Sichuan Dazhou Iron and Steel Group Co Ltd
This article is part of the Global Steel Plant Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Sichuan Dazhou Iron & Steel Group Co Ltd (四川省达州钢铁集团有限责任公司) is a blast furnace-basic oxygen furnace (BF-BOF) steel plant operating in Tongchun District, Sichuan, China.
Location
The map below shows the exact location of the plant in Tongchun District, Sichuan, China:
- Location: No. 25, Xihe Road, Tongchuan District, Dazhou City, Sichuan Province
- Coordinates (WGS 84): 31.189450, 107.453099 (exact)
Background
The main construction of the company Relocation and Upgrading Project has commenced, and the "New Dazhou Steel" is scheduled to be completed and put into operation in 2024. The project plans to have an annual production capacity of 2.428 million tons of iron, 2.3 million tons of crude steel, and 2.25 million tons of steel. The total planned investment is 15 billion yuan.[1][2]
The proposed capacity replacement project plans to build 2 blast furnaces (2x1340m3) and two basic oxygen furnaces (2x100-tonne) in Maliu Town, Dachuan District, Dazhou City, Sichuan Province. It is expected to start production in December 2024 and eliminate the existing two blast furnaces (1x480m3, 1x1260m3) and two basic oxygen furnaces (2x120-tonne).[3]Construction started in June 2022.[4]
Plant Details
Table 1: General Plant Details
Phase | Plant status | Announced date | Construction date | Start date | Pre-retirement announcement date | Retired date | Workforce size |
---|---|---|---|---|---|---|---|
Main plant | Operating[5] | – | – | 1997[5] | – | – | 3854[5] |
Closure | Operating pre-retirement[6] | – | – | – | 2021-09-22[6] | 2025[6] | – |
Expansion | Construction[7] | 2021-09[6] | 2022-06[7] | 2024[6] | – | – | – |
Table 2: Ownership and Parent Company Information
Phase | Parent company | Parent company GEM ID | Owner | Owner company GEM ID |
---|---|---|---|---|
Main plant | Beijing Fangda International Industrial Investment Co Ltd [69.3%]; other [24.6%]; China Cinda Asset Management Co Ltd [6.1%] | E100000123261 [69.3%]; E100000001753 [24.6%]; E100000123329 [6.1%] | Sichuan Dazhou Iron & Steel Group Co., Ltd.[5] | E100000126249 |
Table 3: Process and Products
Phase | Steel product category | Steel products | ISO 14001 | Main production equipment | Detailed production equipment |
---|---|---|---|---|---|
Main plant | finished rolled[8] | Hot-rolled ribbed steel bar series, high-speed wire rod and hot-rolled round steel[8] | 2008-06-27 00:00:00[9] | BF, BOF[6] | 2 BOF (2x120-tonne)[6] |
Closure | finished rolled[8] | Hot-rolled ribbed steel bar series, high-speed wire rod and hot-rolled round steel[8] | – | BF, BOF[6] | 2 BOF (2x120-tonne)[6] |
Expansion | finished rolled[8] | Hot-rolled ribbed steel bar series, high-speed wire rod and hot-rolled round steel[8] | – | BF, BOF[6] | 2 BOF (2x100-tonne)[6] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Basic oxygen furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|---|
Main plant | operating | – | – |
Closure | operating pre-retirement | 2600 TTPA[6][6] | 2600 TTPA[6][6] |
Expansion | construction | 2300 TTPA[6][6] | 2300 TTPA[6][6] |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Blast furnace capacity | Nominal iron capacity (total) |
---|---|---|---|
Main plant | operating | – | – |
Closure | operating pre-retirement | 2070 TTPA[6][6] | 2070 TTPA[6][6] |
Expansion | construction | 2428 TTPA[6][6] | 2428 TTPA[6][6] |
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Phase | Sinter | Coke |
---|---|---|
Main plant | 4300 TTPA[10] | 2100 TTPA[10] |
Closure | – | – |
Expansion | – | – |
Table 7: Actual Crude Steel Production by Year (thousand tonnes per annum)
Year | BOF Production | Total (all routes) |
---|---|---|
2020 | 3078 TTPA[11] | 3078 TTPA[11] |
2021 | –[12] | –[12] |
2022 | – | – |
Table 8: Actual Crude Iron Production by Year (thousand tonnes per annum)
Year | BF Production | Total (all routes) |
---|---|---|
2020 | 2480 TTPA[11] | 2480 TTPA[11] |
2021 | –[12] | –[12] |
2022 | – | – |
Blast Furnace Details
Table 9: Blast Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Retired date | Current size | Current capacity (ttpa) | Decarbonization technology | Most recent relining |
---|---|---|---|---|---|---|---|---|---|
#3 | operating pre-retirement[6] | unknown | unknown | 2005-04-15 00:00:00[13] | 2025-01[6] | 480 m³[6] | 570[6] | unknown | unknown |
unknown | operating pre-retirement[6] | unknown | unknown | 2009-12-01 00:00:00[14] | 2025-01[6] | 1260 m³[6] | 1500[6] | unknown | unknown |
unknown | construction[7] | 2021-09[6] | 2022-06-01 00:00:00[7] | 2024[6] | – | 1340 m³[6] | 1214[6] | unknown | unknown |
unknown | construction[7] | 2021-09[6] | 2022-06-01 00:00:00[7] | 2024[6] | – | 1340 m³[6] | 1214[6] | unknown | unknown |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
References
- ↑ "达州钢铁搬迁升级项目主体工程开工 "新达钢"计划2024年竣工投产". 四川省人民政府办公厅. 2022-06-29.
{{cite news}}
: line feed character in|title=
at position 17 (help) - ↑ "达钢搬迁时间确定!". 搜狐. 2023-05-29.
- ↑ 四川省达州钢铁集团建设项目产能置换方案公告,四川省经济和信息化厅,September 22, 2021
- ↑ 我市举行方大集团达钢搬迁 升级项目主体工程开工仪式,达州日报,2022-6-29
- ↑ 5.0 5.1 5.2 5.3 https://web.archive.org/web/20220318144741/https://www.qcc.com/weblogin?back. Archived from the original on 18 March 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 6.00 6.01 6.02 6.03 6.04 6.05 6.06 6.07 6.08 6.09 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17 6.18 6.19 6.20 6.21 6.22 6.23 6.24 6.25 6.26 6.27 6.28 6.29 6.30 6.31 6.32 6.33 6.34 6.35 6.36 6.37 6.38 6.39 6.40 6.41 6.42 https://web.archive.org/web/20220319203000/https://m.mysteel.com/21/0922/17/0E5F0369D44A05D9_abc.html. Archived from the original on 19 March 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 7.0 7.1 7.2 7.3 7.4 7.5 http://www.dazhou.gov.cn/news-show-237831.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 8.2 8.3 8.4 8.5 https://web.archive.org/web/20220319151645/http://www.dasteel.cn/html/ggfwzx/qyjj/. Archived from the original on 19 March 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20231016142109/http://cx.cnca.cn/CertECloud/result/skipResultList?certNumber=&orgName=%E5%9B%9B%E5%B7%9D%E7%9C%81%E8%BE%BE%E5%B7%9E%E9%92%A2%E9%93%81%E9%9B%86%E5%9B%A2%E6%9C%89%E9%99%90%E8%B4%A3%E4%BB%BB%E5%85%AC%E5%8F%B8&fromIndex=true. Archived from the original on 16 October 2023.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 10.0 10.1 https://web.archive.org/web/20220318080216/https://pccz.court.gov.cn/pcajxxw/pcgg/ggxq?id. Archived from the original on 18 March 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 11.0 11.1 11.2 11.3 https://web.archive.org/web/20240111052811/https://www.chyxx.com/shuju/202103/940451.html. Archived from the original on 11 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 12.0 12.1 12.2 12.3 https://web.archive.org/web/20240111053536/https://www.chyxx.com/shuju/202107/965054.html. Archived from the original on 11 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://www.doc88.com/p-1106930454452.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ http://www.dazhou.gov.cn/xxgk-show-20844.html.
{{cite web}}
: Missing or empty|title=
(help)