Surakachhar 3&4 Coal Mine is an operating coal mine in Korba, Chhattisgarh, India.
Location
Table 1: Project-level location details
Mine Name | Location | Coordinates (WGS 84) |
---|---|---|
Surakachhar 3&4 Coal Mine | Korba, Chhattisgarh, India | 22.367844, 82.63224 (exact) |
The map below shows the exact location of the coal mine:
Project Details
Table 2: Project status
Status | Status Detail | Opening Year | Closing Year |
---|---|---|---|
Operating | – | – | – |
Operating | – | 1964 | – |
Operating[1] | – | 1977[1] | – |
Table 3: Operation details
Capacity (Mtpa) | Production (Mtpa) | Year of Production | Mine Type | Mining Method | Mine Size (km2) | Mine Depth (m) | Workforce Size |
---|---|---|---|---|---|---|---|
– | 0.03[2] | 2022[2] | Underground | Bord and Pillar[1] | 10.46[1] | 300* | 705* |
– | 0.03[2] | 2022[2] | Underground | Bord and Pillar[1] | 10.46[1] | 300* | 615* |
0[1] | 0.056[1] | 2022[1] | Underground | Bord and Pillar[1] | 10.46[1] | 300* | 585* |
Table 4: Coal resources and destination
Total Reserves (Mt) | Year of Total Reserves Recorded | Total Resources (Mt) | Coalfield | Coal Type | Coal Grade | Primary Consumer/ Destination |
---|---|---|---|---|---|---|
1.586[1] | 2023[1] | 3.02[1] | Korba | Subbituminous | Thermal | Chandrapur Thermal Power Station |
2.25[1] | 2023[1] | 11.24[1] | Korba | Subbituminous | Thermal | SAIL Bhilai steel plant |
4[1] | 2023[1] | 14[1] | Korba | Subbituminous | Thermal | Chandrapur Thermal Power Station |
Table 5: Ownership and parent company
Owner | Parent Company | Headquarters |
---|---|---|
South Eastern Coalfields Ltd | Coal India Ltd [100.0%] | India |
South Eastern Coalfields Ltd | Coal India Ltd [100.0%] | India |
South Eastern Coalfields Ltd | Coal India Ltd [100.0%] | India |
Note: The above section was automatically generated and is based on data from the Global Coal Mine Tracker April 2024 release and the September supplement.
Background
The Surakachhar coal mine is a mine complex, operated by South Eastern Coalfields Limited, a subsidiary of Coal India, in Korba, Chhattisgarh, India.[3]
The complex include the Surakachhar main coal mine and Surakachhar 3&4 coal mine. The Surakachhar coal mine has a designed capacity of 0.21 million tonnes-per-annum (MTPA) on a mining lease area of 1045.86 ha.[3] The project is an old project operating since 1963-64, prior to natioalisation of mines, on the consent letters under the Water ACt 1974 and Air ACt 1981, which has been further extended till 31 July, 2010. The project is awaiting environment clearance for a proposed expansion in capacity 0.456 MT on the exisiting mining lease.
Main consumers for the Surakachhar UG coal mine project are SAIL Bhilai steel plant, Chandrapur power station, KRPH (Koradih, Khaparkheda) and Birsinghpur Power Plant.[4]
- Sponsor: South Eastern Coalfields Limited[3]
- Parent company: Coal India
- Location: Korba, Chhattisgarh, India
- Coordinates: 22.367844, 82.63224 (exact)[3]
- Status: Operating[5]
- Capacity: 0.45 MTPA[3]
- Production: Main mine - 0.19 million tonnes (2020); 3&4 mine - 0.1 million tonnes (2020)
- Reserves: 18.753 MT, remianing extractable 7.83 MT[5]
- In service: 1964[5]
- Permits: Mining Closure Plan for the Project and other documents, SECL, 2018
- Coal type: Non-coking
- Mining method: Underground[4]
- Source of financing:
Expansion Details
- Status: Shelved
- Size of Expansion: 0.456 MT
- Permits and Applications: Form 1 application for expansion to MoEF&CC, India, SECL, 2018
Articles and Resources
Additional data
To access additional data, including an interactive map of world coal mines, a downloadable dataset, and summary data, please visit the Global Coal Mine Tracker on the Global Energy Monitor website.
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 (PDF) https://web.archive.org/web/20240109002409/https://environmentclearance.nic.in/writereaddata/Online/TOR/13_Jul_2023_12164995341877752Annexure-Pre-feasibilityReport%2528PFR%2529File.pdf. Archived from the original (PDF) on 09 January 2024.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ 2.0 2.1 2.2 2.3 (PDF) https://web.archive.org/web/20240129173121/https://coal.nic.in/sites/default/files/2023-05/23-05-2023.pdf. Archived from the original (PDF) on 29 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 3.0 3.1 3.2 3.3 3.4 TOR, April 10, 2018
- ↑ 4.0 4.1 Minutes of 48th EAC meeting, MoEF&CC India, 4 October 2019
- ↑ 5.0 5.1 5.2 Mining Closure Plan for the Project and other documents, SECL, 2018