054740/https://www.livemint.com/market/stock-market-news/shyam-metalics-up-56-from-its-ipo-price-icici-securities-sees-another-sharp-rise-in-the-metal-stock-heres-why-11700027859385.html. Archived from the original on 15 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 10.0 10.1 https://web.archive.org/web/20240115061205/https://www.businesstoday.in/markets/company-stock/story/shyam-metalics-and-energy-shares-rise-record-high-july-sales-393404-2023-08-09. Archived from the original on 15 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 11.00 11.01 11.02 11.03 11.04 11.05 11.06 11.07 11.08 11.09 11.10 11.11 11.12 11.13 11.14 11.15 11.16 11.17 11.18 11.19 11.20 11.21 11.22 11.23 11.24 11.25 (PDF) https://environmentclearance.nic.in/writereaddata/Online/TOR/29_May_2018_203914070VIJAZUVAShyamTFR.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20240115050658/https://www.shyammetalics.com/production-facilities/jamuria-plant/. Archived from the original on 15 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 13.0 13.1 https://www.shyammetalics.com/sponge-iron/#.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 14.0 14.1 14.2 14.3 14.4 14.5 (PDF) https://www.shyammetalics.com/wp-content/themes/shyam/assets/investors/qip/Shyam-Metalics-and-Energy-Limited-PPD.pdf.
{{cite web}}
: Missing or empty|title=
(help)