Porto de Sergipe power station
Part of the Global Oil and Gas Plant Tracker, a Global Energy Monitor project. |
Related categories: |
Porto de Sergipe power station (Usina Termelétrica Porto de Sergipe) is an operating power station of at least 1593-megawatts (MW) in Barra dos Coqueiros, Sergipe, Brazil with multiple units, some of which are not currently operating.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Porto de Sergipe power station | Barra dos Coqueiros, Sergipe, Brazil | -10.815646, -36.937062 (exact)[1] |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- I, III, IV, V: -10.815646, -36.937062
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year |
---|---|---|---|---|---|---|
I | Operating[2][3] | fossil gas: LNG[4] | 1593[5][6] | combined cycle[3][7][8] | not found | 2020[3][1] |
III | Announced[9][10] | fossil gas: LNG[11][12] | 400[11][13][14][15] | unknown | not found | – |
IV | Announced[9][10] | fossil gas: LNG[11][12] | 617[11][13][14][15] | unknown | not found | – |
V | Announced[9][10] | fossil gas: LNG[11][12] | 299[11][13][14][15] | unknown | not found | – |
CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.
Table 3: Unit-level ownership and operator details
Unit name | Operator | Owner | Parent |
---|---|---|---|
I | CELSE - Centrais Elétricas de Sergipe[11][1] | Eneva SA [100%][9][16] | Eneva SA [100.0%] |
III | CELSE - Centrais Elétricas de Sergipe[11][1] | Eneva SA [100%][9][16] | Eneva SA [100.0%] |
IV | CELSE - Centrais Elétricas de Sergipe[11][1] | Eneva SA [100%][9][16] | Eneva SA [100.0%] |
V | CELSE - Centrais Elétricas de Sergipe[11][1] | Eneva SA [100%][9][16] | Eneva SA [100.0%] |
Background
The Porto de Sergipe I power station, which began commercial operations in March 2020[17], was originally owned by a consortium headed by New Fortress Energy[18]; in October 2022 Eneva SA acquired 100% ownership of the plant.[19] The project is fueled with liquefied natural gas imported through the Sergipe FSRU LNG terminal.[20]
As of October 2022, Eneva SA was contemplating future development of three additional units (Porto Sergipe III, IV and V) depending on market conditions.[21]
Articles and Resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 "SIGA - Sistema de Informações de Geração da ANEEL". Agência Nacional de Energia Elétrica (ANEEL). 2023. Archived from the original on 2024-01-25. Retrieved 2023-10-10.
- ↑ "SIGA - Sistema de Informações de Geração da ANEEL - Dados Abertos - Agência Nacional de Energia Elétrica". ANEEL. Archived from the original on 2024-01-25.
- ↑ 3.0 3.1 3.2 https://web.archive.org/web/20240125105121/https://eneva.com.br/nossos-negocios/geracao-de-energia/ute-porto-de-sergipe-i/. Archived from the original on 2024-01-25.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20240125090805/https://eneva.com.br/nossos-negocios/geracao-de-energia/ute-porto-de-sergipe-i/. Archived from the original on 2024-01-25.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20240125090149/https://dadosabertos.aneel.gov.br/dataset/siga-sistema-de-informacoes-de-geracao-da-aneel/resource/76310626-e2e0-4880-b199-d63fe287f279. Archived from the original on 2024-01-25.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) http://energiaeambiente.org.br/wp-content/uploads/2022/12/termeletricas_IEMA_2021.pdf https://eneva.com.br/nossos-negocios/geracao-de-energia/ute-porto-de-sergipe-i/. http://energiaeambiente.org.br/wp-content/uploads/2022/12/termeletricas_IEMA_2021.pdf.
{{cite web}}
: Check|url=
value (help); Missing or empty|title=
(help) - ↑ (PDF) https://web.archive.org/web/20240124233259/https://energiaeambiente.org.br/wp-content/uploads/2022/12/termeletricas_IEMA_2021.pdf. Archived from the original (PDF) on 2024-01-24.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://web.archive.org/web/20240125112148/https://www.idbinvest.org/sites/default/files/2018-03/anexo_ii._atm_1.pdf. Archived from the original (PDF) on 2024-01-25.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 9.0 9.1 9.2 9.3 9.4 9.5 9.6 "Company Presentation - March 2023". Eneva. 2023-03-31. Archived from the original on 2024-05-10.
- ↑ 10.0 10.1 10.2 https://eixos.com.br/empresas/eneva-avalia-leilao-de-reserva-de-capacidade-para-expandir-projeto-da-celse/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 11.0 11.1 11.2 11.3 11.4 11.5 11.6 11.7 11.8 11.9 https://web.archive.org/web/20240125082715/https://api.mziq.com/mzfilemanager/v2/d/6c663f3b-ae5a-4692-81d3-ab23ee84c1de/229c7257-3e2d-a00f-6a84-7a6991a69a88?origin=1. Archived from the original on 2024-01-25.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 12.0 12.1 12.2 https://web.archive.org/web/20240125090814/https://www.in.gov.br/web/dou/-/portaria-n-708-de-8-de-junho-de-2021-324789440. Archived from the original on 2024-01-25.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 13.0 13.1 13.2 https://web.archive.org/web/20240125100609/https://www.canalenergia.com.br/noticias/53213819/eneva-quer-inscrever-pipeline-da-celse-nos-leiloes-de-2022-e-2023. Archived from the original on 2024-01-25.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 14.0 14.1 14.2 (PDF) https://bullrun.com.br/rails/active_storage/blobs/proxy/eyJfcmFpbHMiOnsiZGF0YSI6MTAyMjMsInB1ciI6ImJsb2JfaWQifX0=--51d3fe4787cff051570da86d08aff6958a5818fe/10221.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 15.0 15.1 15.2 "Apresentação Corporativa - Março 2023". 2023-03-31. Archived from the original on 2024-01-25.
- ↑ 16.0 16.1 16.2 16.3 "SPE Centrais Elétricas de Sergipe". Eneva. Archived from the original on 2024-05-14. Retrieved 2024-05-10.
- ↑ "UTE Porto de Sergipe I". Celse - Centrais Elétricas de Sergipe S.A. Archived from the original on May 3, 2021. Retrieved May 4, 2021.
- ↑ "Q4 2020 Investor Presentation (pp 11, 36, 40)". New Fortress Energy. March 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Eneva conclui compra da Celse por R$ 6,7 bilhões, maior aquisição da história da companhia". Eneva SA. October 3, 2022.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "UTE Porto de Sergipe I". Eneva. Retrieved 2022-11-21.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Apresentação Corporativa (p 23)". Eneva. October 2022.
{{cite web}}
: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.