Yunnan Gas Pipeline Network

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Yunnan Gas Pipeline Network is a pipeline network in Yunnan Province, China, with segments that are proposed, in construction, and operating.

Location

Loading map...

Network Background

On July 28, 2013, Sino-Myanmar Gas Pipeline began operating. [1]Yunnan was the first province to receive gas along the pipeline. In 2012, Yunnan province initiated the construction of its gas pipeline network, based on the gas supply from the Sino-Myanmar Gas Pipeline and a small amount of local shale gas.[2] By 2016, 6 gas pipelines had been completed. Three years later, 28 gas pipelines were completed, bringing the total pipeline mileage to 2634 kilometers.[3]

Yunnan Major Energy Project lay-out in 14th FYP.png

截至2019年,已建成天然气干支线管道28条,总里程达2634公里。全省天然气消费量从2016年的7.4亿方增长至2019年的18.79亿方,其中缅气从2016年的1.32亿方增长至2019年的10.35亿方,增长近7倍。2019年全省天然气消费量18.79亿方,同比增长21.6%,其中缅气10.35亿方,同比增长17.61%。[3]

In Yunnan's 13th Five-Year Plan on Energy issued in October 2016, it laid out 7 gas pipeline proposals. A detailed list of proposed pipelines is at the sidebar. [4]

In February 2021, Yunnan province issued its 14th Five-Year Plan, in which it set a goal of 5000 kilometers gas pipeline by 2025. [5] A map of the major energy projects including gas pipelines is also attached.

Energy major project--14th FYP of Yunnan.png

The province tries to diversify its gas source. In 2021, a gas pipeline from Guangxi to Yunnan (Baise-Wenshan gas pipeline (百色—文山)was proposed. It will bring gasified LNG to Yunnan.[6]

Network details

云南省天然气省内支线重点项目-十三五能源规划.png

Luxi–Mile–Kaiyuan Branch 泸西-弥勒-开远天然气支线管道

Loading map...
  • Owner: Honghe Nengtou Natural Gas Industry Development Co., Ltd. 红河能投天然气产业发展有限公司
  • Capacity: 0.60 billion cubic meters per year
  • Length: 156.83 kilometers[7]
    • Segment I: 68.6 kilometers[8]
    • Segment II: 88.23 kilometers[7]
  • Diameter:
    • Segment I: 400 millimeters[7]
  • Status:
    • Segment I: Operating[8]
    • Segment II: Construction[9]
  • Start year: 2022[9]
    • Segment I: 2020[10]
    • Segment II:
  • Cost: 593 million RMB

The pipeline was proposed in 2016.[4]

Baoshan–Nujiang Branch 怒江天然气支线管道 (保山-怒江)

Loading map...
  • Owner: Yunnan Provincial energy investment Group Co., Ltd[11]
  • Capacity: 0.18 billion cubic meters per year[12]
  • Length: 120 kilometers[12]
  • Diameter:
  • Status: Proposed[13]
  • Start year:
  • Cost: 180 million RMB


The pipeline was proposed in 2016 and was proposed again in 2023.

Lijiang–Diqing Branch 迪庆天然气支线管道 (丽江-迪庆香格里拉)

Loading map...
  • Owner: Yunnan Provincial energy investment Group Co., Ltd[11]
  • Capacity: 0.23 billion cubic meters per year[14]
  • Length: 172 kilometers[14]
  • Diameter: 300 millimeters[14]
  • Status: Proposed[15]
  • Start year:
  • Cost: 261 million RMB

The pipeline was proposed in 2016, permitted in 2017, and was slated to become operational in 2018.[16] However, by March 2021 the construction had not yet begun, owing to financial difficulties of the sponsor company.[17] The pipeline was mentioned most recently in the Yunnan Province 14th Five-Year Plan.[18]

Yuxi–Pu'er Branch 普洱天然气支线管道 (玉溪-普洱)

Loading map...
  • Owner:
  • Capacity:
  • Length: 307 kilometers
    • Phase I: 81.2 kilometers[19]
    • Phase II: 225.8 kilometers
  • Diameter:
    • Phase I: 300 millimeters[19]
  • Status:
    • Phase I: Operating[19]
    • Phase II: Proposed[20]
  • Start year:
    • Phase I: 2018
    • Phase II:
  • Cost: 1.274 billion RMB
  • Financing:
  • Associated infrastructure: Lufeng–Yuxi Branch Pipeline of Sino-Myanmar Gas Pipeline[21]

Pu'er–Banna Branch 普洱-版纳天然气支线管道

Loading map...
  • Owner:
  • Capacity: 0.55 billion cubic meters per year
  • Length: 126 kilometers
  • Diameter:
  • Status: Proposed[20]
  • Start year:
  • Cost:

Qujing–Zhaotong Branch 昭通天然气支线管道 (曲靖-昭通)

Loading map...
  • Owner: Yunnan Energy Investment Co., Ltd
  • Capacity: 0.39 billion cubic meters per year
  • Length: 280 kilometers[22]
    • Phase I: 91.5 kilometers[23]
  • Diameter:
  • Status:
    • Phase I: Operating[24]
    • Phase II: Construction[24]
    • Phase III: Construction[24]
  • Start year:
  • Cost: 1.4 billion RMB

The pipeline was proposed in 2018.

Zhanyi–Luliang Branch 陆良天然气支线管道 (沾益-陆良)

Screenshot 2024-09-05 at 12.04.57 PM.png
Loading map...
  • Operator:
  • Owner: Qujing Nengtou Natural Gas Industry Development Co., Ltd.[25]
  • Parent company:
  • Capacity: 0.67 billion cubic meters per year
  • Length: 118 kilometers
  • Diameter: 400 mm[25]
  • Status: Operating[8]
  • Start year: 2020
  • Cost: 370 million RMB

The pipeline was proposed in 2016.

Kaiyuan–Mengzi Branch 开远-蒙自天然气支线管道

Loading map...
  • Owner: Yunnan Energy Investment Co., Ltd
  • Capacity: 0.49 billion cubic meters per year
  • Length: 85 kilometers[26]
  • Diameter: 406.4 mm[27]
  • Status: Operating[28]
  • Start year: 2024[28]
  • Cost: 530 million RMB[29]

Mengzi–Wenshan Branch 蒙自-文山天然气支线管道

Loading map...
  • Owner: Honghe Nengtou Natural Gas Industry Development Co., Ltd. 红河能投天然气产业发展有限公司
  • Capacity: 0.49 billion cubic meters per year
  • Length: 85 kilometers[7]
  • Diameter: 406.4 mm[30]
  • Status: Operating[31]
  • Start year: 2024[31]
  • Cost: 530 million RMB

Wenshan–Yanshan Branch 文山-砚山天然气支线管道

Screenshot 2024-09-04 at 11.18.23 AM.png
Loading map...
  • Owner: Yunnan Energy Investment Co., Ltd[32]
  • Capacity: 0.255 billion cubic meters per year[33]
  • Length: 88 kilometers[33]
  • Diameter: 400 millimeters[33]
  • Status: Operating[28]
  • Start year: 2024[28]
  • Cost: 403.40 million RMB[34]

Dali–Lincang Branch (Phase I) 临沧天然气支线管道一期 (大理南涧-临沧凤庆)

Screenshot 2024-09-04 at 12.38.41 PM.png
Loading map...
  • Owner: Lincang Nengxun Natural Gas Pipeline Co., Ltd. 临沧能迅天然气管道有限公司[35]
  • Capacity: 0.32 billion cubic meters per year
  • Length: 131.8 kilometers
  • Diameter: 273 millimeters
  • Status: Operating[36]
  • Start year: 2020[37]
  • Cost: 406 million RMB[37]

Construction on the pipeline began in 2018.[38]

Lincang Fengqing–Lincang Shuangjiang Branch (Phase II) 临沧天然气支线管道二期 (临沧凤庆-双江)

Loading map...
  • Owner:
  • Capacity:
  • Length: 172 kilometers[39]
  • Diameter:
  • Status: Proposed[40]
  • Start year:
  • Cost: 500 million RMB[41]

Shuifu–Zhaotong Branch 水富-昭通输气管道

Loading map...
  • Operator:
  • Owner: Yunnan Zhongcheng Gas Transmission and Distribution Co., Ltd.
  • Parent company:
  • Capacity: 0.50 billion cubic meters per year
  • Length: 260.5 kilometers[42]
  • Diameter: 355.6 mm[43]
  • Status: Operating[44]
  • Start year: 2017[44]
  • Cost: 508 million RMB[45]

Fumin–Changshui Branch 富民-长水支线输气管道

Loading map...
  • Owner: Yunnan PetroChina Kunlun Gas Co., Ltd.[46]
  • Capacity:
  • Length: 105.64 kilometers[47]
    • Fumin Segment: 10.88 kilometers[48]
  • Diameter:
  • Status: Operating[49]
    • Fumin Segment: Operating[50]
  • Start year: 2018[49]
    • Fumin Segment: 2018[48]
  • Cost:

Yuguopu–Laozhaixiang Branch (Wenshan Aluminum Smelter Pipeline) 雨过铺-老寨乡输气管道 (文山铝项目输气专线)

Loading map...
  • Operator:
  • Owner: Honghe Branch of Yunnan Zhonghui Energy Co., Ltd.[51]
  • Parent company:
  • Capacity: 0.165 bcm/y[51]
  • Length: 77 km[51]
  • Diameter: 273.1 mm[51]
  • Status: Operating[52]
  • Start year:
  • Cost: 218.67 million RMB[51]
  • Financing:
  • Associated infrastructure: Yunnan Gas Pipeline Network Honghe Branch[51]

Weixin–Zhenxiong–Yiliang–Zhaoyang Fracking Gas Pipeline 威信-镇雄-彝良-昭阳页岩气输送管道专线

Loading map...
  • Operator:
  • Owner: Yunnan Natural Gas Co., Ltd.[53]
  • Parent company:
  • Capacity: 1 billion cubic meters per year[54]
  • Length: 260 kilometers[54]
  • Diameter:
  • Status: Proposed[55]
  • Start year:
  • Cost: 1500 million RMB[53]

Yanjin–Daguan–Shaoyang Fracking Gas Pipeline 盐津(永善)-大关-昭阳页岩气输送管道

Loading map...
  • Owner:
  • Capacity: 2 billion cubic meters per year[54]
  • Length: 180 kilometers[54][54]
  • Diameter:
  • Status: Proposed[55]
  • Start year:
  • Cost:

Lubiao-Yimen Branch禄脿-易门天然气支线管道

Loading map...
  • Operator:
  • Owner: Yunnan Natural Gas Co., Ltd.[56]
  • Parent company:
  • Capacity: 0.45 billion cubic meters per year[56]
  • Length: 32.05 kilometers[56]
  • Diameter: 300mm[56]
  • Status: Operating[56]
  • Start year: 2018[56]
  • Cost: 204 million RMB[57]

Luxi-Shizong-Luoping Branch 泸西-师宗-罗平支线输气管道

Loading map...
  • Owner: Yunnan Natural Gas Co., Ltd.[58]
  • Capacity: 0.35 billion cubic meters per year[58]
  • Length: 88.28 kilometers[58]
  • Diameter: 323.9mm[58]
  • Status: Proposed[59]
  • Start year:
  • Cost: 384.54 million RMB

South Loop Pipeline (Wenshan-Honghe-Pu'er, Baoshan-Lincang)云南省南环线(文山-红河-普洱段、保山-临沧段)

It is a crucial link between the Sino-Myanmar Gas Pipeline and the Baise-Wenshan Gas Pipeline.[60]

Loading map...
  • Operater:
  • Owner: China Oil and Gas Pipeline Network Corporation Southwest Pipeline Co., Ltd.[60]
  • Parent:
  • Capacity: billion cubic meters per year
  • Length: kilometers
  • Diameter: mm
  • Status: Proposed[61]
  • Start year:
  • Cost:

Tengchong Branch 腾冲支线(龙陵-腾冲)

Loading map...
  • Operator:
  • Owner: Yunnan Petro-China Kunlun Gas Co., Ltd.[62]
  • Parent company:
  • Capacity: 0.15 billion cubic meters per year
  • Length: 60 kilometers
  • Diameter: 219.1 mm[62]
  • Status: Operating
  • Start year: 2018
  • Cost:
  • Financing:
  • Associated infrastructure: Longling Distribution Station of Sino-Myanmar Gas Pipeline[62]

Honghe Branch 红河支线

Loading map...
  • Operator:
  • Owner: Yunnan Petro-China Kunlun Gas Co., Ltd.[63]
  • Parent company:
  • Capacity: 0.315 billion cubic meters per year[63]
  • Length: 209 kilometers[63]
  • Diameter: 323.9 mm[63]
  • Status: Operating[64]
  • Start year: 2023[64]
  • Cost: 485.40 million RMB[63]
  • Financing:
  • Associated infrastructure: Yuxi Terminal Station of Sino-Myanmar Yuxi branch line[63]

Xundian-Songming-Airport Branch Gas Pipeline 寻甸-嵩明-空港支线输气管道

寻甸空港管道.png
Loading map...
  • Operator:
  • Owner: Yunnan Nengtou Dianzhong Gas Industry Development Co., Ltd.[65]
  • Parent company:
  • Capacity: 0.42 billion cubic meters per year[65]
  • Length: 54 kilometers[65]
  • Diameter: 273 mm[65]
  • Status: Cancelled (No more information after 2017, so it may be cancelled.)
  • Start year:
  • Cost: 261.89 million RMB[65]
  • Financing:
  • Associated infrastructure:

Articles and resources

References

  1. "中缅天然气管道开通-中国能源网". www.china5e.com. Retrieved 2023-02-28.
  2. [www.xsbn.gov.cn/files/2016/12/20161206101354661.pdf "云南省人民政府关于印发云南省能源发展规划 (2016—2020年)和云南省能源保障网五年行动计划(2016—2020年)的通知"] (PDF). www.xsbn.gov.cn. 2016-10-10. {{cite web}}: Check |url= value (help)CS1 maint: url-status (link)
  3. 3.0 3.1 "【云发布】到2025年云南建成天然气管道总里程将突破6000公里". m.yunnan.cn (in 中文(中国大陆)). 2020-09-01.{{cite web}}: CS1 maint: url-status (link)
  4. 4.0 4.1 "云南省人民政府关于印发云南省能源发展规划(2016—2020年)和云南省能源保障网五年行动计划(2016—2020年)的通知". www.xsbn.gov.cn. Retrieved 2021-10-26.
  5. "云南省人民政府关于印发云南省国民经济和社会发展第十四个五年规划和二〇三五年远景目标纲要的通知_最新文件_云南省人民政府门户网站". www.yn.gov.cn. 2021-02-09.{{cite web}}: CS1 maint: url-status (link)
  6. "云南即将新建跨省天然气管道项目—桂气入滇(百色—文山)天然气管道-北极星能源网". news.bjx.com.cn. 2022-04-13.{{cite web}}: CS1 maint: url-status (link)
  7. 7.0 7.1 7.2 7.3 "开远天然气管道即将开通,时间为……_要闻_红河频道_云南网". honghe.yunnan.cn. Retrieved 2021-10-06.
  8. 8.0 8.1 8.2 "cnyeig.com". cnyeig. Retrieved 2021-10-06.{{cite web}}: CS1 maint: url-status (link)
  9. 9.0 9.1 "泸西—弥勒—开远支线天然气管网全线开通". 昆明信息港. Retrieved 2022-08-28.
  10. "cnyeig". Retrieved 2021-10-26.{{cite web}}: CS1 maint: url-status (link)
  11. 11.0 11.1 云南省能源投资集团有限公司2023年度第一期超短期融资券募集说明书, 云南省能源投资集团有限公司, 2023-02
  12. 12.0 12.1 "云南省人民政府关于印发云南省能源发展规划(2016—2020年)和云南省能源保障网五年行动计划(2016—2020年)的通知". www.xsbn.gov.cn. Retrieved 2021-10-26.
  13. 2024年泸水市招商引资工作动态速览(3月), 泸水市投资促进局, 2024-04-07
  14. 14.0 14.1 14.2 "云南迪庆天然气支线管道拟于明年3月建成". yn.sina.com.cn. Retrieved 2021-10-26.
  15. “砥砺奋进的五年”系列新闻发布会迪庆专场——世界的香格里拉 幸福和谐新迪庆, 云南省人民政府, 2024-04-30
  16. "swtzb.yn.gov". Retrieved 2021-10-26.{{cite web}}: CS1 maint: url-status (link)
  17. "燃气特许经营权争夺战:立项六年无重大进展,挂职副市长称违纪未违法_腾讯新闻". new.qq.com. Retrieved 2021-10-26.
  18. 发布会|云南推进天然气“全省一张网”, 实现16州市通管道气, 开屏新闻客户端, 2021-05-25
  19. 19.0 19.1 19.2 "云南省天然气有限公司多条天然气支线管道投产通气 "气化云南"迈出铿锵脚步-国际燃气网". gas.in-en.com. Retrieved 2021-10-26.
  20. 20.0 20.1 对政协普洱市第五届委员第二次会议第169号提案答复函, 云南省人民政府, 2023-09-05
  21. 玉溪-普洱天然气支线管道一期工程项目, 招标与采购网, 2022-09-07
  22. "云南省天然气有限公司多条天然气支线管道投产通气 "气化云南"迈出铿锵脚步-国际燃气网". gas.in-en.com. Retrieved 2021-10-26.
  23. "cnyeig". Retrieved 2021-10-26.{{cite web}}: CS1 maint: url-status (link)
  24. 24.0 24.1 24.2 24.3 "问董秘". finance.sina.cn. Retrieved 2021-10-26.
  25. 25.0 25.1 陆良支线天然气管道工程项目竣工决算审计服务招标公告, 电力招标网,2023-09-07
  26. "开远天然气管道即将开通,时间为……_要闻_红河频道_云南网". honghe.yunnan.cn. Retrieved 2021-10-06.
  27. 云南省水利厅关于准予开远—蒙自支线天然气管道工程洪水影响评价审批的行政许可决定书, 云南省水利厅, 2023-06-25
  28. 28.0 28.1 28.2 28.3 云南能投:开远—蒙自支线、文山—砚山支线天然气管道工程项目通气试运行, 证券时报, 2024-05-20
  29. "云南省农村燃气工程 "十三五" 专项规划 (2016-2020年)".{{cite web}}: CS1 maint: url-status (link)
  30. 线路用防腐钢管(螺旋缝埋弧焊管、无缝钢管)及热煨弯头运输招标公告, 采招网,2019-10-09
  31. 31.0 31.1 云南能投:开远-蒙自支线、文山-砚山支线天然气管道工程项目通气试运行, 金融界, 2024-05-20
  32. "云南能投(002053)_公司公告_云南能投:关于云南省天然气文山有限公司文山-砚山天然气支线管道工程项目防腐钢管(直缝高频电阻焊管)及热煨弯管采购运输项目因公开招标形成关联交易的公告新浪财经_新浪网". money.finance.sina.com.cn. Retrieved 2021-10-26.
  33. 33.0 33.1 33.2 "云南能源投资股份有限公司 关于云南省天然气有限公司投资建设文山-砚山天然气支线管道工 程项目的公告" (PDF). Retrieved 2021-10-26.{{cite web}}: CS1 maint: url-status (link)
  34. 云南能投拟投资建设文山-砚山天然气支线管道 总投资逾4亿元, 云南网,2015-05-31
  35. "临沧天然气管道支线一期投产试运成功". www.lincang.gov.cn. Retrieved 2021-10-26.
  36. "天然气管道临沧支线(云县段)项目取得突破性进展". www.ynyx.gov.cn. Retrieved 2021-10-27.
  37. 37.0 37.1 临沧天然气管道支线一期投产试运成功, 临沧日报, 2020-10-23
  38. "天然气管道临沧支线(一期)项目拟今年开工建设_昆明信息港". m.kunming.cn. Retrieved 2021-10-27.
  39. "sohu". sohu. Retrieved 2021-10-06.{{cite web}}: CS1 maint: url-status (link)
  40. 临沧市发展和改革委员会2022年度部门决算, 临沧市发展和改革委员会, 2023-09-14
  41. "天然气管道临沧支线(云县段)项目取得突破性进展". www.ynyx.gov.cn. Retrieved 2021-10-27.
  42. "上海伟伦阀门集团有限公司". www.weilunnc.com. Retrieved 2021-10-27.
  43. 水富至昭通天然气管道输送工程项目, 厚普清洁能源集团工程技术有限公司, 2021-11-18
  44. 44.0 44.1 "关于昭通市2017年国民经济和社会发展计划执行情况与2018年国民经济和社会发展计划草案的报告-昭通市人大常委会". www.ztrd.gov.cn. Retrieved 2021-10-27.
  45. 水富至昭通天然气长输管道正在建设, 昭通新闻网,2016-03-18
  46. "云南省住房和城乡建设厅建设项目选址意见书批前公示_云南省住房和城乡建设厅". zfcxjst.yn.gov.cn. Retrieved 2021-10-27.
  47. 富民—长水天然气支线拟12月投产 将缓解能源供给压力, 春城晚报, 2016-11-03
  48. 48.0 48.1 "kknews". kknews. Retrieved 2021-10-06.{{cite web}}: CS1 maint: url-status (link)
  49. 49.0 49.1 云南省天然气公司富长支线累计输气突破1亿方, 人民资讯, 2021-07-22
  50. "哺石成金-云南能投(002053)关于全资子公司云南省天然气有限公司富长支线(富民段)建成通气的公告". www.bushichengjin.com. Retrieved 2021-10-27.
  51. 51.0 51.1 51.2 51.3 51.4 51.5 蒙自雨过铺镇至老寨乡天然气输气管道项目环境影响报告书(报批稿), 云南中石油慧能能源有限公司红河分公司, 2018-06
  52. 主题教育丨守护匠心、砥砺前行,蒙自天然气管道项目一次性投产成功, CPECC华北分公司 2023-12-31
  53. 53.0 53.1 昭通市能源局对昭通市五届人大一次会议第0114号建议的答复, 昭通市能源局石油天然气科, 2022-07-15
  54. 54.0 54.1 54.2 54.3 54.4 "Outline of the Fourteenth Five-Year Plan for the National Economic and Social Development of Zhaotong City". Retrieved 2021-10-27.{{cite web}}: CS1 maint: url-status (link)
  55. 55.0 55.1 昭通市能源局对昭通市五届人大四次会议第0059号建议的答复, 昭通市能源局, 2023-08-16
  56. 56.0 56.1 56.2 56.3 56.4 56.5 "禄脿-易门天然气支线管道工程建成通气-国际燃气网". mgas.in-en.com. 2018-12-21. Retrieved 2022-09-16.{{cite web}}: CS1 maint: url-status (link)
  57. 禄脿-易门天然气支线管道投产通气, 玉溪网, 2019-03-07
  58. 58.0 58.1 58.2 58.3 "好消息!泸西—师宗—罗平支线天然气管道工程获批复..._项目". www.sohu.com. 2020-08-11. Retrieved 2022-09-16.
  59. 曲靖市能源局2022年度部门决算, 曲靖市能源局, 2023-09-24
  60. 60.0 60.1 "云南省天然气南环线项目前期工作启动会召开-北极星能源网". news.bjx.com.cn (in 中文(中国大陆)). 2022-05-11. Retrieved 2022-09-16.{{cite web}}: CS1 maint: url-status (link)
  61. 保山市人民政府办公室关于印发《保山市碳达峰实施方案》的通知, 保山市人民政府办公室, 2024-05-13
  62. 62.0 62.1 62.2 昆仑燃气云南天然气支线管道工程腾冲支线项目工程施工招标公告, 安装信息网, 2015-07-24
  63. 63.0 63.1 63.2 63.3 63.4 63.5 云南天然气支线管道工程红河支线项目结算审核服务项目, 采招网, 2021-11-18
  64. 64.0 64.1 中石油天然气管道红河支线顺利试运投产通气!, 云南红河发布, 2023-12-07
  65. 65.0 65.1 65.2 65.3 65.4 云南天然气支线管道工程红河支线项目结算审核服务项目, 采招网, 2021-11-18