Sichuan Dazhou Iron and Steel Group Co Ltd

From Global Energy Monitor
This article is part of the
Global Steel Plant Tracker, a project of Global Energy Monitor.
Download full dataset
Report an error
Sub-articles:

Sichuan Dazhou Iron & Steel Group Co Ltd (四川省达州钢铁集团有限责任公司) is a blast furnace-basic oxygen furnace (BF-BOF) steel plant operating in Tongchun District, Sichuan, China.

Location

The map below shows the exact location of the plant in Tongchun District, Sichuan, China:

Loading map...
  • Location: No. 25, Xihe Road, Tongchuan District, Dazhou City, Sichuan Province
  • Coordinates (WGS 84): 31.189450, 107.453099 (exact)

Background

The main construction of the company Relocation and Upgrading Project has commenced, and the "New Dazhou Steel" is scheduled to be completed and put into operation in 2024. The project plans to have an annual production capacity of 2.428 million tons of iron, 2.3 million tons of crude steel, and 2.25 million tons of steel. The total planned investment is 15 billion yuan.[1][2]

The proposed capacity replacement project plans to build 2 blast furnaces (2x1340m3) and two basic oxygen furnaces (2x100-tonne) in Maliu Town, Dachuan District, Dazhou City, Sichuan Province. It is expected to start production in December 2024 and eliminate the existing two blast furnaces (1x480m3, 1x1260m3) and two basic oxygen furnaces (2x120-tonne).[3]Construction started in June 2022.[4]

Plant Details

Table 1: General Plant Details

Phase Plant status Announced date Construction date Start date Pre-retirement announcement date Retired date Workforce size
Main plant Operating[5] 1997[5] 3854[5]
Closure Operating pre-retirement[6] 2021-09-22[6] 2025[6]
Expansion Construction[7] 2021-09[6] 2022-06[7] 2024[6]

Table 2: Ownership and Parent Company Information

Phase Parent company Parent company GEM ID Owner Owner company GEM ID
Main plant Beijing Fangda International Industrial Investment Co Ltd [69.3%]; other [24.6%]; China Cinda Asset Management Co Ltd [6.1%] E100000123261 [69.3%]; E100000001753 [24.6%]; E100000123329 [6.1%] Sichuan Dazhou Iron & Steel Group Co., Ltd.[5] E100000126249

Table 3: Process and Products

Phase Steel product category Steel products ISO 14001 Main production equipment Detailed production equipment
Main plant finished rolled[8] Hot-rolled ribbed steel bar series, high-speed wire rod and hot-rolled round steel[8] 2008-06-27 00:00:00[9] BF, BOF[6] 2 BOF (2x120-tonne)[6]
Closure finished rolled[8] Hot-rolled ribbed steel bar series, high-speed wire rod and hot-rolled round steel[8] BF, BOF[6] 2 BOF (2x120-tonne)[6]
Expansion finished rolled[8] Hot-rolled ribbed steel bar series, high-speed wire rod and hot-rolled round steel[8] BF, BOF[6] 2 BOF (2x100-tonne)[6]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Basic oxygen furnace steelmaking capacity Nominal crude steel capacity (total)
Main plant operating
Closure operating pre-retirement 2600 TTPA[6][6] 2600 TTPA[6][6]
Expansion construction 2300 TTPA[6][6] 2300 TTPA[6][6]

Table 5: Crude Iron Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Blast furnace capacity Nominal iron capacity (total)
Main plant operating
Closure operating pre-retirement 2070 TTPA[6][6] 2070 TTPA[6][6]
Expansion construction 2428 TTPA[6][6] 2428 TTPA[6][6]

Table 6: Upstream Products Production Capacities (thousand tonnes per annum)

Phase Sinter Coke
Main plant 4300 TTPA[10] 2100 TTPA[10]
Closure
Expansion

Table 7: Actual Crude Steel Production by Year (thousand tonnes per annum)

Year BOF Production Total (all routes)
2020 3078 TTPA[11] 3078 TTPA[11]
2021 [12] [12]
2022

Table 8: Actual Crude Iron Production by Year (thousand tonnes per annum)

Year BF Production Total (all routes)
2020 2480 TTPA[11] 2480 TTPA[11]
2021 [12] [12]
2022

Blast Furnace Details

Table 9: Blast Furnace Details

Unit name Status Announced date Construction date Start date Retired date Current size Current capacity (ttpa) Decarbonization technology Most recent relining
#3 operating pre-retirement[6] unknown unknown 2005-04-15 00:00:00[13] 2025-01[6] 480 m³[6] 570[6] unknown unknown
unknown operating pre-retirement[6] unknown unknown 2009-12-01 00:00:00[14] 2025-01[6] 1260 m³[6] 1500[6] unknown unknown
unknown construction[7] 2021-09[6] 2022-06-01 00:00:00[7] 2024[6] 1340 m³[6] 1214[6] unknown unknown
unknown construction[7] 2021-09[6] 2022-06-01 00:00:00[7] 2024[6] 1340 m³[6] 1214[6] unknown unknown

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. "达州钢铁搬迁升级项目主体工程开工 "新达钢"计划2024年竣工投产". 四川省人民政府办公厅. 2022-06-29. {{cite news}}: line feed character in |title= at position 17 (help)
  2. "达钢搬迁时间确定!". 搜狐. 2023-05-29.
  3. 四川省达州钢铁集团建设项目产能置换方案公告,四川省经济和信息化厅,September 22, 2021
  4. 我市举行方大集团达钢搬迁 升级项目主体工程开工仪式,达州日报,2022-6-29
  5. 5.0 5.1 5.2 5.3 https://web.archive.org/web/20220318144741/https://www.qcc.com/weblogin?back. Archived from the original on 18 March 2022. {{cite web}}: Missing or empty |title= (help)
  6. 6.00 6.01 6.02 6.03 6.04 6.05 6.06 6.07 6.08 6.09 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17 6.18 6.19 6.20 6.21 6.22 6.23 6.24 6.25 6.26 6.27 6.28 6.29 6.30 6.31 6.32 6.33 6.34 6.35 6.36 6.37 6.38 6.39 6.40 6.41 6.42 https://web.archive.org/web/20220319203000/https://m.mysteel.com/21/0922/17/0E5F0369D44A05D9_abc.html. Archived from the original on 19 March 2022. {{cite web}}: Missing or empty |title= (help)
  7. 7.0 7.1 7.2 7.3 7.4 7.5 http://www.dazhou.gov.cn/news-show-237831.html. {{cite web}}: Missing or empty |title= (help)
  8. 8.0 8.1 8.2 8.3 8.4 8.5 https://web.archive.org/web/20220319151645/http://www.dasteel.cn/html/ggfwzx/qyjj/. Archived from the original on 19 March 2022. {{cite web}}: Missing or empty |title= (help)
  9. https://web.archive.org/web/20231016142109/http://cx.cnca.cn/CertECloud/result/skipResultList?certNumber=&orgName=%E5%9B%9B%E5%B7%9D%E7%9C%81%E8%BE%BE%E5%B7%9E%E9%92%A2%E9%93%81%E9%9B%86%E5%9B%A2%E6%9C%89%E9%99%90%E8%B4%A3%E4%BB%BB%E5%85%AC%E5%8F%B8&fromIndex=true. Archived from the original on 16 October 2023. {{cite web}}: Missing or empty |title= (help)
  10. 10.0 10.1 https://web.archive.org/web/20220318080216/https://pccz.court.gov.cn/pcajxxw/pcgg/ggxq?id. Archived from the original on 18 March 2022. {{cite web}}: Missing or empty |title= (help)
  11. 11.0 11.1 11.2 11.3 https://web.archive.org/web/20240111052811/https://www.chyxx.com/shuju/202103/940451.html. Archived from the original on 11 January 2024. {{cite web}}: Missing or empty |title= (help)
  12. 12.0 12.1 12.2 12.3 https://web.archive.org/web/20240111053536/https://www.chyxx.com/shuju/202107/965054.html. Archived from the original on 11 January 2024. {{cite web}}: Missing or empty |title= (help)
  13. https://www.doc88.com/p-1106930454452.html. {{cite web}}: Missing or empty |title= (help)
  14. http://www.dazhou.gov.cn/xxgk-show-20844.html. {{cite web}}: Missing or empty |title= (help)