Yazdani Steel and Power Kalinganagar steel plant
This article is part of the Global Iron and Steel Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Yazdani Steel and Power Kalinganagar steel plant is a steel plant in Kalinganagar, Jajpur, Odisha, India that operates direct reduced iron (DRI) and steelmaking technology.
Location
The map below shows the exact location of the plant in Kalinganagar, Jajpur, Odisha, India:
- Location: Kalinganagar, Jajpur, India
- Coordinates (WGS 84): 20.928285, 86.036604 (exact)
Background
Yazdani Steel & Power Limited is a Public incorporated on 29 October 2003 as Dinabandhu Steel & Power Ltd.[1] The company was taken over by Yazdani International Pvt ltd in May 2011, subsequent to which it was renamed Yazdani Steel & Power Limited.[2] The plant plans to expand its capacity from 70 ttpa to 1190 ttpa with an investment of INR 2,415 crores.[3] The expansion plan was approved by Odisha Government in 2021.[4] As of 2025 December, there hasn't any updates.
Plant Details
Table 1: General Plant Details
Start date | Workforce size | Power source | Iron ore source | Coal source |
---|---|---|---|---|
2003[5] | 519[6] | 10 MW CPP (4 MW WHRB; 6 MW AFBC; Proposed to expand to 70 MW CPP (2x8 MW WHRB and 2x22 MW AFBC))[6][7] | Joda[6] | Imported via Paradip port[6] |
Table 2: Ownership and Parent Company Information
Parent company | Parent company PermID | Parent company GEM ID | Owner | Owner company PermID | Owner company GEM ID |
---|---|---|---|---|---|
Serajuddin & Co | 5001423902 | E100001016270 | Yazdani Steel and Power Ltd [100%][5] | 5068656453 | E100001012099 [100%] |
Table 3: Process and Products
Steel product category | Steel products | Steel sector end users | ISO 14001 | ISO 50001 | Main production equipment |
---|---|---|---|---|---|
finished rolled[6] | billet, bar[6] | building and infrastructure[6] | unknown | unknown | DRI; Steel other/unspecified |
Table 4: Plant-level Crude Steel Production Capacities (thousand tonnes per annum)
Capacity operating status1 | Other/unspecified steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|
announced | 1080[8][6] | 1080[8][6] |
operating | 110[6][7] | 110[6][7] |
Table 5: Plant-level Crude Iron Production Capacities (thousand tonnes per annum)
Capacity operating status1 | Sponge iron/DRI capacity | Nominal iron capacity (total) |
---|---|---|
announced | 256[6][7] | 256[6][7] |
operating | 72[6][7] | 72[6][7] |
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Ferronickel | Sinter | Coke | Pellets |
---|---|---|---|
NF | NF | NF | NF |
Table 7: Actual Plant-level Crude Steel Production by Year (thousand tonnes per annum)
Year | Other/unknown steel production |
---|---|
2020 | unknown |
2021 | unknown |
2022 | unknown |
2023 | unknown |
Table 8: Actual Plant-level Crude Iron Production by Year (thousand tonnes per annum)
Year | DRI production | Other/unknown iron production |
---|---|---|
2019 | unknown | unknown |
2020 | unknown | unknown |
2021 | unknown | unknown |
2022 | unknown | unknown |
2023 | unknown | unknown |
Unit Details
Table 9: Direct Reduced Iron Furnace Details
Unit name | Status | Announced date | Start date | Furnace type | Current capacity (ttpa) | Reductant |
---|---|---|---|---|---|---|
unknown DRI (1) | operating[5] | – | 2003[5] | rotary kiln[6] | 36[6][7] | coal[7] |
unknown DRI (2) | operating[5] | – | 2003[5] | rotary kiln[6] | 36[6][7] | coal[7] |
unknown DRI (3) | announced[7] | 2018[9] | – | rotary kiln[6] | 128[6][7] | coal[6][7] |
unknown DRI (4) | announced[7] | 2018[9] | – | rotary kiln[6] | 128[6][7] | coal[6][7] |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Iron and Steel Tracker on the Global Energy Monitor website.
References
- ↑ "Basic Information". Zauba Corp. 07 May, 2023. Retrieved 17 October, 2023.
{{cite web}}
: Check date values in:|access-date=
and|date=
(help)CS1 maint: url-status (link) - ↑ "Final EIA/EMP Report". MoEF&CC. July 2022. Retrieved 11 January 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ Cite error: Invalid
<ref>
tag; no text was provided for refs named:0
- ↑ Pioneer, The. "Odisha needs tactical initiatives to meet steel output target". The Pioneer. Retrieved 2024-12-05.
- ↑ 5.0 5.1 5.2 5.3 5.4 5.5 https://www.zaubacorp.com/company/YAZDANI-STEEL-POWER-LIMITED/U27102OR2003PLC007354.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 6.00 6.01 6.02 6.03 6.04 6.05 6.06 6.07 6.08 6.09 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17 6.18 6.19 6.20 6.21 6.22 6.23 6.24 (PDF) https://environmentclearance.nic.in/writereaddata/Online/TOR/22_Feb_2019_165624717BRW1Q5TEPre-FeasibilityReport.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 7.00 7.01 7.02 7.03 7.04 7.05 7.06 7.07 7.08 7.09 7.10 7.11 7.12 7.13 7.14 7.15 7.16 https://web.archive.org/web/20240923212325/https://environmentclearance.nic.in/DownloadPfdFile.aspx?FileName=hH93gz76f6yPOaSbn7PCTae3e+oMkidNoi6mXyrVSa0FwEhThGNjQe9pFy0RJkLtShKTUWGq3+ovGAOhl6qKC67v1ebfghMnhf9J5UJtie4=&FilePath=93ZZBm8LWEXfg+HAlQix2fE2t8z%252FpgnoBhDlYdZCxzVPEh4a7F53Cae7tleKGoXIDiA7chYePNgRJpehWx3dLsaLaee8RS5VxBvVdCAnIMg=. Archived from the original on 23 September 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 https://web.archive.org/web/20210421081752/https://timesofindia.indiatimes.com/city/bhubaneswar/odisha-approves-8-investment-proposals-worth-rs-6400-crore/articleshow/80138282.cms. Archived from the original on 2021-04-21.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 9.0 9.1 https://web.archive.org/web/20240115055327/https://www.projectstoday.com/News/Yazdani-Steel--Power-awaits-clearance-to-augment-steel-capacity. Archived from the original on 2024-01-15.
{{cite web}}
: Missing or empty|title=
(help)