Guangdong Gas Pipeline Network

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Guangdong Gas Pipeline Network 广东输气管网, consisting four sub-networks with proposed, under construction and operating gas pipelines in Guangdong Province, China.

Location

The pipeline network is within the Guangdong Province, China.[1]

Loading map...
广东省天然气主干管网规划图.png
广东省天然气管网规划图.png
广东省现状天然气主干管网-截至2020年.png

Background

Guangdong Province consumed the most gas among provinces in China in 2023. With 38.7 billion cubic meters, it's nearly 10% of the country's total gas consumption.

The major sources for gas in Guangdong include 6 LNG terminals (Zhuhai LNG Terminal, Guangdong Dapeng LNG Terminal, Diefu LNG Terminal, Huizhou LNG Terminal, Hongmei LNG Terminal, Shenzhen LNG Terminal), gas from Central Asia through West-East Gas Pipeline 2 and West-East Gas Pipeline 3, as well as Sino-Myanmar Gas Pipeline.

In 2012, the mileage of operating gas pipeline in Guangdong Province was around 500 kilometers. [2]It increased to 3630 kilometers in the end of 2020. [3]The province planned to further increase the gas pipeline mileage to 5800 kilometers by 2025.[4]

Under tge provincial gas pipeline network, the province planned to build four sub- networks within the province, including Pearl River Delta gas pipeline network, Guangdong North Gas Pipeline Network, Guangdong East Gas Pipeline Network and Guangdong West Gas Pipeline Network.

In September 2020, the National Pipeline Group and Guangdong Provincial Government signed a strategic cooperation agreement on the reform of the gas pipeline network system in Guangdong Province (关于广东省天然气管网体制改革战略合作协议). Guangdong provincial gas pipeline network became the first provincial gas pipeline network to be integrated into PipeChina.[5]

Network details

Guangdong Pearl River Delta gas pipeline network 广东省珠三角天然气输气管网

Loading map...


Pearl River Delta gas pipeline network consists two phases. [5]Phase I began construction in 2009,[6] reaching seven cities, totalling 463 kilometers. The transport capacity is 16 billion cubic meters.[2] Phase I began operating in 2012.[7] Phase II consists four pipelines. The total mileage is 234 kilometers. Phase II began operating in 2014.[5]

2009年,珠三角外环管网项目分两期启动,到2014年12月,全长238公里的二期工程完工,并与已完工的一期工程连通,与此前建成的珠三角内环管网连通。至此,“十二五”期间,覆盖珠三角的天然气内外环管网建成。中海油广东大鹏LNG、番禺/惠州海上天然气及中石油西气东输二线陆上天然气等通过管网输入珠三角。

Phase I:

Aotou-Guangzhou Pipeline 鳌头-广州干线
Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.
  • Capacity: 16 billion cubic meters per year
  • Length: 42 kilometers[8]
  • Diameter: 914 millimeters[8]
  • Status: Operating
  • Start year: 2012[9]
  • Cost:
Guangzhou-Zhaoqing Pipeline 广州-肇庆干线
Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.
  • Parent:
  • Capacity:
  • Length: 166.6 kilometers[8]
  • Diameter: 914 millimeters[8]
  • Status: Operating
  • Start year: 2012[7]
  • Cost:
Guangzhou-Huizhou Pipeline 广州-惠州干线
Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.
  • Parent:
  • Capacity:
  • Length: 160.5 kilometers[8]
  • Diameter: 914 millimeters
  • Status: Operating
  • Start year: 2012
  • Cost:

Shaoguan Branch, Qingyuan Branch, Dongguan Branch 韶关支线, 清远支线, 东莞支线

Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.
  • Parent:
  • Capacity:
  • Length: 92.3 kilometers
  • Diameter: 450 millimeters, 600 millimeters
  • Status: Operating
  • Start year: 2012
  • Cost:

Phase II:

Fengma-Liudong 冯马-骝东输气管道支线
Loading map...
  • Owner: CNOOC Guangdong NATURAL Gas Co., Ltd.[10]
  • Parent company:
  • Capacity: 0.47 bcm/y[10]
  • Length: 23 kilometers[2]
  • Diameter: 762 mm[10]
  • Status: Operating[2]
  • Start year: 2014[5]
  • Cost:
Gaoming-Zhaoqing 高明-肇庆输气联络线
Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.
  • Parent company:
  • Capacity: 0.049 bcm/y( the amount of 2016)[11]
  • Length: 23.5 kilometers[12]
  • Diameter: 914 mm[13]
  • Status: Operating[12]
  • Start year: 2014[12]
  • Cost: 309.92 million RMB[14]
Liwan Offshore Gas Pipeline 荔湾海气登陆管线
Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.
  • Parent company:
  • Capacity: 12 bcm/y[15]
  • Length: 22.5 kilometers[16]
  • Diameter: 914/660 mm[17]
  • Status: Operating[16]
  • Start year: 2014[16]
  • Cost:

Guangdong East Gas Pipeline Network 粤东天然气主干管网

also known as Guangdong Provincial Natural Gas Network Phase III 广东省天然气管网三期工程.

Loading map...

The Guangdong East Gas Pipeline Network was described in the 13th Provincial Energy Development Five-Year Plan (2016–2020). The network includes five pipelines: a LNG transport line, one major pipeline, one connecting pipeline, and two branches.[18] The proposed length of the full network was 539.8 kilometers, and the total estimated cost was 6.29 billion RMB.[18] In Guangdong Province's 14th Five-Year Plan, pipeline systems were proposed with the goal of reaching every county in the province, though no specific pipelines were mentioned. A map from the 13th Five-Year Plan describes the likely routes.[19]

  • Contruction on the Huizhou–Haifeng Pipeline 惠州—海丰干线 segment began in July 2021.[20]
  • Construction on the Huizhou–Heyuan Branch 惠州—河源支干线 began in 2019.[21] Its source will be the imported LNG from the West-East Gas Pipeline 2, Huizhou LNG Terminal.
  • Construction of the Jieyang–Meizhou Branch 揭阳—梅州支干线 was completed in 2020.[22] Its source will be the West-East Gas Pipeline 2, Jieyang LNG Terminal.
  • Intended approval for the Haifeng–Huilai Connecting Pipeline 海丰—惠来联络线 was announced in December 2020.[23]
  • Jieyang LNG Terminal Transport Pipeline began operating in 2021. It was built by CNPC and, when completed, transferred to PipeChina and merged into the Guangdong East Gas Pipeline Network
  • Network operator: Guangdong Natural Gas Pipeline Co., Ltd. 广东省天然气管网有限公司[24]
  • Network owner: PipeChina (49%), Guangdong Energy Group (28%), PipeChina East Oil Storage & Transportation Co., Ltd. 国家管网集团东部原油储运有限公司 (23%)[24]
  • Network length: 539.8 kilometers[18]
  • Network cost: 6.29 billion RMB[18]

Note the length of the entire network listed above, 529.8 kilometers, is less than that of the individual segments below combined. As of September 2021 there was not a clear explanation for this discrepancy.

Huizhou–Haifeng Pipeline 惠州-海丰干线

  • Owner: PipeChina Guangdong Natural Gas Pipeline Company[25]
  • Capacity: 3.65 billion cubic meters per year[26]
  • Length: 155 kilometers[26]
  • Diameter: D914 millimeters[26]
  • Status: Construction[20]
  • Start year:
  • Cost: 2516.90 million RMB
Loading map...

Huizhou–Heyuan Branch 惠州-河源支干线

  • Owner: PipeChina Guangdong Natural Gas Pipeline Company[25]
  • Capacity: 0.30 billion cubic meters per year[21]
  • Length: 89 kilometers[21]
  • Diameter: D610 millimeters[21]
  • Status: Construction[21]
  • Start year:
  • Cost: 1213.22 million RMB[27]
Loading map...

Note the capacity of 0.30 billion cubic meters per year has been calculated using 8.64 x (10^4) cubic meters per day, according to the environmental impact assessment. A value of 350 days per year is used to get the total per year, and 350 days per year appears to be the standard unit in China's reports.[25]

Jieyang–Meizhou Branch 揭阳—梅州支干线

  • Owner: PipeChina Guangdong Natural Gas Pipeline Company[25]
  • Capacity: 1.27 billion cubic meters per year[28]
  • Length: 150.7 kilometers[28]
  • Diameter: 610 mm[29]
  • Status: Operating[22][30]
  • Start year: 2021[22]
Loading map...

Haifeng–Huilai Connecting Pipeline 海丰-惠来联络线

Guangdong Gas Pipeline Network Haifeng-Huilai 1.jpg
  • Owner: PipeChina Guangdong Natural Gas Pipeline Company[25]
  • Capacity: 5.74 billion cubic meters per year[23]
  • Length: 166.6 kilometers[23]
  • Diameter: 914 millimeters[23]
  • Status: Operating[31]
  • Cost: 3133.68 million RMB[32]
    Loading map...

Jieyang LNG Terminal Transport Pipeline 粤东LNG接收站配套外输管道

Also known as Guangdong East LNG Terminal Transport Pipeline, this pipeline transports gas from the Jieyang LNG Terminal. It includes one major line and two branches, and it mainly supplies gas to the Dananhai Petrochemical Industry Park.[33]

  • Owner: PipeChina
  • Capacity: 5.3 billion cubic meters per year[34]
  • Length: 171.35 kilometers[35]
  • Diameter: 914 mm[36]
  • Status: Operating[33]
  • Start year: 2021[33]
  • Cost:
Loading map...

Huafeng Huaying LNG Export Gas Pipeline 华丰华瀛LNG接收站配套外输管线

The pipeline is a supporting project of Huafeng LNG Terminal.

Loading map...
Chaozhou LNG Terminal Transport Pipeline.jpg
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.[37]
  • Parent:
  • Capacity: 8.0 billion cubic meters per year[37]
  • Length: 59 kilometers[37]
  • Diameter: 914/1016 mm (914 mm of the trunk line; 1016 mm of the connection)[38]
  • Status: Construction[39]
  • Start year:
  • Cost: 1.342 billion RMB[40]

Shante Gas Power Station Gas Supply Pipeline 汕特燃机电厂供气支线[41][42]

The pipeline runs from the Chaozhou LNG Terminal to Lianhua, Shantou, in Guangdong Province, China.[41]

Loading map...
  • Owner: PipeChina Guangdong Natural Gas Pipeline Company[41]
  • Parent:
  • Capacity: 1.1 billion cubic meters per year[41]
  • Length: 62 kilometers[41]
  • Diameter: 610/323.9 mm[43]
  • Status: Construction[44]
  • Cost: 986.2022 million RMB[43]

Huizhou LNG Terminal Transport Pipeline 惠州LNG接收站配套外输管道[45][46]

  • The pipeline starts at Huizhou LNG Terminal and branches into three segments, two of which are approximately parallel and end at the Daya Bay Terminal, and a third that ends at Baihua Industrial Park.[45]
Loading map...
    • Owner: Guangdong Energy Group Natural Gas Co., Ltd.[46]
    • Capacity: 14 billion cubic meters per year[47]
    • Length: 115 kilometers[45]
    • Diameter: 924 millimeters[45]
    • Status: Construction[48]
    • Start year:
    • Cost: 2139.11 million RMB

Jieyang-Dananhai Gas Pipeline 揭阳-大南海天然气管道工程

  • Jieyang natural Gas Pipeline includes 1 trunk line and 2 branch lines, with a total pipeline length of 146.8km. The trunk line is Jieyang-Dananhai Pipeline.
    Loading map...
    • Operator:
    • Owner: Jieyang PetroChina Kunlun Gas Co., Ltd.[49]
    • Capacity: 9 billion cubic meters per year[49]
    • Length: 123.5 kilometers[50]
    • Diameter: 813 mm[51]
    • Status: Operating[50]
    • Start year: 2022 (The trial operation of this pipeline began on March 2022)[50]
    • Cost: 1768.75 million RMB[49]

Jieyang Gas Pipeline Zhanlong Branch 揭阳天然气管道工程占陇支线

Jieyang natural Gas Pipeline includes 1 trunk line and 2 branch lines, with a total pipeline length of 146.8km. Zhanlong Branch is one of the branches.

Loading map...

Guandong North Gas Pipeline Network 粤北天然气主干管网

Loading map...


Guangdong North Gas Pipeline Network, also known as Shaoguan-Guangzhou Line, consists of one major line at 185.5 kilometers in length, as well as three additional branches that make up the remainder of the length[53]

The Shaoguan-Aotou trunk line starts at the first station of Shaoguan in Zhenjiang District and ends at the Wengyuan Substation in Wengcheng Town, Wengyuan County, China. Construction began in February 2019[54], and by January 2021 the pipeline had finished a trial operation[55]

  • Shaoguan-Aotou Trunk Line: 185.5 kilometers long, pipe diameter of 914 millimeters[53]with the capacity of 4.2 billion cubic meters per year.
  • Yingde Branch Line: 32 kilometers long, pipe diameter of 610 millimeters[53] The route and length changed in 2020. The length increased to 46 kilometers and the capacity remained the same at 1.5 billion cubic meters per year. [56]
  • Lechang Branch Line: 13.2 kilometers long, pipe diameter of 323.9 millimeters[53]
  • Ruyuan Branch Line: 5.6 kilometers long, pipe diameter of 323.9 millimeters[53]

Shaoguan-Guangzhou Line 韶关—广州干线

  • Owner: Guang Dong Natural Gas Grid Co., Ltd.[57]
  • Parent:
  • Capacity: 4.5 billion cubic meters per year[57]
  • Length: 236.43 kilometers[58]
  • Diameter: 914 millimeters
  • Status: Operating[59]
  • Start year: 2021[59]
  • Cost: 4.5203371 billion RMB[58]

Guangdong West Gas Pipeline Network 粤西天然气主干管网 [60].[61]

Loading map...

Guangdong West Gas Pipeline Network was outlined in Guandong Province's 13th Five-Year Plan (2016–2020).[62]

  • As of September 2021, no further details for the Zhanjiang-Xuwen Pipeline 湛江-徐闻干线 can be found.*The Zhaoqing-Yunfu Pipeline 肇庆-云浮支干线 is an operating pipeline. It starts at Jindu, Gaoyao District, Zhaoqing City and ends at Silao, Yuncheng District, Yunfu City, with a total length of 42.9 kilometers.[63] Construction began on on October 23, 2018 and was completed on September 25, 2020.[63]
  • The Yangjiang-Jiangmen Pipeline 阳江-江门输气干线 was publicly announced on August 30, 2018, prior to approval on .[64]
  • Construction of the Maoming-Yangjiang Pipeline 茂名-阳江干线 began in March 2020 and was estimated to be completed by a 2021 commission date.[65][66] The pipeline's purposes was to serve Maoming and Ynagjiang, which experienced local gas shortages.
  • The Yangjiang LNG Terminal Transport Pipeline 阳江LNG外输管线 was expected to begin in 2020, and commissioning in 2023.[67] However, as of September 2021 construction had not yet been reported.

Zhanjiang-Donghai Island Pipeline 湛江-东海岛干线

  • Operator:
  • Owner:
  • Parent company:
  • Capacity:
  • Length:
  • Diameter:
  • Status: Cancelled (no more information since 2018)
  • Start year:
  • Cost:
Loading map...

Zhanjiang-Xuwen Pipeline 湛江-徐闻干线

  • Operator:
  • Parent company:
  • Capacity:
  • Length:
  • Diameter:
  • Status: Proposed
  • Start year:
  • Cost:
Loading map...

Zhaoqing-Yunfu Pipeline 肇庆-云浮支干线[60]

  • Operator:
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.
  • Parent company:
  • Capacity: 1.42 billion cubic meters per year[60]
  • Length: 42.9 kilometers[63]
  • Diameter: D610mm[60]
  • Status: Operating[68]
  • Start year: 2022[68]
  • Cost: 791.4759 million RMB[60]
Loading map...

Maoming-Yangjiang Pipeline 茂名-阳江干线[66]

  • Operator: PipeChina Guangdong Natural Gas Pipeline Company
  • Parent company: PipeChina
  • Capacity: 4 billion cubic meters per day[66]
  • Length: 156 kilometers[66]
  • Diameter: D813mm[60]
  • Status: Operating[69][70]
  • Start year: 2021[65]
  • Cost: 3.083 billion RMB[66]
Loading map...

Yangjiang-Jiangmen Pipeline 阳江-江门输气干线[71]

  • Operator: PipeChina Guangdong Natural Gas Pipeline Company[72]
  • Parent company: PipeChina
  • Capacity: 2.685 billion cubic meters per year[64][73]
  • Length: 170.3 kilometres[73]
  • Diameter: D813mm[73]
  • Status: Operating[73]
  • Start year:
  • Cost: 3.66 billion RMB[74]
Loading map...

Yangjiang LNG Terminal Transport Pipeline 阳江LNG外输管线

  • Operator: Guangdong Yangjiang Hailing Bay LNG Co., Ltd. 广东阳江海陵湾液化天然气有限责任公司[72]
  • Parent company: Guangdong Energy Group Natural Gas Co., Ltd. (50%), Pacific Oil & Gas Limited (50%)[72]
  • Capacity: 6.673 billion cubic meters per year[67][75]
  • Length: 42.7 kilometers[67]
  • Diameter: D813mm[67]
  • Status: Proposed[67]
  • Start year: 2023[67]
  • Cost: 593.6 million RMB[67]
Loading map...

Zhuhai LNG Transport Pipeline (Gaolan-Gaoming) 珠海LNG外输管道干线 (高栏港-高明)

Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.
  • Parent company:
  • Capacity: 9 billion cubic meters per year
  • Length: 158.6 kilometers
  • Diameter: 1016/914 mm[17]
  • Status: Operating
  • Start year: 2014
  • Cost:

Shenzhen LNG Peak-shaving Gas Pipeline 深圳LNG调峰接收站配套管道

Shenzhen LNG Peaking Load Acception Station Transport Line (深圳LNG调峰接收站配套管道) is an operating natural gas pipeline starting operating in 2020.[76] The pipeline's route is from Diefu LNG Terminal, Dapeng District in Shenzhen, to Qingxi Town in Dongguan, Guangdong Province, China. It connects three LNG terminals in Shenzhen with West-East Gas Pipeline 2[77]

Loading map...
  • Operator:
  • Owner: West To East Gas Transmission Branch of National Petroleum Pipeline Network Group Co., Ltd.[78]
  • Parent Company: China National Petroleum Corporation
  • Current capacity: 10.70 bcm/year
  • Proposed capacity:
  • Length: 64.3 km[79]
  • Diameter: 1016 mm[79]
  • Status: Operating[79]
  • Start Year: 2020[79]
  • Cost:

Guangdong Dapeng LNG Terminal Transport Pipeline 中海油大鹏LNG外输管线

Guangdong Dapeng LNG Terminal Transport Pipeline.jpg

Guangdong Dapeng LNG Terminal Transport Pipeline 中海油大鹏LNG外输管线 is an operating natural gas pipeline in China.[80] The source of the pipeline is the gasified natural gas at Guangdong Dapeng LNG Terminal .[81][80]

The pipeline's route is from Dapeng LNG Terminal in Chengtoujao, Dapeng District in Shenzhen, to foshan, with a branch going to Huizhou, Guangdong Province, China.[80]

Loading map...
  • Owner: GUANG DONG DAPENG LNG Company Limited
  • Parent Company: CNOOC 中海石油气电集团有限责任公司,33%;Two subsidiaries of BP Group 英格兰和威尔士广东投资有限公司,15%,英格兰和威尔士珠江三角洲投资有限公司,15%;Shenzhen Gas Group 深圳市燃气集团股份有限公司,10%;Guangzhou Gas Group 广州燃气集团有限公司,6%;Guangdong Yudean Group Natural Gas Company 广东粤电天然气有限公司,6%;Shenzhen Energy Group 深圳能源集团股份有限公司,4%;港华投资有限公司,3%;香港电灯(天然气)有限公司,3%;佛山市燃气集团股份有限公司,2.5%;东莞市能源投资集团有限公司,2.5%, 佛山市华昊能能源投资有限公司, 2.50%.
  • Current capacity: 10.30 bcm/year (7.4 mta of liquified gas)[80]
  • Proposed capacity:
  • Length: 274 mi / 441 km
  • Diameter: 323.9/914 mm
  • Status: Operating
  • Start Year: 2006[82]
  • Cost:

PipeChina Guangdong Gas Pipeline Network New proposed pipelines 国家管网集团广东管网新规划管道

Heyuan-Dongyuan Gas Pipeline 河源-东源管道

Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.[83]
  • Capacity:
  • Length: 60.8 kilometers[83]
  • Diameter: 600 millimeters[83]
  • Status: Proposed[83]
  • Start year:
  • Cost: 808.41 million RMB[83]

Heyun-Lianzhou-Lianshan Gas Pipeline 禾云-连州-连山管道

Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.[84]
  • Parent:
  • Capacity: 0.31 billion cubic meters per year[85]
  • Length: 189 kilometers(Heyun-Lianzhou 141, Lianzhou-Lianshan 48)[85]
  • Diameter: 300 millimeters(Heyun-Lianzhou)/200 millimeters (Lianzhou-Lianshan)
  • Status: Proposed
  • Start year:
  • Cost: 1187.40 million RMB[84]

Maoming-Yun'an Gas Pipeline(Maoming-Xinyi segment) 茂名-云安管道(茂名-信宜段)

Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.[86]
  • Capacity: 0.45 billion cubic meters per year[86]
  • Length: 91.18 kilometers[86]
  • Diameter: 323.9 mm[87]
  • Status: Construction[87]
  • Start year:
  • Cost:

Maoming-Yun'an Gas Pipeline(Yun'an-Luoding segment) 茂名-云安管道(云安-罗定段)

Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.[86]
  • Capacity: 0.87 billion cubic meters per year[86]
  • Length: 68.54 kilometers[86]
  • Diameter: 610 mm[88]
  • Status: Proposed
  • Start year:
  • Cost:

Meizhou-Jiaoling-Pingyuan Gas Pipeline 梅州-蕉岭-平远管道

Loading map...
  • Owner: 国家管网集团广东省管网有限公司
  • Capacity: 0.15 billion cubic meters per year[89]
  • Length: 93 kilometers[89]
  • Diameter: 323.9 mm[90]
  • Status: Construction[91]
  • Start year:
  • Cost: 678.75 million RMB[90]

Meizhou-Wuhua-Xingning Gas Pipeline 梅州-五华-兴宁管道

Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.[92]
  • Capacity: 0.155 billion cubic meters per year
  • Length: 58.50 kilometers[92]
  • Diameter: 323.9 mm[93]
  • Status: Construction[92]
  • Start year:
  • Cost: 490 million RMB[92]

Qinghe Gas Pipeline(Qingyuan-Heyun)清禾专线(清远-禾云)

Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.[94]
  • Capacity: 0.82 billion cubic meters per year[94]
  • Length: 52 kilometers[94]
  • Diameter: 600 millimeters[94]
  • Status: Construction[95]
  • Start year:
  • Cost: 499.10 million RMB[84]

Xingning-Heping-Lianping Gas Pipeline 兴宁-和平- 连平(一干两支)管道

建设内容及规模:兴宁-和平-连平项目起点为梅州-五华-兴宁项目的兴宁分输站(和平方向)站场围墙外2m,终点分别为和平末站和连平末站。项目管道包括“一干两支”,线路长度为160.8km,设计压力6.3MPa,设计输量1.5×108Nm3/a,管径为DN300和DN200。其中干线兴宁分输站-林寨清管站长度为93.3km,管径DN300;支线林寨清管站-和平末站段管道长度为29.6km,林寨清管站-连平末站段管道长度为37.9km,管径为DN200。工程沿线共设置4座站场,均为新建,其中包括1座分输站(龙川分输站),1座清管站(林寨清管站),2座末站(和平末站、连平末站)。沿线共设置5座阀室,均为监控阀室。[96]

Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.[96]
  • Capacity: 0.15 billion cubic meters per year[96]
  • Length: 160.80 kilometers[96]
  • Diameter: 300/200 millimeters[96]
  • Status: Proposed
  • Start year:
  • Cost: 1219.46 million RMB[84]

Zhu Zhong Jiang Gas Pipeline 珠中江干线(江门-中山)

国家管网集团广东省天然气管网珠中江干线项目位于珠海、江门、中山市,由“一干一支”组成,线路全长98公里,设计压力9.2兆帕,设计输气量46亿立方米/年,新建站场6座、改扩建站场1座、新建监控阀室3座及配套公用工程等。其中,干线起于江门双水首站,经江门、中山市,止于粤电中山末站,管线长76公里,设计输气量46亿立方米/年;支线起于江门睦洲分输站,经江门、珠海市,止于珠海白蕉末站,管线长22公里,设计输气量8.0亿立方米/年。[97]

Loading map...
  • Owner: Guang Dong Natural Gas Grid Co., Ltd.[97][98]
  • Capacity: 4.6 billion cubic meters per year[97][98]
  • Length: 98 kilometers[97][98]
  • Diameter: 800/400 millimeters[98]
  • Status: Proposed
  • Start year:
  • Cost: 2692.09 million RMB[99]

Guangzhou-Dongguan Gas Pipeline 国家管网集团广东省天然气管网穗莞干线项目 [100]

The pipeline runs from Zengcheng District, Guangzhou, to Gaobu Town, Dongguan.[101]

Loading map...
    • Operator:
    • Owner: Guang Dong Natural Gas Grid Co., Ltd.[101]
    • Parent company:
    • Capacity: 5.0 bcm/y[101]
    • Length: 16.25 km[101]
    • Diameter: 914 mm[102]
    • Status: Construction[100]
    • Start year:
    • Cost: 440.55 million RMB[102]
    • Financing:
    • Associated infrastructure: Guangzhou-Huizhou Pipeline[102]

Zhongke Branch 中科配套输气管道(一干一支)[103]

中科配套输气管道项目主要承担中科炼化及东兴炼化燃料用气需求,分为主干线和东兴炼化支线(“一干一支”),途经湛江市麻章区、经开区、霞山区、经济技术开发区,沿线共设3座输气站场和3座线路截断阀室,总长约75千米,设计输气量为18亿立方米/年。[104]

Loading map...

Articles and resources

References

  1. "广东省天然气主干管网规划图". chinagdp.org. Retrieved September 13, 2021.{{cite web}}: CS1 maint: url-status (link)
  2. 2.0 2.1 2.2 2.3 "广东省天然气管网二期工程太阳能发电装置 - 百度文库". wenku.baidu.com. Retrieved 2021-09-30.
  3. "广东省城镇燃气发展"十四五"规划" (PDF). zfcxjst.gd.gov.c. 2021-12. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  4. 广东省能源发展 “十四五” 规划2022-03, 广东省人民政府
  5. 5.0 5.1 5.2 5.3 "广东天然气"省网"以市场化方式融入国家管网_中国政府网". www.gov.cn. 2020-09-25.{{cite web}}: CS1 maint: url-status (link)
  6. "广东省天然气管网一期工程惠州干线开工-搜狐新闻". news.sohu.com. 2009-04-21.{{cite web}}: CS1 maint: url-status (link)
  7. 7.0 7.1 "【广东省天然气资源供需现状】-国家发展和改革委员会". www.ndrc.gov.cn. Retrieved 2021-09-21.
  8. 8.0 8.1 8.2 8.3 8.4 "广东省发展和改革委员会 - 关于广东省天然气管网一期管道工程鳌头-广州干线、广州-惠州干线、广州-肇庆干线、东莞支干线(潼湖分输站-东莞分输站段)项目的核准意见". drc.gd.gov.cn. Retrieved 2021-09-30.
  9. "中国海油广东管网向惠州供气-国务院国有资产监督管理委员会". www.sasac.gov.cn. Retrieved 2021-09-21.
  10. 10.0 10.1 10.2 广东珠海LNG项目一期工程(东干线广州段)(冯马—骝东天然气管道项目)配套固体废物污染防治设施验收意见的函, 广东省生态环境厅, 2020-06-03
  11. 行政处罚决定书〔2018〕11号, 广东省生态环境厅, 2018-10-10
  12. 12.0 12.1 12.2 "【转载】行政处罚决定书〔2018〕11号_重点领域信息公开". www.hengqin.gov.cn. Retrieved 2021-09-30.
  13. 天然气管网二期工程管道数据采集工作招标公告, 采招网,2011-10-24
  14. 关于广东省天然气管网二期工程高明-肇庆联络线项目审批前公示, 广东省发展和改革委员会, 2011-10-28
  15. 广东省环境保护厅关于广东省天然气管网二期工程荔湾海气输气管道项目竣工环境保护验收意见的函, 广东省环境保护厅, 2016-09-06
  16. 16.0 16.1 16.2 "广东省天然气管网二期工程荔湾海气输气管道项目环境保护设施验收决定公告 - 广东省生态环境厅公众网". gdee.gd.gov.cn. Retrieved 2021-09-30.
  17. 17.0 17.1 天然气管网二期工程管道线路施工招标公告, 采招网,2011-09-07
  18. 18.0 18.1 18.2 18.3 粤东天然气主干管网惠州-海丰干线项目 (惠州段) 社会稳定风险调查征求公众意见的公示, Huizhou Development & Reform Bureau, Apr. 24, 2018, accessed Sep. 6, 2021.
  19. Map of Guangdong East Gas Pipeline Network, chindagdp.com, accessed Sep. 6, 2021.
  20. 20.0 20.1 Gao Li, 粤东天然气主干管网惠州-海丰干线项目工程开工, Sinopec News, Jul. 20, 2021, accessed Sep. 6, 2021.
  21. 21.0 21.1 21.2 21.3 21.4 [1], Nanfang Daily, Sep. 25, 2020, accessed Sep. 6, 2021.
  22. 22.0 22.1 22.2 全线贯通!广东省实现21个地级市通达天然气主干管网, Dayoo News via Dayang.com, Nov. 1, 2020, accessed Sep. 6, 2021.
  23. 23.0 23.1 23.2 23.3 广东省生态环境厅拟对粤东天然气主干管网海丰-惠来联络线项目环境影响评价文件作出批准决定的公示, Department of Ecology and Environment of Guandong Province, Dec. 18, 2020, accessed Sep. 6, 2021.
  24. 24.0 24.1 国家管网集团东部原油储运有限公司, qcc, accessed Sep. 6, 2021.
  25. 25.0 25.1 25.2 25.3 25.4 粤东天然气主干管网惠州-河源支干线项目项目环境影响报告书, Environmental Impact Assessment, Nov. 2018, archived from the original on Sep. 6, 2021.
  26. 26.0 26.1 26.2 广东省发展改革委关于粤东天然气主干管网惠州-海丰干线项目核准的批复, Guangdong Development & Reform Bureau, Nov. 13, 2020, accessed Sep. 6, 2021.
  27. 粤东天然气主干管网惠州-河源支干线项目核准前公示, 广东省发展和改革委员会, 2018-09-07
  28. 28.0 28.1 广东省生态环境厅关于粤东天然气主干管网揭阳-梅州支干线项目环境影响报告书的批复, Department of Ecology and Environment of Guangdong Province, Jun 26, 2019, accessed Sep. 6, 2021.
  29. 肇庆—云浮、揭阳—梅州两条天然气管网支干线投产, 南方网,2022-09-30
  30. [2], Sichuan Oil and Natural Gas Development Research Center, Oct. 20, 2021, accessed Sep. 6, 2021.
  31. 国家管网集团“海丰—惠来”联络线向粤东地区正式供气, 国家管网集团, 2023-05-31
  32. 粤东天然气主干管网海丰-惠来联络线项目(汕尾段)社会稳定风险评估——公众参与公告, 海丰县发展和改革局, 2018-12-14
  33. 33.0 33.1 33.2 "粤东天然气主干管道并入广东省网 将提升省输气管线互联互通、互供互保能力_南方网". news.southcn.com. Retrieved 2021-09-30.
  34. "国家管网粤东LNG接收站配套外输管道投运|界面新闻 · 快讯". www.jiemian.com. Retrieved 2021-09-30.
  35. "粤东天然气主干管道并入广东省网-新华网". www.gd.xinhuanet.com. Retrieved 2021-09-30.
  36. 国家管网集团广东省管网有限公司2023年环焊缝质量风险排查开挖复检无损检测服务项目招标公告, 招标与采购网,2023-03-02
  37. 37.0 37.1 37.2 广东省生态环境厅拟对粤东天然气主干管网华丰LNG储配站和华瀛LNG接收站配套外输管线项目环境影响评价文件进行审查的公示, 广东省生态环境厅, 2019-12-02
  38. 粤东天然气主干管网华丰LNG储配站和华瀛LNG接收站配套外输管线项目《建设工程规划许可证》批后公告, 潮州市饶平县人民政府,2021-04-02
  39. 能源集团所属省天然气管网华丰LNG储配站和华瀛LNG接收站配套外输管线项目正式开工, 新浪网, 2020-06-02
  40. 粤东天然气主干管网华丰LNG储配站和华瀛LNG接收站配套外输管线项目项目环境影响报告书, 广东省天然气官网有限公司, 2019-10
  41. 41.0 41.1 41.2 41.3 41.4 汕特燃机电厂供气支线项目环境影响报告书 (金本公示稿), Shantou, accessed Sep. 14, 2021.
  42. 汕头市汕特燃机电厂供气支线项目水土保持方案审批准予行政许可决定书, Jul. 9, 2021, accessed Sep. 14, 2021.
  43. 43.0 43.1 汕特燃机电厂供气支线项目核准前公示, 汕头市发展和改革局, 2021-01-15
  44. "汕特燃机电厂供气支线项目有序推进_图片新闻_澄海区人民政府门户网站". www.chenghai.gov.cn. 2022-05-17. Retrieved 2022-08-23.{{cite web}}: CS1 maint: url-status (link)
  45. 45.0 45.1 45.2 45.3 惠州LNG接收站外输管道项目社会稳定风险调查公示, Huizhou, accessed Sep. 8, 2021.
  46. 46.0 46.1 惠州市2021年重点建设项目计划, Huizhou, accessed Sep. 8, 2021.
  47. "详细页". ggzy.gz.gov.cn. Retrieved 2021-09-30.
  48. "惠州LNG接收站外输管道项目开工建设-基层动态-广东省能源集团有限公司". www.geg.com.cn. 2021-07-29. Retrieved 2021-09-23.{{cite web}}: CS1 maint: url-status (link)
  49. 49.0 49.1 49.2 "揭阳市发展和改革局关于揭阳天然气管道工程项目核准的批复" (PDF). 2019-10-29.
  50. 50.0 50.1 50.2 致“揭阳天然气管道工程”沿线居民安全告知书, 揭阳中石油昆仑燃气有限公司, 2022-03-02
  51. 51.0 51.1 51.2 51.3 51.4 揭阳天然气管道工程EPC总承包招标公告, 电力招标网,2020-02-27
  52. 揭阳天然管道工程占陇支线线路主体贯通, 廊坊中油朗威工程项目管理有限公司, 2024-06-12
  53. 53.0 53.1 53.2 53.3 53.4 [3], Guangdong Provincial Development and Reform Commission, Jun. 5, 2018, accessed Sep. 7, 2021.
  54. [4], accessed Sep. 7, 2021.
  55. [5], Sinopec News, Jan 7, 2021, accessed Sep. 7, 2021.
  56. "粤北天然气主干管网韶关-广州干线项目英德支干线环境影响报告书" (PDF). Guangdong Provincial Bureau of Ecology and Environment. 2020-12-01.{{cite web}}: CS1 maint: url-status (link)
  57. 57.0 57.1 "粤北天然气主干管网韶关-广州干线项目英德支干线环境影响报告书" (PDF). Guangdong Provincial Bureau of Ecology and Environment. 2020-12-01.{{cite web}}: CS1 maint: url-status (link)
  58. 58.0 58.1 [6], Guangdong Provincial Development and Reform Commission, Jun. 5, 2018, accessed Sep. 7, 2021.
  59. 59.0 59.1 [7], Sinopec News, Jan 7, 2021, accessed Sep. 7, 2021.
  60. 60.0 60.1 60.2 60.3 60.4 60.5 粤西天然气主干管网肇庆-云浮支干线项目 环境影响报告书 (送审稿), Environmental Impact Report (draft), Sep. 8, 2020, archived from the original on Sep. 2, 2021.
  61. "Guangdong Pipeline Network". Retrieved September 10, 2021.{{cite web}}: CS1 maint: url-status (link)
  62. Social stability risk survey announcement, Kaiping government website, accessed Sep. 2, 2021.
  63. 63.0 63.1 63.2 "2021工程"首个项目粤西天然气主干管网肇庆-云浮支干线项目正式具备投产条件, sohu.com, Oct. 1, 2020, accessed Sep. 2, 2021.
  64. 64.0 64.1 粤西天然气主干管网阳江-江门干线项目核准前公示, Guandong Provincial Development and Reform Commission, Aug. 30, 2018, accessed Sep. 2, 2021.
  65. 65.0 65.1 [8]
  66. 66.0 66.1 66.2 66.3 66.4 [9], Environmental Impact Assessment report, archived from [10] on Sep. 2, 2021.
  67. 67.0 67.1 67.2 67.3 67.4 67.5 67.6 Pre-approval Yangjiang LNG public announcement, yangjiang.gov.cn, Sep. 30, 2019, accessed Sep. 2, 2021.
  68. 68.0 68.1 广东省天然气管网肇庆-云浮支干线、揭阳-梅州支干线(揭阳-梅州段)一次性投产成功, 南方新闻网, 2022-09-30
  69. 粤西天然气主干管网茂名——阳江干线明年底通气 , sohu.com, May 10, 2020, accessed Sep. 2, 2021.
  70. "茂名市政府工作报告(2022年1月10日 庄悦群)_中国经济网——国家经济门户". district.ce.cn. 2022-2-11. Retrieved 2022-08-29. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  71. 粤西天然气主干管网台山段主体工程基本完成, Tasishan Municipal People's Government, Sep. 14, 2020, accessed Sep. 2, 2021.
  72. 72.0 72.1 72.2 Guangdong Yangjiang Hailing Bay LNG Co., Ltd., qcc.com, accessed Sep. 2, 2021.
  73. 73.0 73.1 73.2 73.3 [11], accessed Sep. 2, 2021.
  74. [12], gdee.gd.gov, accessed Sep. 2, 2021.
  75. "阳江LNG调峰储气库项目外输管道工程项目 环境影响评价信息首次公示-通知公告-广州粤宁环保科技有限公司". www.gd-eia.com. 2021-08-18. Retrieved 2021-09-23.{{cite web}}: CS1 maint: url-status (link)
  76. 深圳LNG外输管道安全顺利建成 中国石油新闻中心 June 8, 2020
  77. 深圳迭福、迭福北LNG接收站互联,跑步进入“全国一张网” China Gas, July 13, 2020
  78. 广东省生态环境厅关于中石油深圳液化天然气应急调峰站项目外输管道工程环境影响报告书的批复, 广东省生态环境厅, 2019-01-11
  79. 79.0 79.1 79.2 79.3 深圳LNG外输管道投产,实现了深圳等三大LNG与西二线的互联互通, 界面新闻, 2020-07-09
  80. 80.0 80.1 80.2 80.3 接收站及输气干线项目 广东大鹏液化天然气有限公司, July 6,2018
  81. 企业名片:中海油管道企业 中国管道保护网
  82. 油气管网设施运营企业基本情况 CNOOC, January 20, 2020
  83. 83.0 83.1 83.2 83.3 83.4 "河源市发展和改革局关于国家管网集团广东省天然气管网"县县通工程"河源-东源项目核准的批复-河源市人民政府门户网站". www.heyuan.gov.cn. 2022-02-09. Retrieved 2022-09-13.{{cite web}}: CS1 maint: url-status (link)
  84. 84.0 84.1 84.2 84.3 "广东省2022年重点建设项目计划表page 45" (PDF). 2022-3-17. {{cite news}}: Check date values in: |date= (help)
  85. 85.0 85.1 "环境信息公示平台". www.eiacloud.com. 2022-07-11. Retrieved 2022-09-13.{{cite web}}: CS1 maint: url-status (link)
  86. 86.0 86.1 86.2 86.3 86.4 86.5 "广东省生态环境厅关于国家管网集团广东省天然气管网"县县通工程"茂名-云安项目环境影响报告书的批复- 广东省生态环境厅公众网". gdee.gd.gov.cn. 2022-07-25. Retrieved 2022-09-13.{{cite web}}: CS1 maint: url-status (link)
  87. 87.0 87.1 开工!高州这个镇将建起联通茂名至云安的天然气管网, 南方报业,2023-05-07
  88. 广东省天然气管网 “县县通工程”,将会途径罗定! , 广东省天然气管网、 国家管网集团建设项目管理分公司, 2023-05-30
  89. 89.0 89.1 "梅州市生态环境局关于国家管网集团广东省天然气管网"县县通工程"梅州-蕉岭-平远项目环境影响报告书的批复" (PDF). 梅州市生态环境局. 2022-7-25. {{cite news}}: Check date values in: |date= (help)
  90. 90.0 90.1 梅州市发展和改革局关于国家管网集团广东省天然气管网“县县通工程”梅州-蕉岭-平远项目核准的批复, 梅州市人民政府, 2021-04-22
  91. 梅州-蕉岭-平远项目开工, 梅州日报, 2022-10-25
  92. 92.0 92.1 92.2 92.3 "梅州天然气管网"梅州-五华-兴宁"项目正式动工". www.xingning.gov.cn (in 中文). 2021-04-30. Retrieved 2022-09-13.{{cite web}}: CS1 maint: url-status (link)
  93. 梅州市发展和改革局关于国家管网集团广东省天然气管网“县县通工程”梅州-五华-兴宁项目核准的批复, 梅州市发展和改革局, 2021-04-15
  94. 94.0 94.1 94.2 94.3 "国家管网集团广东省天然气管网清禾专线项目穿越回兰明霞洞自然保护区生态风险评估公示 - 清新区政府门户网站 -http://www.qingxin.gov.cn/bmxz/bm/qxqlyj/qt/tzgg/content/post_1408854.html". www.qingxin.gov.cn. 2021-06-30. Retrieved 2022-09-14. {{cite web}}: External link in |title= (help)CS1 maint: url-status (link)
  95. 宏点网络网站管理系统|HDWS40.S0420.(074) (2022-1-27). "国家管网清禾专线项目第一道焊口开始焊接|行业动态|管道保护网". www.guandaobaohuchina.com (in 中文(中国大陆)). Retrieved 2022-09-14. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  96. 96.0 96.1 96.2 96.3 96.4 "梅州市人民政府门户网站 通知公告 国家管网集团广东省天然气管网"县县通工程"兴宁-和平-连平项目环境影响报告书(征求意见稿)公示". www.meizhou.gov.cn. 2022-07-12. Retrieved 2022-09-14. {{cite web}}: no-break space character in |title= at position 12 (help)CS1 maint: url-status (link)
  97. 97.0 97.1 97.2 97.3 "广东省生态环境厅关于国家管网集团广东省天然气管网珠中江干线项目环境影响报告书的批复- 广东省生态环境厅公众网". gdee.gd.gov.cn. 2022-08-01. Retrieved 2022-09-14.{{cite web}}: CS1 maint: url-status (link)
  98. 98.0 98.1 98.2 98.3 "国家管网集团广东省天然气管网珠中江干线项目环境影响评价公众参与说明" (PDF). June 2022.
  99. 广东省发展改革委关于国家管网集团广东省天然气管网珠中江干线项目核准的批复, 广东省发展和改革委员会, 2022-08-19
  100. 100.0 100.1 五建公司两大项目顺利开工,中国石化新闻网, 2022-04-22
  101. 101.0 101.1 101.2 101.3 广东省生态环境厅关于国家管网集团广东省天然气管网穗莞干线项目环境影响报告书的批复, 广东省生态环境厅,2022-11-23
  102. 102.0 102.1 102.2 国家管网集团广东省天然气管网穗莞干线项目环境影响报告书, 国家管网集团广东省管网有限公司, 2022-09
  103. "中国石化新闻网-- 中科炼化配套输气管道主干线进气点火". www.sinopecnews.com.cn. 2020-01-17. Retrieved 2022-09-16. {{cite web}}: line feed character in |title= at position 10 (help)CS1 maint: url-status (link)
  104. 104.0 104.1 104.2 104.3 104.4 104.5 "中科炼化一体化工程配套输气管道项目东兴支线全线贯通-国际燃气网". gas.in-en.com. 2021-12-21. Retrieved 2022-09-16.{{cite web}}: CS1 maint: url-status (link)
  105. 105.0 105.1 中科炼化一体化配套输气管道工程环境影响报告书审批前公示, 湛江市生态环境局, 2019-03-06
  106. 106.0 106.1 106.2 106.3 "中国石化新闻网-- 中科炼化配套输气管道主干线进气点火". www.sinopecnews.com.cn. 2020-01-17. Retrieved 2022-09-16. {{cite web}}: line feed character in |title= at position 10 (help)CS1 maint: url-status (link)

Related GEM.wiki articles

External resources

External articles

*add as many countries as the pipeline passes through