Rungta Mines Dhenkanal steel plant
This article is part of the Global Steel Plant Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Rungta Mines Dhenkanal steel plant, also known as RML Odisha, is a blast furnace-basic oxygen furnace (BF-BOF) and direct reduced iron (DRI) steel plant operating in Dhenkanal, Odisha, India.
Location
The map below shows the exact location of the plant in Dhenkanal, Odisha, India:
- Location: Jhadabandh, PO-Nimabahali, Meramandali, Dist-Dhenkanal, Odisha-759121, India
- Coordinates (WGS 84): 20.764524, 85.299318 (exact)
Background
In 2018, Rungta Mines Ltd. proposed to install a 2.85 mtpa steel plant at villages Jharbandh, Galpada and Tarkabeda, district Dhenkanal in Odisha. It planned to establish the facilities in two phases of 1.45 million tonnes per annum followed by 1.4 million tonnes per annum.[1] The capacities and configuration were modified subsequently.[2]
According to the OECD steelmaking report, the plant plans to expand its EAF capacity by 110 ttpa by 2030.[3] According to an environmental clearance dated August, 2021, the plant is partially under operation and partially under construction. The plant has also proposed to expand facilities from 3.55 mtpa to 7.53 mtpa.[4]
Plant Details
Table 1: General Plant Details
Phase | Plant status | Announced date | Start date | Power source |
---|---|---|---|---|
Main plant | Operating[5] | 2018[6] | 2021[7] | 695 MW Captive power plant[7] |
Expansion | Announced[6] | 2021[7] | 2030[8] | – |
Main plant | Operating[5] | 2018[6] | 2021[7] | 695 MW Captive power plant[7] |
Main plant | Operating[5] | 2018[6] | 2021[7] | 695 MW Captive power plant[7] |
Table 2: Ownership and Parent Company Information
Phase | Owner | Owner company PermID | Owner company GEM ID |
---|---|---|---|
Main plant | Rungta Mines Ltd[9] | 4298502619 | E100000130898 |
Table 3: Process and Products
Phase | Main production equipment | Detailed production equipment |
---|---|---|
Main plant | BF, DRI, EAF, other[6] | 7 DRI (2x500 tpd; 3x600 tpd; 2x900 tpd); 2 BF (600 m3, 450 m3); 2 EAF (1x90 ton; 1x110 ton); 15 IF (20 ton each)[7] |
Expansion | BF, BOF, DRI, other[7] | 5 DRI (900 tpd each); 3 BF (2x650 m3; 1x1250 m3); 6 BOF (2x65 ton; 4x45 ton); 20 IF (20 ton each)[7] |
Main plant | BF, DRI, EAF, other[6] | 7 DRI (2x500 tpd; 3x600 tpd; 2x900 tpd); 2 BF (600 m3, 450 m3); 2 EAF (1x90 ton; 1x110 ton); 15 IF (20 ton each)[7] |
Main plant | BF, DRI, EAF, other[6] | 7 DRI (2x500 tpd; 3x600 tpd; 2x900 tpd); 2 BF (600 m3, 450 m3); 2 EAF (1x90 ton; 1x110 ton); 15 IF (20 ton each)[7] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Basic oxygen furnace steelmaking capacity | Electric arc furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|---|---|
Main plant | announced | – | 1680 TTPA[7][7] | 2193 TTPA[7][7] |
Expansion | announced | 3069 TTPA[7][7][7][7][7][7] | – | 4189 TTPA[7][7][7][7][7][7] |
Main plant | operating | – | –[7][7] | 205 TTPA[7][7] |
Main plant | construction | – | –[7][7] | 821 TTPA[7][7] |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Blast furnace capacity | Sponge iron/DRI capacity | Nominal iron capacity (total) |
---|---|---|---|---|
Main plant | announced | 1733 TTPA[6][7][7] | 1437 TTPA[7][7][7][7][7][7][7] | 3170 TTPA[6][7][7][7][7][7][7][7][7][7] |
Expansion | announced | 3041 TTPA[7][7][7] | 2156 TTPA[7][7][7][7][7] | 5197 TTPA[7][7][7][7][7][7][7][7] |
Main plant | operating | –[6][7][7] | 260 TTPA[7][7][7][7][7][7][7] | 260 TTPA[6][7][7][7][7][7][7][7][7][7] |
Main plant | construction | –[6][7][7] | 548 TTPA[7][7][7][7][7][7][7] | 548 TTPA[6][7][7][7][7][7][7][7][7][7] |
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Phase | Sinter | Coke | Pellets |
---|---|---|---|
Main plant | 2827 TTPA[7] | 1070 TTPA[7] | 28750 TTPA[7] |
Expansion | 4653 TTPA[7] | 1680 TTPA[7] | –[7] |
Main plant | 2827 TTPA[7] | 1070 TTPA[7] | 28750 TTPA[7] |
Main plant | 2827 TTPA[7] | 1070 TTPA[7] | 28750 TTPA[7] |
Blast Furnace Details
Table 7: Blast Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Current size | Current capacity (ttpa) | Decarbonization technology | Most recent relining |
---|---|---|---|---|---|---|---|---|
1 | announced[6] | 2018[6] | unknown | unknown | 600 m³[6] | 567[6] | unknown | unknown |
2 | announced[6] | 2018[6] | unknown | 2030[10] | 450 m³[7] | 583[7] | unknown | unknown |
unknown | announced[7] | 2021[7] | unknown | unknown | 650 m³[7] | 864[7] | unknown | unknown |
unknown | announced[7] | 2021[7] | unknown | unknown | 650 m³[7] | 864[7] | unknown | unknown |
unknown | announced[7] | 2021[7] | unknown | unknown | 1250 m³[7] | 1312[7] | unknown | unknown |
unknown | announced[6] | 2018[6] | unknown | 2030[10] | 450 m³[7] | 583[7] | unknown | unknown |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
References
- ↑ "Executive Summary of draft environmental impact assessment and Environmental Management plan of Dhenkanal Steel Plant" (PDF). December, 2018. Retrieved 17 October, 2023.
{{cite web}}
: Check date values in:|access-date=
and|date=
(help)CS1 maint: url-status (link) - ↑ "EIA" (PDF). October 2021. Retrieved 10 January 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Latest developments in steelmaking capacity" (PDF). OECD. 2022. Retrieved 17 October, 2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "Environmental Clearance" (PDF). Environmental Clearance, MoEF&CC. 05 August, 2021. Retrieved 17 October, 2023.
{{cite web}}
: Check date values in:|access-date=
and|date=
(help)CS1 maint: url-status (link) - ↑ 5.0 5.1 5.2 (PDF) http://environmentclearance.nic.in/writereaddata/Online/TOR/11_Aug_2021_1508437177105306300_CoverLetter.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 6.00 6.01 6.02 6.03 6.04 6.05 6.06 6.07 6.08 6.09 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17 6.18 6.19 6.20 (PDF) https://web.archive.org/web/20220112195758/https://cdn.s3waas.gov.in/s3069d3bb002acd8d7dd095917f9efe4cb/uploads/2019/01/2019012572.pdf. Archived from the original (PDF) on 12 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 7.000 7.001 7.002 7.003 7.004 7.005 7.006 7.007 7.008 7.009 7.010 7.011 7.012 7.013 7.014 7.015 7.016 7.017 7.018 7.019 7.020 7.021 7.022 7.023 7.024 7.025 7.026 7.027 7.028 7.029 7.030 7.031 7.032 7.033 7.034 7.035 7.036 7.037 7.038 7.039 7.040 7.041 7.042 7.043 7.044 7.045 7.046 7.047 7.048 7.049 7.050 7.051 7.052 7.053 7.054 7.055 7.056 7.057 7.058 7.059 7.060 7.061 7.062 7.063 7.064 7.065 7.066 7.067 7.068 7.069 7.070 7.071 7.072 7.073 7.074 7.075 7.076 7.077 7.078 7.079 7.080 7.081 7.082 7.083 7.084 7.085 7.086 7.087 7.088 7.089 7.090 7.091 7.092 7.093 7.094 7.095 7.096 7.097 7.098 7.099 7.100 7.101 7.102 7.103 7.104 7.105 7.106 7.107 7.108 7.109 7.110 7.111 7.112 7.113 7.114 7.115 7.116 7.117 7.118 7.119 7.120 7.121 7.122 7.123 7.124 7.125 7.126 7.127 7.128 7.129 7.130 7.131 7.132 7.133 (PDF) https://web.archive.org/web/20240115055307/https://cdn.s3waas.gov.in/s3069d3bb002acd8d7dd095917f9efe4cb/uploads/2021/11/2021112334.pdf. Archived from the original (PDF) on 15 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-2022.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220111145838/https://www.therungtagroup.com/. Archived from the original on 11 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 10.0 10.1 (PDF) https://web.archive.org/web/20220111173338/https://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-2021.pdf. Archived from the original (PDF) on 11 January 2022.
{{cite web}}
: Missing or empty|title=
(help)