Shymkent CHP-3 power station
Part of the Global Oil and Gas Plant Tracker, a Global Energy Monitor project. |
Related categories: |
Shymkent CHP-3 power station (Шымкентская ТЭЦ-3, ТЭЦ АО "3-Энергоорталык") is an operating power station of at least 160-megawatts (MW) in Shymkent, Sayram, Turkistan, Kazakhstan with multiple units, some of which are not currently operating. It is also known as Tchimkent, Shymkent HPP.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Shymkent CHP-3 power station | Shymkent, Sayram, Turkistan, Kazakhstan | 42.27335, 69.693644 (exact)[1][2] |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- CC1, ST1, ST2: 42.27335, 69.693644
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year |
---|---|---|---|---|---|---|
CC1 | Pre-construction[3][4][5][6] | fossil gas: natural gas[7][8] | 556[9] | combined cycle[7][2] | yes[5][9] | – |
ST1 | Operating[10][2] | fossil gas: natural gas, fossil liquids: fuel oil[11][12][2][9] | 80[13][11][9] | steam turbine[13] | yes[11][2][9] | 1980[2] |
ST2 | Operating[10][2] | fossil gas: natural gas, fossil liquids: fuel oil[11][12][2][9] | 80[13][11][9] | steam turbine[13] | yes[11][2][9] | 1985[2] |
CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
CC1 | 3-Energoortalyk JSC [100%][10][7] | Eurasian Resources Group SARL [100.0%] |
ST1 | 3-Energoortalyk JSC [100%][10][7] | Eurasian Resources Group SARL [100.0%] |
ST2 | 3-Energoortalyk JSC [100%][10][7] | Eurasian Resources Group SARL [100.0%] |
Background
There is a proposal to increase generating capacity through construction of a new 450 MW combined cycle unit.[14] This project was included in the "Comprehensive development plan for the city of Shymkent until 2023" which was adopted by the government in July 2019.[15] In October 2020, it was reported that to facilitate a detailed assessment of the project, a contract was signed for the development of a feasibility study.[16] There have been no updates as of April 2023. The proposal has not been mentioned in the "Comprehensive development plan for the city of Shymkent for the years 2021-2025".[17]
In October 2023, it was reported that construction of a combined cycle unit of 556 MW was being considered on the territory of the power station. A contract has been signed to develop a feasibility study, and project estimation work was in progress. Previously, a delegation from China had visited Shymkent to further discuss the project in detail.[18]
In February 2024, Ministry of Energy of Kazakhstan released "Electric Power Industry Development Plan until 2035", which included construction of a new 500-MW power plant in Shymkent. The plant is expected to be commissioned in 2028.[19] The new unit was mentioned again in the "National Infrastructure Plan of the Republic of Kazakhstan until 2029" released in June 2024. [20] Neither document mentions Shymkent CHP-3 as a site for the construction, which means that the original project might be shelved. The new plant - Aksa Enerji Shymkent power station - will be built by Turkish company Aksa Energy and will have a capacity of up to 500 MW.[21]
Articles and Resources
References
- ↑ https://www.google.com/maps/place/Tets-3,+3-Energoortalyk/@42.2727166,69.6916681,449m/data=!3m1!1e3!4m5!3m4!1s0x38a8e06d39e722ed:0x234cd1a84339398d!8m2!3d42.2727682!4d69.6937221.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 https://web.archive.org/web/20220126112931/https://tengrinews.kz/money/shyimkentskaya-tets-otmechaet-40-letniy-yubiley-423563/. Archived from the original on 2022-01-26.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://web.archive.org/web/20230107000447/http://www.eurasianresources.lu/uploads/1/files/20077_ERG_SR%20ENG%20web2.pdf. Archived from the original (PDF) on 2023-01-07.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220517154553/https://forbes.kz/process/urbanity/nepalskiy_milliarder_hochet_stroit_v_shyimkente_disneylend/. Archived from the original on 2022-05-17.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 5.0 5.1 https://web.archive.org/web/20210702225240/https://gastopowerjournal.com/item/9883-funding-secured-for-kazah-chp-project. Archived from the original on 2021-07-02.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220709172706/https://vera.kz/istoriya-o-tom-kak-v-shymkente-likvidiruyut-deficit-elektroenergii/. Archived from the original on 2022-07-09.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 7.0 7.1 7.2 7.3 7.4 (PDF) https://web.archive.org/web/20210702223725/https://invest.warmia.mazury.pl/images/ERG_Capital_Projects_ERG_Investment_Projects_ENG.pdf. Archived from the original (PDF) on 2021-07-02.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20210702223112/https://www.primeminister.kz/en/news/v-pravitelstve-rk-prinyat-kompleksnyy-plan-razvitiya-goroda-shymkent-do-2023-goda. Archived from the original on 2021-07-02.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 9.0 9.1 9.2 9.3 9.4 9.5 9.6 9.7 https://yujanka.kz/otoplenie-budet-vovremya-shymkentskaya-tets-3-gotova-k-rabote/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 10.0 10.1 10.2 10.3 10.4 https://web.archive.org/web/20221231113408/https://eurasianresources.lu/en/pages/all-enterprises/3-energoortalyk-jsc. Archived from the original on 2022-12-31.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 11.0 11.1 11.2 11.3 11.4 11.5 (PDF) https://web.archive.org/web/20210702231008/https://esmap.org/sites/default/files/esmap-files/Rpt_199b97_kazakvol2.pdf. Archived from the original (PDF) on 2021-07-02.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 12.0 12.1 (PDF) https://web.archive.org/web/20221220073522/https://www.eurasianresources.lu/uploads/1/files/ERG%20SR%202019%20WEB.pdf. Archived from the original (PDF) on 2022-12-20.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 13.0 13.1 13.2 13.3 https://web.archive.org/web/20220520005442/https://bbgl.ru/station/505. Archived from the original on 2022-05-20.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "Шымкентская ТЭЦ отмечает 40-летний юбилей". Главные новости Казахстана - Tengrinews.kz. December 22, 2020. Archived from the original on July 2, 2021. Retrieved January 29, 2022.
- ↑ Горбунова, Арина (July 9, 2019). "Непальский миллиардер хочет строить в Шымкенте «Диснейленд»". Archived from the original on May 17, 2022. Retrieved July 11, 2022.
- ↑ "Нурлан Ногаев побывал в энергопроизводящих организациях Шымкента и Кентау". Erg.kz. Oct 27, 2020. Retrieved May 26, 2022.
- ↑ "ПЛАН РАЗВИТИЯ ГОРОДА ШЫМКЕНТ НА 2021-2025 ГОДЫ" (PDF).
{{cite web}}
: CS1 maint: url-status (link) - ↑ "ОТОПЛЕНИЕ БУДЕТ ВОВРЕМЯ: ШЫМКЕНТСКАЯ ТЭЦ-3 ГОТОВА К РАБОТЕ". yujanka.kz. October 11, 2023. Retrieved November 2, 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "План мероприятий по развитию электроэнергетической отрасли до 2035 года". www.gov.kz. February 20, 2024. Retrieved April 4, 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Об утверждении Национального инфраструктурного плана Республики Казахстан до 2029 года (Russian)". Adilet. July 25, 2024. Retrieved October 30, 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Турецкая компания построит в Шымкенте парогазовую установку мощностью до 500 МВт". КУРСИВ. April 25, 2024. Retrieved November 4, 2024.
{{cite web}}
: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.