Vlora-Fier Gas Pipeline

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Vlora-Fier Gas Pipeline is a proposed gas pipeline running within Albania.

Location

The pipeline is proposed to run between the Trans-Adriatic Gas Pipeline and the Vlora power station.[1]

Loading map...

Project details

  • Operator: Albgaz Sh.a[2]
  • Owner: Albgaz Sh.a[2]
  • Parent: Albgaz Sh.a[2]
  • Capacity: 1 bcm/y[3]
  • Length: 40 km[1]
  • Diameter: 400 mm[2]
  • Status: Proposed
  • Start year: 2025
  • Cost: €21.86 million (US$24.9 million)[4]
  • Financing:
    • WBIG Grant: €1,100,000[1]
    • External Grant: €300,000[1]
    • Own Contribution: €843,840[1]
    • EBRD Loan: €10,625,669[1]

Background

The pipeline project is also known as the "Trans-Adriatic-Pipeline (TAP) Exit Point to Vlora Thermal Power Plant (TPP) gas pipeline project"[1] and "IAEF - Vlora CCGT Pipeline"[2] When constructed, it will allow natural gas to flow from the TAP to the Vlora thermal power plant in Albania.[5]

The FEED study took place in 2018, permitting between 2018 and 2019, and FID in 2019.[2]

The technical assistance project 'Detailed Design and Tender documents for the Fier – Vlora gas pipeline' was launched in June 2020.[6]

Albgaz, Excelerate and Snam signed a Memorandum of Understanding on the possibilities of cooperation for the construction of the Fier-Vlora pipeline in July 2021.[7]

Articles and resources

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 WBIF. "Fier – Vlora Gas Transmission Pipeline". Western Balkans Investment Framework.{{cite web}}: CS1 maint: url-status (link)
  2. 2.0 2.1 2.2 2.3 2.4 2.5 2.6 ENTSOG (July 10, 2020). "TYNDP 2020 - Annex A - Projects Details" (PDF). European Network System Operators for Gas. Retrieved October 5, 2021.{{cite web}}: CS1 maint: url-status (link)
  3. Jonuzaj, Klaudjo (June 14, 2018). "Azerbaijan's SOCAR to prepare a feasibility study for Fier-Vlora pipeline in Albania – report". SeeNews. Retrieved October 5, 2021.{{cite web}}: CS1 maint: url-status (link)
  4. Ten Year Network Development Plan 2020 - Annex A - Projects Tables, ENTSOG, accessed Dec. 5, 2021
  5. "TAP to build exit point in Fier in 2-3 years". Albania Daily News. Mar 22nd, 2022. Retrieved Jul 5th, 2022. {{cite web}}: Check date values in: |access-date= and |date= (help)CS1 maint: url-status (link)
  6. Western Balkans Investment Framework (July 7, 2020). "EU Supports Additional Technical Assistance to Gas Transmission Network in Albania". WBIF. Retrieved Oct 5, 2021.{{cite web}}: CS1 maint: url-status (link)
  7. "Memorandum for LNG terminal, construction of Fier-Vlora pipeline and distribution of liquefied gas signed". politiko.al. Retrieved 2021-10-05.

Related GEM.wiki articles

External resources

External articles

*add as many countries as the pipeline passes through