Power Sector Transition in Gujarat
This article is part of the Global Energy Transition Tracker project sponsored by Global Energy Monitor |
Introduction
The state of Gujarat, India has created a surplus of power since 2009, and produces nearly 12% of the country's renewable energy.[1] Gujarat had plans to increase from 9,670 MW to 30,000 by 2022 — and is poised to surpass this by a wide margin, creating the world's largest solar and wind energy park at 30,000 MW.[2][3] Set to be completed in 2026, the Gujarat Hybrid Renewable Energy Park would take up 726 square km of land, roughly the size of Singapore.[4] This project is being built in tandem with a desalination plant that would process 26.4 million gallons of water, helping 800,000 people living in the dry region.[5]
However, the area this project would occupy is considered "wasteland" by the government, and locals are concerned about impacts on people and hundreds of species of birds that live in the area.[6] As more of Gujarat's land is designated "wasteland," nomads, farmers, and cattle herders are increasingly driven off their land by even very small solar projects.[7]
India as a country has also implemented a tariff system for their energy sector, and this includes requirements for energy providers to have a certain percentage of their supply coming from renewable sources. With this requirement, the world's largest interconnected grid has seen demand for renewables skyrocket.
India's energy consumption has more than doubled since 2000, with around 900 million people gaining access to an electrical connection in less than two decades.[8]
Current System Description
Current Power Capacity Mix
Installed capacity in Gujarat
Energy Source | Installed Capacity | Number of Plants |
---|---|---|
Coal[9] | 17,692 MW | 21 (68 units) |
Oil and Gas[10] | 9,310 MW | 19 (28 units) |
Hydropower[11] | 1,990 MW | 4 |
Solar[12][13] | 10,133.66 MW | |
Wind[14] | 14,653 MW | 183 (206 units) |
Prospective Power Capacity
According to the Renewable Energy Policy, 2023, Gujarat possess 36 GW of potential solar capacity and 143 GW of potential wind.[15]
Announced, Pre-construction, and Construction Capacity in Gujarat, Global Energy Monitor (2023)
Energy Source | Announced | Pre-construction | Construction | Total |
---|---|---|---|---|
Coal[9] | 1,200 MW | 800 MW | 170 MW | 2,170 MW |
Solar[12] | 12,501 MW | 927 MW | 13,428 MW | |
Onshore Wind[14] | 2,622 MW | 476 MW | 3,098 MW | |
Offshore Wind[16] | 500 MW | 500 MW |
Renewable Energy in Gujarat
Renewable Targets
National Target: In 2010, the Jawaharlal Nehru National Solar Mission (JNNSM) - an initiative intended to build and bolster India’s solar industry - established a target of 20 GW of grid-connected solar by 2022,[17] a goal which was reached in 2018.[18] This target was raised in 2015 to 100 GW of solar by 2022, which would include 40 GW of rooftop solar.[19] While this goal was not met, utility-scale solar reached 70.1 GW by June 2023.[20] Rooftop solar installations fell far short of the target and only reached 8.8 GW by the end of 2022.[21] In 2022, India raised its renewable energy targets to 500 GW by 2030, of which 280 GW will come from solar generation.[22]
India has surpassed its commitment made at the COP21 - Paris Summit by already meeting 40% of its power capacity from non-fossil fuels - almost nine years ahead of its commitment.[23]
Nationally Determined Contributions (NDC): 50% of India's power needs to be coming from non-fossil sources by 2030.[24]
Prime Minister Narendra Modi set the goal for a net zero economy in India by 2070.[25]
Renewable Energy Target (RES): by August 2022, India as a whole had reached 66% of its 2022 renewable energy target; the country would need to build renewables 2.5 times faster to meet its 2030 goal.[26]
Prime Minister Narendra Modi has announced more ambitious targets for 2030, including installing 500 GW of renewable energy capacity, reducing the emissions intensity of its economy by 45%, and reducing a billion tonnes of CO2.[27]
In 2023, the New & Renewable Energy Secretary Bhupinder Singh Bhalla mentioned that India is expected to add 25GW of renewable energy in 2023, and the government is planning to raise the annual increase to 40GW in 2024, aiming for 50GW for the next five year. Among the newly added capacity, at least 10GW will come from wind energy.[28]
State and Local Targets: In October 2023, the Government of Gujarat released the Gujarat Renewable Energy Policy - 2023, which outlines the State's renewable energy plans and will remain in effect through 2028. Through this policy, the State aims to reach 100 GW of renewable energy by 2030, which may include solar (ground-mounted, rooftop, floating, canal top), wind (rooftop, utility-scale), and projects which combine both generation types. The Government of Gujarat also aims to attract investments of approximately INR ₹5 lakh crores.[29] Additionally, each Indian state has a Renewable Energy target (RES), and Gujarat is one of four states to have exceeded its target.[26]
Ahmedabad, Gujarat, the largest city in the state, set a target in 2022 to reduce carbon emissions by 139 million tonnes by 2030. To do this, over the course of 8 years the state government has announced plans to build 68,000 MW of renewable energy.[30]
Progress toward clean energy targets: Analyses conducted in early 2024 predict that India is on-track to meet its 2030 clean energy goals. An estimated 412 GW of wind, solar, and hydroelectric power will be online by 2030, while fossil fuels are expected to drop from 57% to 36-41% of the country's energy share by the end of the decade. Financing remains the largest challenge to these goals.[31]
Major Renewable Projects
Project | Capacity | Status |
---|---|---|
Gujarat Hybrid Renewable Energy Park | 30,000 MW | Construction |
Kutchh Manufacturing (Adani Group) solar farm | 750 MW | Pre-construction |
Dholera Solar Park (Phase 1 and 2) | 4,300 MW | Pre-construction |
Kutch (NTPC) Solar Park | 4,750 MW | Pre-Construction |
Gujarat Greenshore wind farm | 600 MW | Announced |
In addition, India is nuclear capable with three units (1,140 MW) operating at the Kakrapar nuclear power plant in Gujarat and a fourth unit (700 MW) still under development.[32] Nuclear energy has reached about 3% of India's generating capacity mix and is expected to expand to 9% by 2047.[33]
Khavda Ultra Mega Solar Park
Khavda, Gujarat is home to several large-scale wind and solar parks under development. The park has multiple agencies leasing the project area to many different developers in several separate projects. The phases currently under construction include:[34]
- NTPC Renewable Energy Ltd's 4,750-MW solar project; under development by Sterling and Wilson Renewable Energy Ltd. Expected to come online in phases between 2024 and 2025.
- GSECL's 3,325-MW solar project; under development by NHPC Ltd, SJVN Green Energy Ltd, NTPC Renewable Energy Ltd, KPI Green Energy Ltd, NLC India, SAEL Industries Ltd, Engie Energy Pvt Ltd, and JSW Neo Energy Ltd. Expected to come online in early 2026.
- GIPCL's 600-MW solar project (Phase I); under development by GIPCL. Expected to come online in 2024.
- GIPCL's 1,200-MW solar project (Phase II); under development by SJVN Ltd, SEAL, and Coal India Ltd. Expected to come online in 2025.
- GIPCL's 575-MW solar project (Phase III); under development by GIPCL. No estimated date of completion.
- NHPC's 600-MW solar project; under development by NHPC through the CPSU Scheme. Expected to come online in 2026.
- Adani's 1,000-MW solar project has come online.[35]
Potential impacts from renewable expansion
The government of India has a reputation for finding ways to avoid buying land for these projects, or taking it through eminent domain.[36]
Local Impacts
The Charanka Solar Park, a 216 MW project in the state that was part of the "Gujarat Solar Power Policy 2009," was the largest solar project in Asia at the time of its construction, requiring a vast area of land. Through the policy, the park was on the edge of a unique salt marsh ecosystem in the Great Rann of Kutch and Little Rann of Kutch. In addition, it is land that nomadic Rabari peoples use regularly for their livestock herds, but do not own. [37]
The Gujarat Solar Park, India’s first utility-scale solar park, promised to bring Charanka clean drinking water, free electricity, irrigation, and 1,000 permanent jobs. 10 years after these promises were made, 60 locals are employed, and security guards are working 12 hour shifts (against the 8 hour mandate) while making little pay. Women have not received jobs.[38]
Fossil Fuel in Gujarat
Fossil Resources and Retirement
India is the second largest coal producer and consumer in the world, with government plans to expand production, and projections indicate that India is expected to beat China as the world’s largest importer in the next few years.[39]
Coal Mines: There are eight active coal mines in Gujarat (see table below). The expansion plan of the existing Bhavnagar Lignite Mine, is the only proposed coal mine project in Gujarat.[40]
Status | Name of Coal Mine | Mine Size(Km2) | Mining Method | Annual Coal Production (Mt) | Workforce |
---|---|---|---|---|---|
Operating | Bhavnagar Lignite Mine, Phase 1 | 36.72 | Open Pit | 1.64 | 346 |
Proposed | Bhavnagar Lignite Mine, Expansion | Open Pit | 346 | ||
Operating | Khadsaliya Lignite Mine | Open Pit | 0.17 | 370 | |
Operating | Mangrol Valia Coal Mine | 20.8 | Open Pit | 2.53 | 586 |
Operating | Mata No Madh Lignite Coal Mine | Open Pit | 3.48 | 604 | |
Operating | Rajpardi Lignite Mine | 3.85 | Open Pit | 0.71 | 397 |
Operating | Tadkeshwar Lignite Mine | Open Pit | 0.9 | 390 | |
Operating | Umarsar Lignite Mine | 21.86 | Open Pit | 1.82 | 449 |
Active | Vastan Lignite Mine | 15.36 | Open Pit | 0.52 | 379 |
Closed | Panandhro Lignite Mine | 17.19 | Open Pit | 0.71 |
Oil and Gas Extraction: India has 49 operational oil, gas, and mixed fields,[41] with one in Gujarat (Ankleshwar Oil and Gas Block). Gujarat is the second-largest oil-producing region in India.[42] Additionally, The Jamnagar Refinery in Gujarat is the largest oil refinery in the world, with a capacity of approximately 1,240,000 barrels per day.[43] Moreover, Nayara Energy's oil refinery in Vadinar, Gujarat will be expanded in the coming years.[44] Further, GSPC and NGEL recently signed a Memorandum of Understanding to advance blending gas networks with green hydrogen.[45]
Cancellation and Retirement: The state government of Gujarat cancelled a 4 GW coal plant in 2017 due to an existing surplus of energy and the need to transition away from fossil fuels. The Australian government, meanwhile, asserted that it was their "moral obligation" to provide poorer countries like India with coal — though there was no real demand for it or the massive coal mines that would have supplied it.[46] Between 2016 and 2021, India as a whole retired 56 coal-based plants, and had plans to shutter 47 more.[47] At the same time, India is set to construct around 100 more mines in coming years.[48]
Overview of current fossil fuel impacts
National impacts
Premature deaths per year due to air pollution in India reached 1.2 million, and are expected to rise to 1.4 million in 2040 if India policies and development continue to progress as they are now. If the country shifted to meet the more sustainable goals, this would decrease to an estimated 0.6 million.[49]
According to estimates from the Air Quality Life Index, the life expectancy of the average person in India would increase by 5.26 years if fine particulate matter pollution met World Health Organization guidelines.[50]
India is in the midst of having pipelines to import fracked gas into the country implemented, which is expected to lower the price of gas which has historically come through LNG imports. However, by 2040 there's likely to be a scarcity in supply of pipeline gas, with India's reserves drying up, which would drive prices up by double.[51]
There has been intense grassroots opposition to coal and coal mining in India, where farmers and fishers in particular face environmental destruction and state violence. Sometimes this leads to the murder, injury, and incarceration of protestors, and often times it leads to projects getting cancelled, with as much as a 67% success rate in the country.[52]
In addition, India's rampant coal mine buildout has been proven unnecessary through analysis of all existing mines. GEM's data shows that India's current mines are chronically underutilized, and create vast quantities of methane.[48][53]
For more information, visit GEM's Opposition to Coal in India page.
Local Impacts
In Gujarat, the average citizen's life expectancy would increase by 3.15 years if fine particulate matter pollution met World Health Organization guidelines.[50]
In May of 2018, police arrested over 500 farmers in Gujarat protesting against the establishment of three proposed lignite mines to supply the part-built 500 MW Bhavnagar power station in Gujarat. An estimated 1,000 people gathered to protest against Gujarat Power Corporation Limited’s (GPCL) occupation of 1,415 hectares of land it bought before 2005 but which was subsequently reoccupied and farmed by displaced villagers.[54] While Bhavnagar is in operation, Bhadreshwar and parts of Tata Mundra Ultra Mega Power Project in the state were cancelled.
Employment
Current employment by sector (figures from 2021 data)
Hydropower: 413,728 jobs for all of India[55]
Solar PV: 217,000 jobs for all of India[55]
Biogas: 85,000 jobs for all of India[55]
Solid Biomass: 58,000 jobs for all of India[55]
Liquid Biofuels: 35,055 jobs for all of India[55]
Wind: 35,400 jobs for all of India[55]
Solar heating/cooling: 19,000 jobs for all of India[55]
CSP: No jobs[55]
Geothermal: No jobs[55]
Coal Mines: 3,521 jobs in operating coal mines, 346 in proposed coal mines[40]
(One thesis from the University of British Columbia shows the approximate workforce for direct and indirect jobs to coal mines and coal power plants in Gujarat could be up to 76,896.[56][57] - Further detailed needed to be confirmed.)
Prospective employment from renewable energy sector
While jobs in wind energy have stagnated in India, employment in the solar sector has increased dramatically. Solar workforce training certifications from the Skill Council for Green Jobs have risen from less than 10,000 in 2017, to over 100,000 in 2022. In FY22, only 600 new workers were employed in wind, compared to 52,100 in solar.[24]
The 30-GW renewable energy park planned in Khavda, Gujarat is estimated to generate more than 15,200 green jobs.[35]
According to a 2019 study by the International Climate Initiative, Federal Ministry of the Environment, and other organizations, up to 3.5 million people can be employed in the Indian power sector by 2050, with over 3.2 million of those jobs in the renewables sector. In the most extreme scenario played out by this study, the renewable energy sector could employ five times more people by 2050 than the entire Indian fossil-fuel sector employed in 2019.
Between 143,000 and 250,000 skilled experts and 410,000-850,000 lower level workers would be needed for the solar sector in the coming years. Meanwhile, due to increased mechanization in coal mining 105,000 jobs were lost between 2000 and 2015.[58]
Supply Chain
In early 2024, Grew Energy signed a Memorandum of Understanding to establish a solar component manufacturing facility in Dholera, Gujarat. The plant is expected to be operational in 2025 and employ more than 1,600 individuals. This facility will have a manufacturing capacity of 2.8 GW, and an additional announcement for another 3.2 GW facility in Dholera brings the town's capabilities to over 6 GW.[59]
Additionally, Suzlon Group, which was founded in Gujarat, is a manufacturer of wind turbine components that will be used in developments like KP Group's 193 MW wind-solar hybrid project.[60]
Land availability
According to the International Energy Agency’s 2023 report “Net Zero Roadmap: A Global Pathway to Keep the 1.5 °C Goal in Reach,” an average utility-scale solar PV project of 100 MW generally occupies from 1 km² to 3 km², while a 100 MW onshore wind turbine project generally covers from 5 km² to 30 km².[61] Based on these estimates, the current prospective 23,115 MW of utility-scale solar will require between 231.15 km² and 693.45 km², and 5,616 MW of utility-scale wind will require between 280.8 km² and 1,684.8 km².
Under 2023’s Gujarat Renewable Energy Policy, approximately 4 lakh acres of land is expected to be used for renewable energy development.[62]
"Wasteland":
The Gujarat Hybrid Renewable Energy Park has been allotted 60,000 hectares — roughly the size of Singapore or Greater Mumbai.[6]
Gujarat's Government has also allotted 6,024 hectares of “wasteland" for a 9,000 MW project. The proposed park will be built on a plot of land in the Little Rann Of Kutch district. In 2019, the state authorities started to assess the area for the production of electricity from renewable sources like photovoltaic or wind.[63]
Elsewhere in India, the story is similar: In the state of Karnataka to the south, the Pavagada Ultra Mega Solar Park covers twenty square miles, and is over 2000 MW in capacity. 22% of the energy for the entire state of Karnataka is generated there, but none of the that electricity goes directly to the local communities whose farmland has been turned into solar installations. Generations-old land agreements were ignored because the farmers using the land had no deed, and so weren't eligible for compensation even when their land was taken. The developers of Pavagada were not required to study the social or environmental impacts of the work, though the World Bank commissioned two studies that predicted profound impacts on the land an its people; some would have assured income through leasing their land, but others, particularly women, would lose employment on local farms.[36]
Use of canals as space:
In Gujarat, there are over 80,000km of canals; according to Gujarat State Electricity Corporation, if 30% of this were converted to solar, 18,000MW of power could be produced, saving 90,000 acres of land. Some projects like this have already been built, and the solar panels, cooled by the water below them, gain a small amount of efficiency. However, maintaining long stretches of solar panels can be challenging.[64]
Potential of closed coal mines:
The closed mines could be the potential locations for renewable projects. Currently, one coal mine, Panandhro Lignite Mine, is closed with 17.19 km2 of space available for repurposing.[65]
Symbolic Importance
India boasts the largest interconnected grid on the planet, but it has not been a benefit to everyone. Farmers, nomads, and wildlife have been deeply impacted by massive projects (both renewable and fossil). So as states like Gujarat promote and continue to build multi-gigawatt projects and advertise their business friendliness in their urban centers, it's important to also consider effects on rural people. (And in the context of India, those in lower social castes are even more vulnerable.)
The Modhera "Solar Village" in Gujarat, while only 6 MW, has displaced and impoverished cattle herders in nearby Sujanpura. The town, famous for its sun temple, is drawing tourists and developers to the "new sun temple based on solar energy." While Modhera has been able to move away from coal dependency, herders now need to pay for hay to feed their livestock rather than graze on the land now occupied by solar, and have had to sell cattle due to the lack of grazing. At least one farmer was so distraught he considered suicide.[7]
For wildlife in Gujarat, energy projects that take up tens of thousands of hectares are a threat. The area of Kutch in the state is the site of several large scale projects, and the area of desert being used has been identified as "wasteland" despite having unique ecosystems. For for hundreds of species of bird in particular, this land is vital. Even flamingos, emblems of the state of Gujarat, risk colliding with powerlines and other dangers from these projects.[6]
Gujarat, a stronghold of natural gas energy, holds the distinction of being the first state in the country to establish its own gas transmission line.[66] Among India's 23 operational oil and gas fields, six are located in Gujarat. The state has also witnessed grassroots opposition to coal mining and generation due to their adverse impacts on land use, farmlands, and water resources.
Simultaneously, Gujarat plays a pivotal role in India's renewable energy landscape. Since 2009, it has consistently generated surplus power, contributing nearly 12% of the nation's renewable energy. Gujarat had achieved 44% of its installed capacity from renewable sources by 2023. The state is committed to reaching 80 GW of renewable energy by 2030.[67] Gujarat's energy transition journey offers valuable lessons in reducing fossil fuel dependence and establishing itself as a regional renewable energy hub.
Permitting
Electricity projects do not require a generation license, but permits, consents, and approvals are required for acquiring land, ensuring environmental responsibility and compliance with protection measures, corporate and labor compliance, and approvals to construct and operate the power plant. Additional permissions are required for nuclear power and hydropower greater than 25 MW.[68] Wind projects are exempt from requirements to complete an Environmental Impact Assessment (EIA), while other renewable energies, aside from small-scale hydropower, still require one.[69]
Renewable energy projects, like most major projects in India, require environmental clearance. To receive clearance, a developer must complete an Environmental Impact Assessment (EIA) which outlines the potential effects that the project may have on the surrounding environment, as well as mitigation measures that will be undertaken. Any project larger than 1 MW must undergo an EIA, with larger developments requiring more rigorous analysis and wind/solar requiring additional wildlife assessments. The clearance process is time-intensive, often delayed, and bureaucratically complicated.[70]
Environmental clearances require the following steps:[71]
- Site identification
- Environmental Impact Assessment completion, which is reviewed by relevant state agencies like the State Pollution Control Board and State Forest Department
- Public hearing, with a hearing committee comprised of the District Collector; officials from the district development body, State Pollution Control Board, Department of Environment and Forest, and Taluka and Gram Panchayat; senior citizens of the district, and others.
- Application and approval (if applicable) of environmental clearance. Approval is administered by an Appraisal Committee.
- Requisite documents needed to finalize compliance must be filed within 90 days of approval.
Similarly, land acquisition must be completed carefully with consideration of landowner compensation and agency approvals, both of which can delay development.[70]
The Gujarat Electricity Regulatory Commission (GERC) is responsible for administering licenses for the transmission and distribution of electricity. GERC is also tasked with promoting electricity, enforcing standards, and adjudicating conflicts between licensees while providing support and recommendations to the Government of Gujarat.[72] GERC must collaborate with India's Central Electricity Regulatory Commission to ensure efficient and economically advantageous delivery of electricity.[68]
Governmental information
Governmental Policies and Papers
Government of India under Prime Minister Narendra Modi:
The Modi administration has spent the past nine years overhauling India's energy sector. Between 2014 and 2022 India added 1,69,110 MW of generation capacity, which exceeds the country's maximum demand. The administration also takes credit for 1,66,080 Circuit Kilometers of transmission lines, integrating the countries grids into one consolidated grid-- the largest in the world.[73]
Gujarat-Specific Policies:
There are a number of initiatives and incentives in place to promote renewable energy in Gujarat. These include subsidies for manufacturers, provisions for companies willing to relocate or invest in the state, and fiscal incentives to train people in these technologies. Wind and wind-solar hybrids can also be exempt from demand cuts.[1]
Gujarat Solar Power Policy 2009: a state level policy that aims to create solar power projects developed through a public-private partnership arrangement where the state acquires and designates land for the parks and expedites planning procedures for private developers to develop plots within them; in all the cases, developers sell the power produced to the state at an agreed tariff. [37]
Gujarat Wind-Solar Hybrid Power Policy 2018: Provides a framework for the promotion of large, grid-connected wind-solar PV systems and encourages new technologies to further these operations, such as storage.[74]
The Gujarat Renewable Energy Policy 2023: The state government expects to generate 50% of the energy from renewables, and attract investment of nearly Rs 5 lakh crore in the renewable energy sector with the help of this policy. An estimated 36 GW of solar and 143 GW of wind capacity will be harnessed under the policy. Ground-mounted solar, rooftop solar, floating solar, canal top solar as well as wind, rooftop wind, and wind-solar hybrid projects will be covered under the policy, and approximately 4 lakh acres of land are expected to be utilized for renewable energy plants.[62]
India-Wide Policies:
The Electricity Act, 2003: Provides the enabling legal framework for promotion of Renewable Sources of energy by the State Electricity Regulatory Commissions (SERCs) through tariffs for energy supplies.[75]
National Electricity Policy (NEP): Expresses the need for fully exploiting non-conventional energy sources and the need for technology development and R&D, as well as conditions to promote these technologies. Policies include power purchases by distribution companies through competitive bidding processes.[75]
Tariff Policy 2016: Elaborates the role of Regulatory Commissions, the mechanism for promoting renewable energy, the time-frame for Implementation. Also fixes a minimum percentage of total electricity consumption from each distribution licensee that must be from renewables and waste-to-energy plants (or related Renewable Energy Credits or RECs).[75]
The Renewable Purchase Obligation (RPO) is meant to achieve the target of solar energy equivalent to 8% of the total energy consumption as envisaged by the Government of India. RPO percentage for FY 2022-23, FY 2023-24, and FY 2024-25 is set at 17%, 18.7%, and 20.7%, respectively.[76]
Jawaharlal Nehru National Solar Mission (NSM): In 2010, this government program was initiated under the National Action Plan on Climate Change (NAPCC) with the goal of generating 20 GW of grid-connected solar PV, as well as 2 GW of off-grid PV. The proposed time line is: Phase-I (1000MW): 2010-12, Phase-II (7000MW): 2013-17, and Phase-III (20,000MW): 2018- 2022.[37]
Relevant political coalitions
India and France:
The fifth Assembly of the International Solar Alliance (ISA) was held on 18.10.2022. India and France have been re-elected as the President and Co-President of the ISA Assembly for a third consecutive two-year term for the period of October 2022 to October 2024.[77]
India and the United States:
In 2009, the Partnership to Advance Clean Energy (PACE) was launched. In 2014 and 2015, then President Barack Obama and Prime Minister Modi met to announce priority initiatives.[78]
Transmission and Grid Capacity
Current transmission resources
India: In 2023, the Indian Transmission network includes 4,68,977 ckm of transmission lines (220kV and above voltage level) and 11,58,875 MVA of the transformation capacity in substations (220kV and above voltage level). The inter-regional capacity of the National Grid is 1,12,250 MW. Under the ‘Gati Shakti Master Plan’, the power transmission network is planned to be expanded from 4,25,500 circuit kilometer (existing as on 31.05.2020) to 4,54,200 circuit kilometer (ckm) by 2024-25 resulting in addition of nearly 28,700 ckm.[79]
Gujarat: Gujarat Energy Transmission Corporation Ltd (GETCO) was created in 1999 to build, operate, and maintain the state transmission network. As of 2022, Gujarat’s grid is made up of 70,378 circuit kilometers of transmission lines and 2,246 substations, with 138,646 MVA in transformation capacity. Substation availability is 99.91%.[80]
New transmission needed for renewables
In areas like Kutch, the government has made plans to double transmission capacity to 30 MW in the wake of multitudes of applications from renewable energy companies, totaling approximately 15 GW.[81] For example, in September 2024, Power Grid was awarded a letter of intent allowing them to build an inter-state transmission system near to evacuate renewable power from Khavda, Kutch, Gujarat.[82]
Sterlite Power commissioned the 5 GW Lakadia-Vadodara Transmission Project Ltd. (LVTPL), which would bring renewable energy from Bhuj and Kutch to the national grid. With investments of USD $244.4 million, 812 towers across 335 kilometers will comprise the largest transmission corridor build in India thus far. This infrastructure would be critical for the Gujarat Hybrid Renewable Energy Park.[83]
Another power "expressway" is being built from Mumbai to Gujarat, the Mumbai Urja corridor. This would bring 2,000 MW of solar and wind energy from Kutch and Vadodara to Maharashtra. Mumbai, the commercial capital of India, can't produce enough power on its own, so projects like these are needed to avoid grid failures and blackouts. This project is expected to fulfill up to 40% of Mumbai's electricity demand.[84]
Similarly, Khavda-Bhuj Transmission Limited (KBTL) recently filed an application for a second transmission license to evacuate 7 GW of electricity, in addition to the 3 GW of the project's first phase. Despite KBTL lacking regulatory eligibility criteria, the Commission exercised its power to relax regulations, allowing KBTL to proceed with soliciting public feedback. The total project cost is estimated at ₹216 crore.[85]
The Central Electricity Authority (CEA) is working with the Central Transmission Utility (CTU) to develop a transmission system to for an initial 10 GW offshore wind transmission capacity, with 5 GW allocated to both the Gujarat and Tamil Nadu coasts.[86]
Social and environmental impacts of new transmission
In 2022 it was announced that landholders in Gujarat would receive 15% of estimated land value (double the previous amount) for the use of their land for transmission lines.[87] It is not made clear what kind of compensation, if any, non-landowners would receive.
Ownership
Major owners of current fossil capacity
Adani: In addition to part of the Gujarat Hybrid Renewable Energy Park, Adani (the largest private thermal power produce in India) has two powerplants in Gujarat; it owns the 4620 MW Mundra Thermal Power Project coal plant, as well as the 40 MW Bitta solar farm (which has 115.5 times less capacity than the coal plant.)[88]
Gujarat Industries Power Company Ltd.: Owns Vadodara Station-I and II for gas plants, Surat Lignite Power Plant for coal, and several solar power plants totaling 262 MW.[89]
Gujarat Urja Vikas Nigam, the parent company of the Gujarat State Electricity Corporation Ltd, owns approximately 5,940 of coal power capacity. Their major projects include the Bhavnagar power station, Gandhinagar Thermal Power Station, Kutch GSECL power station, Sikka Thermal Power Station, Ukai Thermal Power Station, and Wanakbori Thermal Power Station.[9][90]
Torrent Power: Owns the 1200 MW DGEN Mega Power Project, the 1147.5 MW SUGEN project, the 382.5 MW UNOSUGEN, and the 362 MW AMGEN project in Gujarat. In addition, Torrent owns 10 wind and solar projects, totaling 786.5 MW.
Nuclear Power Corporation Of India Ltd.: Owns the only nuclear plant in Gujarat, Kakrapar nuclear power plant, with a capacity of 1840 MW.[91]
Major owners of prospective renewables
Extra large projects in India frequently have multiple developers. The Gujarat Hybrid Renewable Energy Park, for instance, has six so far:
-Adani Green Energy has been allocated 19,000 hectares for wind and solar
-Sarjan Realties gets 9,500 hectares for wind and solar
-National Thermal Power Corporation (NTPC) gets 9,500 hectares for wind and solar
-Gujarat State Electricity Corporation gets 6,650 hectares for wind and solar
-Gujarat Industries Power Company Limited gets 4,750 for wind and solar
-Soler Energy Corporation of India (SECI) will take 23,000 hectares for solar only
Each MW requires up to two hectares of space.[92]
NTPC Ltd.: This company has plans to build other large projects totaling 5,170 MW of solar, most of which will be the 4750 MW Kutch (NTPC) Solar Park.[12]
Finance
Clean energy investments have recently expanded in India, reaching USD$68 billion in 2023 and representing a 40% increase relative to 2016-2020. Nearly half of this spending focused on low-carbon power sector technologies, though investments need to increase by an estimated 20% to meet India’s climate and clean energy goals. Meanwhile, coal spending also increased to reach USD$33 billion in 2023. Despite this, globally, the cost of capital has increased in recent years which has made local currency financing more expensive. This is particularly evident in India and other emerging economies where local currency financing is more prevalent.[39]
Approximately USD $386 billion, or Rs 32.45 lakh crore, has been committed for renewable energy projects across India, according to the country's power and renewable energy minister.[93]
Potential providers of wind/solar finance
In early 2024, President Modi approved a government investment of ₹15,336 crore to support electrification of Particularly Vulnerable Tribal Groups in 18 states. The goal is to use solar to electrify one lakh off-grid households from 2023 through 2026. The Central Government's investment is matched by ₹8,768 crore provided by states.[94]
Ministry of New and Renewable Energy (MNRE):
There are eight modes by which solar parks are developed with Central Financial Assistance (CFA) from the MNRE, as shown in the table to the left.
For wind power, similar government incentives and programs exist including (but not limited to): Permitting Foreign Direct Investment (FDI) up to 100 percent under the automatic route, Waiver of Inter State Transmission System (ISTS) charges for inter-state sale of solar and wind power for projects to be commissioned by 30th June 2025, setting up of Project Development Cell for attracting and facilitating investments, standard bidding guidelines for tariff-based competitive bidding process for procurement of Power from Grid Connected Solar PV and Wind Projects, concessional custom duty exemption on certain components required for manufacturing of wind electric generators, and Generation Based Incentive (GBI) is being provided to the wind projects commissioned on or before 31st March 2017.[95]
Public Private Partnerships:
The first major solar installation in India, which was inaugurated in 2012, was Gujarat's own Charanka solar park, which houses multiple solar and wind farms totaling 500 MW. At the time, projects like this were not seen as scalable or affordable, but that has shifted drastically in the past decade. In 2010, when renewable energy was still taking off in the country, major lenders for renewable energy companies in India were private Non-Banking Financial Companies (NBFCs) and the Indian Renewable Development Agency (IREDA), which is a Public Limited Government Company NBFC. In 2021 that has shifted to predominantly private banks, global bonds, ECB lenders, and far less use of NBFCs. Tariffs have also dropped from Rs15/kWh to less than Rs2/kWh. [96][97]
Today large private banks like the State Bank of India (SBI), HDFC Bank, Axis Bank and ICICI Bank are major funders of renewables while avoiding the thermal energy sector. Major players in equity include sovereign entities like ENEL, CDPQ and CPPIB, GIC, Temasek, IFC, CDC, and NIIF, as well as Private Equity firms like Goldman Sachs, KKR, GIP, Actis, Morgan Stanley, ADIA, and JP Morgan. Major companies like Total SE, Shell, Petronas, Adani, Tata, and Reliance Industries. [98]
Over the next decade, India needs $10.1 trillion in funding to meet its net-zero goal of 2070. Climate Finance Leadership Initiative (CFLI) India members have recently announced the potential to mobilize $6.5 billion from Macquarie Group, Tata Motors, various banks including the State Bank of India, and other public-private collaborations.[99]
In 2019, SB Energy, an affiliate of Soft Bank of Japan, announced to invest USD $4 billion or Rs 30,000 crore in the renewable energy sector in Gujarat. The money will be invested on solar, wind, and other unconventional renewable energy development[100]
In 2022, the state-owned Indian Renewable Energy Development Agency (IREDA) sanctioned a total of Rs. 121,061 crores (~USD $14.5 billion), of which Rs. 8,553 crores (~USD $1.04 billion) were allocated for 190 RE project accounts in Gujarat. The company has disbursed approximately Rs. 3,965 crores (~USD $480 million) in Gujarat, out of a cumulative loan disbursement of Rs. 79,994 crores (~USD $9.6 billion) in the country.[101]
IREDA is also planning to set up an office in the Gujarat International Finance Tec-City (also known as GIFT City) in Gandhinagar district, Gujarat. This plan was announced in mid-2023, and the purpose of the office is to finance renewable energy projects in foreign currency, allowing the IREDA to avoid foreign exchange hedging costs.[102][103]
Just Energy Transition Partnerships
Other
Multi-billionaire Gautam Adani announced a commitment of ₹2 lakh crore (~USD 25 billion) to Gujarat to increase job opportunities and expand renewable energy development. The investment will support construction of a 30-GW green energy park in Khavda, Kutch, Gujarat and aims to create more than 100,000 local jobs.[104]
Hydrogen:
Reliance Industries is leading a $12b (around one trillion rupees) project to build a green hydrogen hub in Gujarat. The hub would involved 14 plots of land covering 1,456 hectares on India's west coast. Reliance and the company Greenko plan to produce 90,000 tonnes per year of output, while Welspun would produce 20,000.[105] Additionally, APM Terminals Pipavav is developing a green hydrogen "ecosystem" and port structure for shipping.[106]
Gujarat has also been developing it's "GIFT City" project, designed to put the state at the epicenter of global finance and IT. Located between Ahmedabad and Gandhinagar, stakeholders include the Gujarat Urban Development Company (GUDCL), Gujarat Industrial Development Corporation (GIDC), and Gujarat Maritime Board (GMB).[107] In April of 2024, IREDA set up an office in GIFT City to boost green hydrogen and renewable energy projects.[108]
Articles and resources
Related GEM.wiki articles
References
- ↑ 1.0 1.1 "Renewable Energy" (PDF). vibrantgujarat.com.
{{cite web}}
: CS1 maint: url-status (link) - ↑ www.ETEnergyworld.com. "Gujarat sets 30,000 MW renewable energy generation target by 2022 - ET EnergyWorld". ETEnergyworld.com. Retrieved 2023-05-24.
- ↑ www.ETEnergyworld.com. "PM Modi to inaugurate 30,000 MW renewable energy park on Dec 15 - ET EnergyWorld". ETEnergyworld.com. Retrieved 2023-05-24.
- ↑ "World's largest 30,000 MW solar wind park in Gujarat to be fully operational by 2026: Govt - DeshGujarat". DeshGujarat. 2023-03-27. Retrieved 2023-05-24.
- ↑ Fabienne Lang (2020-12-21). "India Is Building the World's Largest Hybrid Renewable Energy 'Megapark'". Retrieved 2023-05-24.
- ↑ 6.0 6.1 6.2 Mayank Aggarwal. "The mega renewable energy park may not be as green as expected". india.mongabay.com. Retrieved 2023-05-24.
- ↑ 7.0 7.1 Tanvi Deshpande (2023-03-05). "Gujarat's Famous Solar Village Has Left Herders Without A Pasture". Retrieved 2023-06-02.
- ↑ "Energy in India today – India Energy Outlook 2021 – Analysis - IEA". IEA. Retrieved 2023-05-26.
- ↑ 9.0 9.1 9.2 Global Energy Monitor, Global Coal Plant Tracker, January 2024 release.
- ↑ Global Oil and Gas Plant Tracker," Global Energy Monitor, February 2024.
- ↑ Global Energy Monitor, Global Hydropower Tracker, May 2023 release.
- ↑ 12.0 12.1 12.2 Global Energy Monitor, Global Solar Power Tracker, December 2023 release.
- ↑ Nearly 70.1 GW Solar Power Capacity Installed in the Country: Union Minister for New & Renewable Energy and Power Ministry of New and Renewable Energy, Aug-9-2023
- ↑ 14.0 14.1 Global Energy Monitor, Global Wind Power Tracker, December 2023 release.
- ↑ “Regulatory update on Renewable Energy Policy 2023 issued by the State of Gujarat,” JSA Advocates & Solicitors, October 10 2023
- ↑ “SECI invites proposals for 500-MW offshore wind energy project in Gujarat,” Energy World, September 16 2024
- ↑ “Indian Renewable Energy Status Report: Background Report for DIREC 2010,” National Renewable Energy Laboratory, October 2010
- ↑ “India hits 20GW solar capacity milestone,” The Times of India, January 31 2018
- ↑ “India's 100GW of Solar by 2022: Pragmatism or Targetitis?,” Economic and Political Weekly, December 16 2015
- ↑ “India achieves 70.10 GW solar energy against target of 100GW by year 2022,” Energyworld, July 28 2023
- ↑ “India installed 1.6 GW of rooftop solar in 2022,” PV Magazine, March 2 2023
- ↑ “India’s RE Triumph: 500 GW by 2030 with 280 GW from Solar; PLI Scheme Fuels National Hydrogen Mission,” SolarQuarter, July 31 2023
- ↑ "India's clean energy transition is rapidly underway, benefiting the entire world – Analysis - IEA". IEA. Retrieved 2023-05-26.
- ↑ 24.0 24.1 "India's Expanding Clean Energy Workforce 2022 Update" (PDF). nrdcindia.org. 2023. Retrieved 5/30/2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ Nirendra Dev (2022-09-16). "Gujarat focuses on net-zero and carbon-free ecosystem, 50 per cent energy needs from renewable energy sources by 2030". Organiser. Retrieved 2023-06-02.
- ↑ 26.0 26.1 "Gujarat is now the Fourth State to Meet RE Targets For 2022, But Four Key States Need to Ramp Up – EQ Mag Pro". EQ Mag. Retrieved 2023-06-02.
- ↑ India’s clean energy transition is rapidly underway, benefiting the entire world IEA, Jan-10-2022
- ↑ India sets sight on 40 GW renewable energy capacity by 2024: Bhupinder Bhalla, Secy, MNRE EnergyWorld, Sep-26-2023
- ↑ "Gujarat Renewable Energy Policy 2023,” JMK Research & Analytics, October 12 2023
- ↑ "Gujarat to reduce carbon emissions from power production to 139 million tonnes by 2030". The Economic Times. Retrieved 2023-06-02.
- ↑ “India targets 412 GW from renewables by 2030, aiming to cut fossil fuel share to 41%,” EnergyWorld, January 8 2024
- ↑ Global Energy Monitor, Global Nuclear Power Tracker, October 2023 release.
- ↑ “New nuclear reactor in India reaches first criticality,” Power Technology, December 20 2023
- ↑ “Quarterly Report on Under-construction Renewable Energy Projects,” Government of India Ministry of Power, Central Electricity Authority, Renewable Project Monitoring Division, June 2024
- ↑ 35.0 35.1 “Adani Green Energy operationalizes 1,000 MW (1 GW) of the 30,000 MW Khavda renewable energy park,” Adani Renewables, March 11 2024
- ↑ 36.0 36.1 Subramanian, Meera (2023-04-26). "India's Quest to Build the World's Largest Solar Farms". The New Yorker. Retrieved 2023-05-31.
- ↑ 37.0 37.1 37.2 Yenneti, K & Day, R 2015, 'Procedural (in)justice in the implementation of solar energy: The case of Charanaka solar park, Gujarat, India', Energy Policy, vol. 86, pp. 664-673. https://doi.org/10.1016/j.enpol.2015.08.019
- ↑ Mayank Aggarwal. "A decade on, India's first solar park has many promises left to fulfil". india.mongabay.com. Retrieved 2023-06-09.
- ↑ 39.0 39.1 “World Energy Investment 2024,” International Energy Agency, June 2024
- ↑ 40.0 40.1 Global Coal Mine Tracker, Global Energy Monitor, April 2024 release.
- ↑ Global Energy Monitor, Global Oil and Gas Extraction Tracker, March 2024 release.
- ↑ "Major Oil Fields in India - IAS Site". IAS Site. 2021-06-04. Retrieved 2023-05-25.
- ↑ “The 8 largest oil refineries in the world,” Sterling Thermal Technology, February 15 2023
- ↑ “Zydus Group to invest Rs 5,000 cr in Gujarat,” EnergyWorld, January 13 2024
- ↑ “Vibrant Gujarat Summit: NTPC Green Energy signs MoUs with GSPC, GPPL for green hydrogen projects,” EnergyWorld, January 13 2024
- ↑ Joshua S Hill. "Gujarat Cancelling 4 Gigawatt Coal Power Plant As India Moves Away From Coal - CleanTechnica". cleantechnica.com. Retrieved 2023-06-05.
- ↑ PSU Watch Bureau. "'India has retired 56 coal-based thermal power plants since 2016; 47 more to follow'". PSU Watch. Retrieved 2023-06-05.
- ↑ 48.0 48.1 Kapoor, Means, Driskell Tate (October 2022). "Why India's New Coal Mines Won't Solve its Power Crisis" (PDF). globalenergymonitor.org. Retrieved 6/13/2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: multiple names: authors list (link) CS1 maint: url-status (link) - ↑ “Air Quality and Climate Policy Integration in India: Frameworks to deliver co-benefits,” International Energy Agency, July 2021
- ↑ 50.0 50.1 “The Index,” Air Quality Life Index, Retrieved October 31 2023
- ↑ "Examining the impact of natural gas use on Indian economy and environment | Indian Institute of Technology Bombay". www.iitb.ac.in. Retrieved 2023-05-25.
- ↑ "Coal Plants by Country: Units," Global Coal Plant Tracker, accessed June 2017
- ↑ Driskell Tate, Ryan (March 2022). "Bigger than Oil or Gas? Sizing up Coal Mine Methane 2022" (PDF). Globalenergymonitor.org. Retrieved 6/13/2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "62 teargas shells lobbed as farmers clash with policy," Times of India, 14 May 2018
- ↑ 55.0 55.1 55.2 55.3 55.4 55.5 55.6 55.7 55.8 "Renewable Energy Employment by Country". www.irena.org. Retrieved 2023-05-30.
- ↑ About 40 percent of India’s districts have some form of coal dependency Mongabay-India, July-1-2021
- ↑ Fossil fuel phase outs to meet global climate targets : investigating the spatial and temporal dimensions of just transitions Pai, Sandeep, University of British Columbia, June-2021
- ↑ "Future skills and job creation with renewable energy in India: Assessing the co-benefits of decarbonising the power sector" (PDF). CEEW.in. October 2019. Retrieved 6/8/2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ “Grew Energy to set up solar component unit in Gujarat's Dholera for Rs 3,800 cr,” EnergyWorld, January 12 2024
- ↑ “Suzlon secures a repeat order ot 193.2 MW from The KP Group in Gujarat,” EnergyWorld, December 21 2023
- ↑ “Net Zero Roadmap: A Global Pathway to Keep the 1.5 °C Goal in Reach,” International Energy Agency, September 2023
- ↑ 62.0 62.1 Gujarat government's new policy aims to generate half the power through renewable sources by 2030 The Economic Times, Oct-4-2023
- ↑ Shetty, Sangita (July 18, 2022). "Gujarat Govt Decides To Allot 6000 Hectares Wasteland For Renewable Energy Park". solarquarter.com. Retrieved 6/8/2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ Kalpana Sunder. "The 'solar canals' making smart use of India's space". Retrieved 2023-06-09.
- ↑ Global Coal Mine Tracker Global Energy Monitor, April 2023
- ↑ “Young Professional’s Guide To: Gujarat, India - A State on the Move,” The Way Ahead, February 9 2020
- ↑ “Over 44% of electricity generation capacity in Gujarat comes from renewable resources,” Economic Times, October 5 2023
- ↑ 68.0 68.1 “Q&A: electricity generation and transmission in India,” Lexology, September 27 2021
- ↑ Lakhanpal, Shikha. "The Social and Environmental costs of Renewable energy projects". atree.org. Retrieved 5/30/2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ 70.0 70.1 “Compliances for Renewable Energy Companies in India,” Complinity, Retrieved February 12 2024
- ↑ “Environmental Clearance - The Process,” Centre for Science and Environment, Retrieved February 12 2024
- ↑ “Functions,” Gujarat Electricity Regulatory Commission, Retrieved February 12 2024
- ↑ SMSala. "Eight Years of the Modi Government: Transformation of the Power Sector". Rising Kashmir. Retrieved 2023-06-12.
- ↑ "TARIFF FRAMEWORK FOR PROCUREMENT OF POWER BY DISTRIBUTION LICENSEES FOR THE STATE OF GUJARAT". The Leading Solar Magazine In India. Retrieved 2023-06-09.
- ↑ 75.0 75.1 75.2 Singh, Roopwant (08/04/2022). "GUJARAT ELECTRICITY REGULATORY COMMISSION (PROCUREMENT OF ENERGY FROM RENEWABLE SOURCES) (THIRD AMENDMENT) REGULATIONS, 2022" (PDF). Gercin.org. Retrieved 6/8/2023.
{{cite web}}
: Check date values in:|access-date=
and|date=
(help); line feed character in|title=
at position 55 (help)CS1 maint: url-status (link) - ↑ Joshi, Arjun (April 12, 2022). "Renewable Power Obligation Target in Gujarat Set at 17% for FY 2023". Mercomindia.com. Retrieved 6/8/2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "MNRE Annual Report 2022-23" (PDF). Retrieved 6/12/2023.
{{cite web}}
:|archive-url=
requires|archive-date=
(help); Check date values in:|access-date=
(help) - ↑ "U.S.-India Energy Cooperation". Energy.gov. Retrieved 2023-06-12.
- ↑ "Under PM's Gati Shakti Master Plan, 27,000 circuit kilometers of transmission lines to be added at an investment of Rs. 75,000 crores by 2024-25: Union Power & NRE Minister Shri R. K. Singh". www.pib.gov.in. Retrieved 2023-06-02.
- ↑ “State Transmission Utility (STU) Plan of Transmission Sector: Gujarat,” Gujarat Energy Transmission Corporation Limited, March 2022
- ↑ "Govt plans to double power transmission capacity in Kutch, Gujarat". Retrieved 2023-06-02.
- ↑ “Power Grid bags transmission project in Gujarat,” Energy World, September 20 2024
- ↑ Bellini, Emilliano (March 7, 2023). "Sterlite Power commissions 5 GW green energy corridor project in India". PV Magazine. Retrieved 6/2/2023.
{{cite news}}
: Check date values in:|access-date=
(help) - ↑ Sen, Somit (April 23, 2023). "Long-distance transmission corridor to bring green power from Gujarat to Mumbai by year-end". Mumbai Mirror. Retrieved 2023-06-02.
- ↑ “KBTL Pursues Transmission License For Gujarat Renewable Energy Project,” Solar Quarter, February 13 2024
- ↑ Prateek, Saumy (August 8, 2018). "Read more: https://www.mercomindia.com/cea-transmission-infrastructure-plan-wind". Retrieved 6/2/2023.
{{cite web}}
: Check date values in:|access-date=
(help); External link in
(help)CS1 maint: url-status (link)|title=
- ↑ "Gujarat govt doubles land payout for installing power infra". The Economic Times. Retrieved 2023-06-09.
- ↑ "Thermal Power Generation Company in India | Adani Power Limited". www.adanipower.com. Retrieved 2023-06-01.
- ↑ "Gujarat Industries Power Company Ltd". www.gipcl.com. Retrieved 2023-06-01.
- ↑ "Power Generation – GSECL". www.gsecl.in. Retrieved 2023-06-01.
- ↑ "Business Areas: Generation". torrentpower.com. Retrieved 6/1/2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ Simrin Sirur. "How Gujarat is building 'world's largest' solar power park, close to its border with Pakistan". theprint.in. Retrieved 2023-06-12.
- ↑ “Banks and financial institutions have committed $386 bn funding for renewable energy projects,” Energy World, September 16 2024
- ↑ “Centre approves over ₹24,000 crore for tribal solar electrification scheme,” EnergyWorld, January 8 2024
- ↑ "MNRE Annual Report 2022-23" (PDF). Retrieved 6/5/2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "IREDA". www.ireda.in. Retrieved 2024-05-28.
- ↑ "India's first solar park at Charanka village in Gujarat". The Economic Times. Retrieved 2024-05-28.
- ↑ Saboo, Ankur (February, 2022). "Renewable Energy Financing Landscape in India The Journey So Far and the Need of the Hour" (PDF). ieefa.org. Retrieved May 28, 2024.
{{cite web}}
: Check date values in:|date=
(help); line feed character in|title=
at position 27 (help)CS1 maint: url-status (link) - ↑ "CFLI India Announces Climate Finance Solutions with the Potential to Mobilize over US $6.5 billion in India". Bloomberg Philanthropies. Retrieved 2024-05-24.
- ↑ Japan's Soft Bank Group to invest Rs 30,000 crore in renewable energy in Gujarat The Economic Times, Dec-9-2019
- ↑ IREDA sanctions loan of Rs. 8,553 crores in Gujarat for Renewable Energy projects IREDA India, June-10-2022
- ↑ IREDA to establish office in Gujarat’s GIFT city to finance Renewable Energy projects in foreign currency Ministry of New and Renewable Energy, India, Feb-24-2023
- ↑ IREDA to set up office in Gujarat's GIFT City to finance renewable energy projects EnergyWorld from The Economic Times, Fe-25-2023
- ↑ “Adani Group commits ₹2 lakh crore for Gujarat's green energy, job creation,” EnergyWorld, January 10 2024
- ↑ Parkes, Rachel (2024-04-11). "Some of India's largest companies teaming up for massive $12bn green hydrogen hub in Gujarat: reports". hydrogeninsight.com. Retrieved 2024-05-28.
- ↑ "APM Terminals Pipavav to develop green hydrogen ecosystem - APM Terminals". www.apmterminals.com. Retrieved 2024-05-28.
- ↑ "GIFT | Welcome to the new epicentre of Global Finance and IT". www.giftgujarat.in. Retrieved 2024-05-28.
- ↑ DeshGujarat (2024-04-18). "IREDA's GIFT City office to boost Green Hydrogen & Renewable Energy projects". DeshGujarat. Retrieved 2024-05-28.